• Copy the reference
  • Tutorial video

Award

TABLE OF ABBREVIATIONS

AAD request Application for an Authorization for Foreign Currency Acquisition (Solicitud de Autorización de Adquisición de Divisas)
15 AAD requests or 15 AADs or Controverted AADs or AADs in dispute 15 AAD requests filed by Air Canada between September 2013 to January 2014 for ticket sales corresponding to October 2012 to December 2013 and for a total amount of approximately U.S.$ 50 million
Additional Facility Rules or AF Rules Rules Governing the Additional Facility for the Administration of Proceedings by the Secretariat of the International Centre for Settlement of Investment Disputes, 2006
AF Arbitration Rules Arbitration (Additional Facility) Rules
ALAV Venezuelan Airlines Association (Asociación de Líneas Aéreas de Venezuela)
ALD Authorization to Liquidate Foreign Currency (Autorización de Liquidación de Divisas)
ATA Air Transport Agreement between the Government of Canada and the Government of the Republic of Venezuela, signed in Caracas on 26 June 1990
BASSA Bassa Business, Aviation & Services, S.A.
BCV Central Bank of Venezuela (Banco Central de Venezuela)
BIT or Canada- Venezuela BIT Agreement between the Government of Canada and the Government of the Republic of Venezuela for the Promotion and Protection of Investments, signed in Caracas on 1 July 1996
CADIVI Commission for the Administration of Foreign Currency (Comisión de Administración de Divisas)
CENCOEX National Centre of Foreign Trade (Centro Nacional de Comercio Exterior)
Chicago Convention Chicago Convention on International Civil Aviation, signed on 7 December 1944
Civil Code Venezuelan Civil Code, published in Extraordinary Official Gazette No. 2.990, dated 26 July 1982
Claimant or Air Canada Air Canada Inc.
Designated Airlines Airlines designated under the ATA
DR-CAFTA Dominican Republic-Central America Free Trade Agreement
Exchange Agreement No. 1 Agreement entered into between the Ministry of Finance and the Central Bank on 5 February 2003
Exchange Agreement No. 2 Agreement entered into between the Ministry of Finance and the Central Bank on 9 February 2003
Forex Foreign exchange control
GSA Passenger General Sales Agreement between Air Canada and Business Aviation & Services, S.A. BASSA
IATA International Air Transport Association
ICJ International Court of Justice
ICSID International Centre for Settlement of Investment Disputes
ICSID Convention Convention on the Settlement of Investment Disputes between States and Nationals of Other States, 1965
ILC International Law Commission
ILC Articles International Law Commission’s Draft Articles on Responsibility of States for Internationally Wrongful Acts
INAC National Institute for Civil Aviation / National Institute for Civil Aeronautics (Instituto Nacional de Aviación Civil /Instituto Nacional de Aeronáutica Civil)
IVSS Venezuelan Institute for Social Security (Instituto Venezolano de los Seguros Sociales)
IVSS Certificates Certificates of Good Standing issued by the IVSS
LOPA Organic Law of Administrative Procedures (Ley Orgánica de Procedimientos Administrativos)
MFN Most Favored Nation
MPPDP Ministry of the Popular Power for the Office of the Presidency and Government Administration Oversight (Ministerio del Poder Popular del Despacho de la Presidencia y Seguimiento de la Gestión de Gobierno)
NAFTA North America Free Trade Agreement
NAFTA Interpretation NAFTA Notes of Interpretation of Certain Chapter 11 Provisions
Parties Air Canada and the Republic
PDVSA Petróleos de Venezuela, S.A.
Providencia No. 23 Providencia No. 23 issued by CADIVI, published in Official Gazette No. 37.667, dated 8 April 2003
Providencia No. 124 Providencia No. 124 issued by CADIVI, published in Extraordinary Official Gazette No. 6.122, dated 23 January 2014
RAV 108 Venezuelan Aviation Regulation No. 108 (Regulación Aeronáutica Venezolana)
RUSAD Users Registry of the Currency Administration System (Registro de Usuarios del Sistema de Administración de Divisas)
SICAD Alternative System for the Acquisition of Currency (Sistema Complementario de Administración de Divisas)
SOTI Sold Outside Ticked In
SOTI tickets Tickets ticketed in the Republic but sold outside of the Republic
Suspension Notice Air Canada's notice of suspension of its flights to Caracas dated 17 March 2014
The Republic or Venezuela The Bolivarian Republic of Venezuela
VCLT Vienna Convention on the Law of the Treaties
VEF Bolivar Fuerte
Toronto-Caracas- Toronto route Non-stop route between Lester B. Pearson International Airport in Toronto, Canada, and Aeropuerto Internacional de Maiquetía Simón Bolívar in Caracas, Venezuela, began in 2004

TABLE OF SUBMISSIONS AND TRIBUNAL DECISIONS

Request for Arbitration Request for Access to the Additional Facility and Request for Arbitration, dated 16 December 2016
PO No. 1 Procedural Order No. 1, dated 12 January 2018
Memorial Memorial on the Merits submitted by Air Canada, dated 22 March 2018
Application for Bifurcation Respondent’s Application for Bifurcation, dated 15 June 2018
Response to Application for Bifurcation Response to Respondent’s Application for Bifurcation, dated 28 June 2018
PO No. 2 Procedural Order No. 2, dated 10 July 2018
Counter- Memorial Counter-Memorial on Jurisdiction and Merits, dated 3 August 2018
PO No. 3 Procedural Order No. 3, dated 14 September 2018
PO No. 4 Procedural Order No. 4, dated 29 October 2018
PO No. 5 Procedural Order No. 5, dated 20 November 2018
PO No. 6 Procedural Order No. 6, dated 29 November 2018
Reply Reply Memorial on the Merits and Counter-Memorial on Jurisdiction submitted by Air Canada, dated 14 December 2018
PO No. 7 Procedural Order No. 7, dated 28 May 2019
Rejoinder Rejoinder on Jurisdiction and Merits submitted by the Bolivarian Republic of Venezuela, dated 25 October 2019
PO No. 8 Procedural Order No. 8, dated 24 February 2020
PO No. 9 Procedural Order No. 9, dated 3 April 2020
PO No. 10 Procedural Order No. 10, dated 7 July 2020
R-PHB Respondent’s Post-Hearing Brief, dated 5 June 2020
C-PHB Claimant’s Post-Hearing Brief, dated 5 June 2020
Reply R-PHB Respondent’s Reply Post-Hearing Brief, dated 14 September 2020
Reply C-PHB Claimant’s Reply Post-Hearing Brief, dated 14 September 2020
C-Costs Respondent’s Submission on Costs, dated 8 January 2021
R-Costs Claimant’s Submission on Costs, dated 8 January 2021

A. SUMMARY OF THE FACTS AND PROCEDURE

I. The Parties and other concerned entities

1.
Claimant is Air Canada Inc., a Canadian airline headquartered in Montreal, Canada ("Claimant" or "Air Canada").
2.
Air Canada has been a wholly private company since 1989 and is publicly traded on the Toronto Stock Exchange. It is one of the 20 largest airlines in the world, operating an average of 1,600 scheduled flights per day and flying directly to 222 airports around the world.1
3.
Respondent is the Bolivarian Republic of Venezuela ("Republic" or "Venezuela").
4.
Other entities concerned are the following:

(a) The Commission for the Administration of Foreign Currency or Comisión de Administración de Divisas ("CADIVI");

(b) The National Institute for Civil Aviation, later renamed National Institute for Civil Aeronautics ("INAC");

(c) The Venezuelan Airlines Association or Asociación de Líneas Aéreas de Venezuela ("ALAV");

(d) The International Air Transport Association ("IATA"); and

(e) Banco Mercantil, an exchange agency ("Banco Mercantil").

II. Overview of the factual background

5.
The following Section is a general summary of the facts of the dispute and does not purport to be exhaustive. To the extent that a more detailed statement of the essential facts is necessary, it is given in connection with the various claims and defenses.

1. Air Canada’s presence in Venezuela until 1 July 2004

2. The Venezuelan currency exchange regime

3. The filing of the Autorizacíon de Adquisición de Divisas

4. The suspension of Air Canada’s flights to Caracas

III. The arbitral proceedings

1. The commencement of the proceedings

35.
On 16 December 2016, Claimant filed with the International Centre for Settlement of Investment Disputes ("ICSID") a Request for Access to the Additional Facility and Notice of Arbitration, together with Exhibits C-1 to C-18 ("Request for Arbitration").
36.

On 13 January 2017, the ICSID Secretary-General approved access to the Additional Facility pursuant to Article 4 of the Rules Governing the Additional Facility for the Administration of Proceedings by the Secretariat of ICSID ("AF Rules") and registered the Request for Arbitration pursuant to Articles 4 and 5 of the Arbitration (Additional Facility) Rules ("AF Arbitration Rules").

37.

On 26 September 2017, ICSID notified the Parties of the constitution of the Tribunal and the commencement of the proceedings pursuant to Article 13 of the AF Arbitration Rules. The Tribunal is composed of Prof. Pierre Tercier (Swiss), President, appointed by the Chairman of the Administrative Council in accordance with Article 10 of the AF Arbitration Rules; Mr. Charles Poncet (Swiss), appointed by Claimant; and Ms. Deva Villanua (Spanish), appointed by Respondent.

38.

On 14 December 2017, further to the Parties’ agreement to extend the 60-day deadline provided for in Article 21 of the AF Arbitration Rules, the Tribunal held a First Session with the Parties by telephone conference.

39.
On 12 January 2018, the Tribunal issued Procedural Order No. 1 ("PO No. 1"). PO1 provided, inter alia, that the applicable AF Arbitration Rules would be those in force as of 10 April 2006; that the place of the arbitration proceeding would be Paris, France, and that the procedural languages would be English and Spanish.
40.
PO No. 1 also set out the Procedural Calendar. Pursuant to the Procedural Calendar, Respondent could file an Application for Bifurcation either before or with the filing of its Counter-Memorial.

2. The written procedure

41.
On 22 March 2018, Claimant filed its Memorial on the Merits ("Memorial"), together with two witness statements, one expert report, factual exhibits C-19 to C-101 and legal authorities CL-1 to CL-76.
42.
On 15 June 2018, Respondent filed its Application for Bifurcation ("Application for Bifurcation"), together with legal authorities RL-1 to RL-48.
43.
On 18 June 2018, the Tribunal invited Claimant to reply to Respondent’s Application for Bifurcation by 28 June 2018.
44.
On 28 June 2018, Claimant filed its Response to Respondent’s Application for Bifurcation ("Response to Application for Bifurcation"), together with factual exhibit C-102 and legal authorities CL-77 to CL-92.
45.
On 10 July 2018, the Tribunal issued Procedural Order No. 2 ("PO No. 2"), rejecting Respondent’s Application for Bifurcation. It also deferred to a later stage of the proceedings its decision on the Parties’ costs in connection with the Application for Bifurcation.
46.
On 3 August 2018, Respondent filed its Counter-Memorial on Jurisdiction and Merits ("Counter-Memorial"), together with two witness statements, one expert report, factual exhibits R-1 to R-46 and legal authorities RL-1 to RL-122.39
47.
On 10 August 2018, the Parties filed their document production requests in the form of Redfern Schedules.
48.
On 24 August 2018, the Parties filed their objections to the other Party’s document production requests and produced documents the request of which they did not object.
49.
Also on 24 August 2018, the Tribunal confirmed that, as agreed by the Parties, the language of the arbitration shall be only English, as opposed to English and Spanish as was originally foreseen in PO No. 1.
50.
On 31 August 2018, the Parties filed their replies to the objections to the other Party’s document production requests. With their replies, the Parties also set out their general remarks on the other Party’s document production requests and objections.
51.
On 14 September 2018, the Tribunal issued Procedural Order No. 3 ("PO No. 3") together with Annexes A and B, deciding on the document production requests. In PO No. 3, the Tribunal also directed the Parties as follows:

55. In relation to Claimant's Redfern Schedule:

a. Respondent shall confirm or clarify Claimant's understanding in relation to Claimant's Request No. 3 by 20 September 2018. Claimant shall reply, if needed, by 28 September 2018. The Tribunal shall decide, if necessary, by 5 October 2018(Claimant's Redfern Schedule, page 9, Request No. 3).

b. The Parties shall enter into a confidentiality agreement in relation to confidential documents responding to Claimant's Requests Nos 6, 14, 16, 23, 24, 25 and 26 by 20 September 2018(Claimant's Redfern Schedule, page 13, Request No. 6; pages 36-38, Requests Nos 23 to 25).

[...]

56. In relation to Respondent's Redfern Schedule:

a. Claimant shall, in relation to Respondent's Requests Nos 4 and 6, submit a privilege log in relation to documents that may be protected by legal privilege in line with the principles of Article 9(2)(b) and 9(3) of the IBA Rules by 20 September 2018. Respondent shall provide its comments to such log by 28 September 2018. The Tribunal shall decide by 5 October 2018(Respondent's Redfern Schedule, page 12, Request No. 4 and page 16, Request No. 6).

b. Claimant shall provide a list describing documents responsive to Respondent's Requests Nos 17, 18, 20, 21 and 22 that were already disclosed or shared with Respondent by 20 September 2018. Respondent shall reply, if needed, by 28 September 2018. The Tribunal shall decide, if necessary, by 5 October 2018(Respondent's Redfern Schedule, pages 33 to 35, Requests Nos 17 and 18; pages 37 to 39, Requests Nos 20 to 22).

c. Claimant shall respond to Respondent's explanations in relation to Respondent's Requests Nos 36 and 37 by 20 September 2018. Respondent shall reply, if needed, by 28 September 2018. The Tribunal shall decide, if necessary, by 5 October 2018(Respondent's Redfern Schedule, pages 55 to 57, Requests Nos 36 and 37).

[...]

57. For these reasons, the Tribunal orders the following:

[...]

4. The Parties shall take the necessary steps to comply with the Tribunal's directions set forth in paragraphs 55 and 56 above.

52.
On 19 and 20 September 2018, the Parties requested leave to address the Tribunal’s specific instructions under paragraphs 55 and 56 of PO No. 3 and to complete the production of documents. The Tribunal granted such leave on 21 September 2018.
53.
On 4 October 2018, the Parties made their respective submissions addressing the Tribunal’s directions set out in paragraphs 55 and 56 of PO No. 3
54.
On the same date, the Parties informed the Tribunal that they continued to negotiate a confidentiality agreement ("Confidentiality Agreement") pursuant to paragraph 55 of PO No. 3. The Parties confirmed that they would either provide to the Tribunal an executed version or seek the latter’s intervention if they could not reach an agreement.
55.
On 11 October 2018, the Parties informed the Tribunal that they had made progress in respect of the Confidentiality Agreement, but that they sought the Tribunal’s intervention on two matters on which they were still in disagreement. In the same communication, they enclosed the draft Confidentiality Agreement and noted that they would provide the Tribunal with their positions on the disputed points.
56.
On 12 October 2018, Respondent submitted its further position concerning the Tribunal’s directions of paragraph 56 of PO No. 3.
57.
On 15 October 2018, the Parties submitted their respective positions on the disputed points in the draft Confidentiality Agreement.
58.
On 24 October 2018, Claimant submitted its reply to Respondent’s position of 12 October 2018. It argued, among other things, that Respondent’s production of documents was deficient because it comprised of non-responsive, illegible, and duplicate documents. Claimant also argued that Respondent had not produced any documents issued or generated by its relevant government entities and that it had failed to produce any documents in response to Claimant’s Requests Nos 1 and 2. Claimant therefore requested the Tribunal to order Respondent to comply with PO No. 3 and to produce all documents responsive to Claimant’s requests.
59.
On 29 October 2018, the Tribunal issued Procedural Order No. 4 ("PO No. 4"), deciding on document production, including matters relating to the execution of the Confidentiality Agreement. Specifically, it decided the following:

51. For these reasons, the Tribunal orders the following:

[...]

2. Concerning the dispute resolution provision of the draft Confidentiality Agreement, the Tribunal invites the Parties to confer and agree on a text along Claimant’s proposal.

[...]

9. Respondent shall respond to Claimant’s objection on the alleged deficient production of documents by Respondent by 5 November 2018. The Tribunal will decide by 12 November 2018.

60.
On 4 November 2018, Respondent informed the Tribunal that it had fully complied with the document production ordered in PO No. 3. It also confirmed that, to the extent it identified any document responsive to Claimant’s requests which had not previously been produced during the pendency of the arbitration, it would produce such document. Moreover, it noted that it was conducting a detailed review and that it would be contacting counsel for Claimant directly with its particularized concerns.
61.
On 7 November 2018, the Tribunal took note of Respondent’s letter of 4 November 2018 and the fact that Respondent would contact Claimant to address any concerns. The Tribunal stated that it would decide if the Parties were unable to resolve the pending disagreements.
62.
On 12 November 2018, Claimant requested the Tribunal to resolve its application of 24 October 2018, concerning the alleged deficiency of Respondent’s document production. It also informed the Tribunal that the Parties had failed to agree on the dispute resolution provision of the Confidentiality Agreement pursuant to PO No. 4. Thus, Claimant submitted its proposal in an Annex and requested the following:

"that the Tribunal invites Venezuela to enter into the Confidentiality Agreement in the form attached hereto as Annex 2 by no later than November 16, 2018 and to order Venezuela to produce responsive documents that same date to avoid any further delay. In the alternative, and should Venezuela refuse to enter into the Confidentiality Agreement, Air Canada respectfully asks that the Tribunal enters into a confidentiality order in the same or similar terms to the ones contained in the Confidentiality Agreement. "

63.
On 13 and 14 November 2018, the Tribunal invited the Parties to comment on the other Party’s position concerning (i) the dispute resolution provision of the Confidentiality Agreement and (ii) the status of the Parties’ cooperation (if any) concerning the alleged deficiency of Respondent’s document production.
64.
On 16 November 2018, Claimant informed the Tribunal that it did not understand Respondent to offer to correct its deficient production of documents: while Respondent acknowledged its obligation of ongoing production of documents, Claimant had not received any supplemental production or indication that it would produce further documents. Further, concerning Respondent’s allegations on the supposed deficiencies in Claimant’s production, Respondent had not contacted Claimant to raise any issues.
65.
Also on 16 November 2018, Respondent noted that it had fully complied with the Tribunal’s decisions in PO No. 3 and PO No. 4. Specifically, its proposed dispute resolution provision for the Confidentiality Agreement was in line with Claimant’s proposal and satisfied the requirement of neutrality. By contrast, Claimant’s proposal did not reflect the Parties’ agreement on the draft Confidentiality Agreement as it was missing Respondent’s proposed edits concerning the number of arbitrators, the languages of the arbitration and the languages of potential evidence. Moreover, while noting that it could not consent to creating jurisdiction for this Tribunal under the Confidentiality Agreement, Respondent submitted its own proposal in an Annex and requested the following:

"that the Arbitral Tribunal (i) deny Air Canada's request of 12 November 2018 and (ii) declare that the Republic's proposed terms, as reflected in the Confidentiality Agreement in the form attached hereto as Annex 1 are reasonable and in accordance with the Arbitral Tribunal's directions set forth in P.O. No. 4."

Respondent also noted that it intended to contact Claimant concerning Respondent’s concern on the latter’s document production.

66.
On 20 November 2018, the Tribunal rendered Procedural Order No. 5 ("PO No. 5"), deciding, among other things, the following:

1. The Parties shall endeavour and enter into a Confidentiality Agreement in the terms proposed in para. 14 above, by 23 November 2018. Failing an agreement between the Parties, the Tribunal shall issue an order to this effect.

In paragraph 14 of PO No. 5, the Tribunal stated the following:

Accordingly, the Tribunal considers that, in line with its considerations of neutrality set out in PO No. 4, and in view of the Parties' positions, the appropriate dispute resolution provision of the Confidentiality Agreement should comprise the following elements:

- During the pendency of the present proceedings, any dispute concerning the Confidentiality Agreement shall be resolved by the present Tribunal;

- Following the end of the present proceedings, any dispute concerning the Confidentiality Agreement shall be resolved as follows:

Arbitration under the Rules of Arbitration of the International Chamber of Commerce;

Sole arbitrator;

French law;

English and Spanish language of the arbitration;

English and Spanish fluency of the sole arbitrator;

Documents in the arbitration may be submitted in their original language.

67.
On 23 November 2018, Respondent informed the Tribunal that it was not in a position to enter into a Confidentiality Agreement in the terms proposed by PO No. 5 because this would confer jurisdiction to the Tribunal.

For Respondent, neither of the Tribunal’s considerations in PO No. 5 took into account that the jurisdiction that would be created were to cover a potential liability claim against Air Canada for breach of contract under French law - clearly not a procedural matter. This was a distinct consent to the one allegedly given by the Republic under the BIT. The Republic would not be granting it freely were it to follow the Tribunal’s order.

Further, the Tribunal’s proposed procedural order was inadequate because it still left unanswered the question of the appropriate forum for the Republic’s potential action for a breach of confidentiality, and its confidential information was without protection upon termination of the arbitration.

68.
On 29 November 2018, the Tribunal issued Procedural Order No. 6 ("PO No. 6"), deciding on the confidentiality terms that would govern the production of documents, as set out in an Annex to said Order. It also ordered the Parties to:

"enter into enter into a Confidentiality Agreement by 3 December 2018 concerning only the timeframe following the termination of the present arbitration. The Confidentiality Agreement shall comprise the agreed text of the draft Confidentiality Agreement, including the dispute resolution provision providing for an ICC arbitration."

69.
On 14 December 2018, Claimant filed its Reply Memorial on the Merits and Counter Memorial on Jurisdiction ("Reply Memorial"), together with two witness statements, one expert report, factual exhibits C-34, C-35, C-64, and C-103 to C-160, and legal authorities CL-6 (updated), CL-52 (updated), and CL-93 to CL-135.
70.
On 12 February 2019, Respondent requested the suspension of the Procedural Calendar, specifically, the filing of its Rejoinder by the due date. Respondent based its request on the political situation in Venezuela at the time and the possible travel disruptions of Respondent’s expert to the country.
71.
On 15 February 2019, after being invited by the Tribunal to clarify its request, Respondent confirmed that it was requesting the stay of the entire proceeding.
72.
On 22 February 2019, Claimant commented on and objected to Respondent’s request for a stay.
73.
On 26 February 2019, the Tribunal granted Respondent an extension of one month to file its Rejoinder but rejected its request for a suspension or stay of the proceeding.
74.
On 28 March 2019, ICSID transmitted to the Tribunal and the Parties (i) a letter from Mr. José Ignacio Hernández G., Procurador Especial de la República Bolivariana de Venezuela, to ICSID, dated 27 March 2019, and (ii) a letter from ICSID to Mr. Hernández, acknowledging receipt of his correspondence, dated 28 March 2019 (both in the Spanish language).

In his letter, Mr. Hernández noted that the judicial representation of the Republic, including in arbitration proceedings, was vested exclusively on him, as Procurador Especial de la República. Consequently, any notice or communication from ICSID to the Republic had to be addressed to him and not to any other individual claiming to act on behalf of the Republic. In addition, ICSID should not consider valid any instruction or communication submitted as of 5 February 2019 by any other person that claims to act on behalf of the Republic.

75.
On 29 March 2019, Respondent renewed its requested for a stay of the proceedings and reiterated the circumstances preventing it from adequately preparing its Rejoinder. It also enclosed a letter from its economic expert explaining how the U.S. sanctions on Venezuela were impacting his ability to provide expert services in this arbitration.
76.
On 2 April 2019, the Tribunal invited Claimant to confirm whether it objected to Respondent’s request for a stay.
77.
On 3 April 2019, Claimant communicated its preliminary observations on (i) the letter of Mr. Hernández to ICSID, dated 27 March 2019, and (ii) Respondent’s request for a stay, dated 29 March 2019.

Claimant reiterated its objection to "an indefinite stay or suspension of the arbitration"" but suggested nonetheless that the Tribunal should extend the date by which Respondent would file its Rejoinder by six months and that new Hearing dates be fixed for the first quarter of 2020. Claimant suggested this course of action for the following reasons: (a) it was no longer clear who was empowered to represent Venezuela in this arbitration and Venezuela should be ordered to clarify this issue immediately through further submissions from Mr. Hernández and the De Jesús law firm; (b) Claimant would be prejudiced if the Hearing is maintained in the face of further delays from Venezuela and procedural surprises and uncertainty; and (c) the proposed six-month extension of the deadline for filing the Rejoinder would give Venezuela ample time to submit a competent legal opinion and retain a replacement expert if necessary.

78.
On the same date, the Tribunal informed the Parties that the deadline for Respondent’s Rejoinder had been now postponed and that it would communicate further instructions.
79.
On 4 April 2019, the Tribunal notified the Parties and Mr. Hernández its decision on (i) the suspension of the Procedural Calendar and (ii) the procedure to address the question of Respondent’s representation. Specifically, the Tribunal decided:

(a) to extend the filing of the Rejoinder by six months, i.e., 4 October 2019, and postpone the Hearing until the first quarter of 2020, respectively. The suspension of the Procedural Calendar would be subject to the procedure on the question of Respondent’s representation; and

(b) to address the question of Respondent’s representation as a preliminary matter via the filing of two rounds of submissions and, if necessary, a hearing on the matter, following which it would render its decision.

80.
On 5 April 2019, ICSID communicated to the Tribunal and the Parties (i) a letter from Mr. Reinaldo Enrique Muñoz Pedroza, Procurador General de la República, to ICSID (in the Spanish language), dated 4 April 2019, and (ii) a letter from ICSID to Mr. Muñoz Pedroza, acknowledging receipt of his correspondence, dated 5 April 2019.

Mr. Muñoz Pedroza, referred to the letter from Mr. Hernández to ICSID of 27 March 2019, and noted that arbitral tribunals did not have any authority or jurisdiction to question or decide on the functions or authority of the President or Attorney General. He contested the authority relied on by Mr. Hernández to present himself as Procurador Especial de la República. He concluded that the representation of the Republic’s interest before arbitral tribunals fell within the authority of the Republic’s Attorney General.

Mr. Muñoz Pedroza announced that he would issue instructions to the attorneys representing the Republic to request the dismissal in limine litis of the incident raised by the letter from Mr. Hernández for lack of jurisdiction or competence.

81.
On 8 April 2019, ICSID informed the Tribunal and the Parties that it had requested from Mr. Hernández and Mr. Muñoz Pedroza the English translations of their letters of 27 March 2019 and 4 April 2019, respectively. ICSID communicated the English translation of Mr. Muñoz Pedroza’s letter on 10 April 2019 and of Mr. Hernández’s letter (as well as of the Estatuto que Rige la Transición a la Democracia para Restablecer la Vigencia de la Constitución de la República Bolivariana de Venezuela, hereinafter the "Estatuto") on 12 April 2019.
82.
On 12 April 2019, following the Tribunal’s instructions of 4 April 2019, the Parties communicated their agreed revisions to the Procedural Calendar.
83.
On 16 April 2019, the Tribunal informed the Parties and Mr. Hernández that its decision of 4 April 2019 concerning the next steps on the question of Respondent’s representation was maintained.
84.
On the same date, the Tribunal amended the Procedural Calendar (on Jurisdiction and Merits), reflecting the Parties’ agreements that the filing of the Rejoinder would be due by 4 October 2019 and that the Hearing would take place on one of the following dates: 2-5, 3-6 or 10-13 March 2020.
85.
On 19 April 2019, the Parties and Mr. Hernández filed their comments on the question of Respondent’s representation in the form of letters and exhibits thereto.
86.
On 23 April 2019, the Tribunal reminded the Parties and Mr. Hernández of the deadline for the reply comments on the question of Respondent’s representation and asked them whether a meeting in persona or via video conference would be requested.
87.
On 29 April 2019, the Parties and Mr. Hernández filed their reply comments on the question of Respondent’s representation in the form of letters and exhibits thereto.

In reply to the Tribunal’s instructions of 23 April 2019, Claimant noted that no hearing was necessary but that a telephone or video hearing might suffice if the Tribunal believed that a hearing would be useful. Respondent also confirmed that no hearing was necessary. Mr. Hernández did not express any request in relation thereto.

88.
On 30 April 2019, the Tribunal informed the Parties and Mr. Hernández that it had decided not to hold a hearing on the representation issue.
89.
On 28 May 2019, the Tribunal issued Procedural Order No. 7 ("PO No. 7"), deciding that the proceedings would continue with the representatives of Respondent on record in this case.
90.
On 12 September 2019, Respondent requested a time-extension for the filing of its Rejoinder. Respondent referred to the issuance of Executive Order 13884 "Blocking Property of the Government of Venezuela" by the President of the United States of America on 5 August 2019 and noted that this measure impacted the Republic’s ability to finalize its Rejoinder, in particular from obtaining the economic expert report that was to accompany its submission.
91.
On 20 September 2019, following an invitation from the Tribunal, Claimant commented on Respondent’s further request for an extension of time to file its Rejoinder and urged the Tribunal to deny such request.
92.
On 26 September 2019, the Tribunal rejected Respondent’s request for an extension to file its Rejoinder. It also decided that Respondent could file its expert reports at any time up to one month before the Hearing so that Respondent could take the necessary measures to tackle any difficulties it still faced. Moreover, the Tribunal decided that it would deal with any procedural difficulties that could arise from such filing at a later stage of the proceedings. Finally, the Tribunal noted that the Hearing would take place as agreed.
93.
On 16 October 2019, Respondent sought another extension to file its Rejoinder by 31 October 2019.
94.
On 22 October 2019, following an invitation from the Tribunal, Claimant objected to Respondent’s request for an extension to file its Rejoinder.
95.
On the same date, the Tribunal granted Respondent an extension to file its Rejoinder by 25 October 2019.
96.
On 25 October 2019, Respondent filed its Rejoinder on Jurisdiction and Merits ("Rejoinder"), together with factual exhibits R-47 to R-91 and legal authorities RL-123 to RL-166.

3. The Hearing

97.
On 14 January 2020, the Parties notified the fact witnesses and experts they intended to cross-examine during the Hearing.
98.
On 21 January 2020, the Tribunal requested that the Parties liaise and attempt to agree on a Hearing schedule.
99.
On 29 January 2020, the Parties filed jointly a Hearing Schedule.
100.
On 3 February 2020, the Tribunal held a Pre-Hearing Conference Call with the Parties. During the Pre-Hearing Conference Call, the Parties confirmed their agreements on several items indicated in their joint Hearing Schedule. Respondent informed the Tribunal and Claimant that Dr. Flores, Respondent’s quantum expert, would not be available for examination during the Hearing due to the continuing effect of the U.S. sanctions. In this connection, the Parties presented their positions on the consequences of Dr. Flores’s absence, including the admissibility of his expert report, the time allocation to each Party during the Hearing, and the sequestration of Mr. Rosen, Claimant’s quantum expert. The Tribunal invited the Parties to indicate their respective positions in writing and that it would decide on this matter thereafter.
101.
On 4 February 2020, the Tribunal invited the Parties to discuss the questions of the admissibility of Dr. Flores’ report, of the influence on the sequestration, and of the allocation of Hearing time.
102.
On 10 February 2020, Respondent sent a letter to the Tribunal, arguing that Dr. Flores’s impossibility to participate in the Hearing affected, inter alia, the total time allocated to each Party at the Hearing: 60% for Respondent and 40% for Claimant, resulting in 7 hours allocated to Claimant and 10 hours to the Respondent with 2.5 hours reserved per Party for opening statements.

Respondent further argued that Dr. Flores was prevented from attending the Hearing due to unilateral and illegitimate U.S. sanctions and that the situation was beyond the control of Dr. Flores and the Republic. These "extraordinary circumstances" made his expert report of 3 August 2018 admissible.

Moreover, Dr. Flores’s "legitimate impossibility" to participate in the Hearing generated an imbalance between the Parties that required an adjustment of the rule of sequestration. Mr. Rosen should not be authorized to attend the Hearing prior to giving evidence and would be sequestered until he testified.

103.
On 17 February 2020, Claimant sent a letter to the Tribunal setting out its position in relation to Dr. Flores’s absence. Claimant argued that the Tribunal should not reward Respondent’s failure to present its quantum expert at the Hearing by allocating additional time to it for cross-examination. The Tribunal should maintain the 50/50 time allocation agreed between the Parties.

Claimant further argued that Dr. Flores’s expert report should be excluded or given no weight by the Tribunal. Specifically, Respondent had ample opportunity to support its case with an opinion from an expert who is not subject to such sanctions and could appear to defend his or her own report but had failed to do so.

In addition, Claimant’s quantum expert should not be sequestered or prevented from attending any other portions of the Hearing before he testifies. Sequestering Claimant’s expert would infringe on Claimant’s rights of defense.

104.
On 21 February 2020, the Parties communicated their list of participants to the Hearing.
105.
On 24 February 2020, the Tribunal issued Procedural Order No. 8 ("PO No. 8"), confirming the Parties’ agreement on the organization of the Hearing and deciding on the Parties’ disagreement in relation to Dr. Flores’s absence from the Hearing as follows:

[...]

The Tribunal decides that the equal allocation of time as originally agreed between the Parties shall be maintained. The fact that a witness or an expert will not attend the Hearing should not affect this repartition.

In any event, the time allocated will be applied with a good faith standard and will remain flexible generally and if technical delays and/or interruptions materially reduce a Party's allocated time.

[...]

The Tribunal decides that, in light of the exceptional circumstances, the expert report of Dr. Flores is admissible. However, it also notes that Respondent could have avoided the present procedural incident had it chosen an expert unaffected by the US sanctions. Therefore, when deciding on the evidentiary weight accorded to Dr. Flores' report, the Tribunal will take into consideration that Dr. Flores will not ratify its content, nor will it be subject to Claimant's cross-examination.

[...]

The Tribunal decides that, in order to avoid any imbalance between the Parties in their presentations and examinations, Mr. Rosen shall be sequestrated both during the opening statements and the witness examinations.

106.
On 2 March 2020, Respondent sent a letter to the Tribunal, referring to the COVID-19 outbreak across the world and requesting that the Tribunal reconsider the manner in which Respondent’s witnesses would be examined during the Hearing. Respondent suggested that the witnesses be examined via videoconference from Caracas and sought guidance from the Tribunal as to the procedural adjustments that could be required beyond the physical presence of such witnesses.
107.
On 3 March 2020, and after being invited by the President of the Tribunal to do so, Claimant noted that it would not oppose Respondent’s request in relation to the manner of hearing its own witnesses. In connection with the remaining participants to the Hearing, Claimant noted that, subject to the Tribunal’s views, it did not believe that any further procedural adjustments were necessary.
108.
On the same date, the Tribunal confirmed that Respondent’s witnesses would testify via videoconference and noted that the Hearing Schedule was maintained.
109.
On 6 and 7 March 2020, the Tribunal and the Parties exchanged further correspondence on the possible impact of the COVID-19 outbreak on the Hearing.
110.
On 7 March 2020, the Tribunal ultimately decided to maintain the Hearing but reserved the right to change its decision at any time in case circumstances required it to do so.
111.
Between 10 and 12 March 2020, a Hearing was held at the World Bank premises in Paris, France.

On Day 1, the Parties delivered their Opening Statements ("C-Opening" for Claimant and "R-Opening" for Respondent).

On Day 2, the examinations of Claimant’s witnesses, Mr. Alfredo Sebastián Babún Sabat and Mr. Alex Pittman, and Respondent’s witnesses, Mr. Yhonatan Rafael Blanco and Ms. Anira Dinorys Padrón Barito took place. As it had been agreed, the examinations of Mr. Blanco and Ms. Padrón took place via videoconference.

On Day 3, the examination of Claimant’s expert, Mr. Howard Rosen, took place. Further, the Tribunal and the Parties discussed certain procedural matters, in particular, the next steps of the proceedings.

112.
On 16 March 2020, the Tribunal sent a letter to the Parties, summarizing the decisions taken at the end of the Hearing in relation to the next steps of the proceedings.
113.
On 3 April 2020, the Parties communicated their agreed corrections to the Hearing transcript ("Tr. [date];[reference]").
114.
On the same date, the Tribunal issued Procedural Order No. 9 ("PO No. 9"), deciding on the content of the Parties’ Post-hearing Briefs, and providing a list of questions that the Parties should address in relation to jurisdiction, the merits and the quantum aspects of the case.

4. The steps following the Hearing

115.
On 2 June 2020, Claimant requested leave to submit three new legal authorities with its Post-Hearing Brief.
116.
On 4 June 2020, following an invitation from the Tribunal, Respondent objected to Claimant’s request of 2 June 2020.
117.
On the same date, the Tribunal decided to admit Claimant’s three additional legal authorities as follows:

1. In Procedural Order No. 9, the Tribunal noted that "[t]he Parties may not submit any new legal or factual exhibits (subject to Article 41(2)...)."

2. Article 41(2) of the Arbitration (Additional Facility) Rules provide that "[t]he Tribunal may, if it deems it necessary at any stage of the proceeding, call upon the parties to produce documents, witnesses and experts".

3. Claimant's request to file the three additional legal authorities for use in its Post- Hearing Brief is very belated. This is particularly so as Respondent's position on the lex specialis derogat a generali maxim has been pleaded in depth from the outset of the present case.

4. Nevertheless, because of the connection with the Tribunal's question in Procedural Order No. 9, the Tribunal decides to admit the three additional legal authorities.

5. To ensure equal treatment and no prejudice caused to Respondent, Respondent may, if it so requests, submit new legal authorities in response to Claimant's three additional legal authorities together with a short comment.

118.
On 5 June 2020, the Parties filed, simultaneously, their respective Post-Hearing Briefs ("C-PHB" and "R-PHB"). Claimant’s Post-Hearing Brief was accompanied by legal authorities CL-157 to CL-159 pursuant to the Tribunal’s decision of 4 June 2020.
119.
On 17 June 2020, the Tribunal acknowledged receipt of the Parties’ Post-Hearing Briefs and reminded them that, in case of need, either Party could make an application for a second round of Post-Hearing Briefs by 22 June 2020. The Tribunal also noted that it would pursue its deliberations and invited the Parties to liaise and agree on the format and procedure of the Statement of Costs.
120.
On 22 June 2020, Respondent requested the Tribunal (i) to exclude part of Claimant’s Post-Hearing Brief from the record; and (ii) leave to comment on the remaining parts of Claimant’s Post-Hearing Brief which was produced, according to Respondent, in breach of PO No. 9. In the alternative, were the Tribunal to deny its request, Respondent sought leave to comment on Claimant’s Post-Hearing Brief by 11 September 2020 and to produce additional legal authorities in connection with the issue of lex specialis and Claimant’s three new legal authorities.
121.
On 23 June 2020, Claimant confirmed that it would not request a second round of Post-Hearing Briefs. It nevertheless requested leave to respond to any submission from Respondent.
122.
On 24 June 2020, the Tribunal invited the Parties to comment, if they wished so, on the other Party’s communications of 22 and 23 June 2020.
123.
On 1 July 2020, Claimant requested the Tribunal, to deny Respondent’s requests of 22 June 2020 (see supra para. 120). Claimant also stated that "[i]f the Tribunal were somehow minded to give Venezuela a further opportunity to argue its case beyond simply submitting new legal authorities in response to Air Canada's three additional authorities together with "a short comment," Air Canada would request a right to respond."
124.
On 2 July 2020, Respondent confirmed that, "the Bolivarian Republic of Venezuela has no observation on Air Canada's decision not to answer the Republic's post-hearing submission."
125.
On 8 July 2020, the Tribunal issued Procedural Order No. 10 ("PO No. 10"), deciding as follows:

1. Paragraphs 100-153 of Claimant's Post-Hearing Brief are admissible.

2. Respondent shall have an opportunity to respond to paragraphs 100-153 of Claimant's Post-Hearing Brief as set out in the present Procedural Order (see para. 41).

3. Respondent shall have an opportunity to file a short comment with legal authorities as set out in the present Procedural Order (see para. 41). The possibility for a short reply from Claimant is reserved (see para. 30).

4. The Parties shall have an opportunity to file simultaneously Reply Post-Hearing Briefs by 11 September 2020 and in the manner explained in the present Procedural Order (see para. 41).

126.
On 11 September 2020, the Parties filed, simultaneously, their respective Reply Post-Hearing Briefs ("Reply C-PHB" and "Reply R-PHB").
127.
On 8 December 2020, the Tribunal informed the Parties that it was deliberating and preparing the Award. It invited the Parties to liaise and agree, if possible, on the format, procedure and timing for their Submissions on Costs. The Parties agreed to file them by 8 January 2021.
128.
On 8 January 2021, the Parties filed their respective Submissions on Costs ("C-Costs" and "R-Costs").
129.

On 12 August 2021, the Tribunal declared the proceedings closed pursuant to Article 44 of the AF Arbitration Rules.

B. LEGAL CONSIDERATIONS

I. In general

1. The arbitration agreement

130.

Claimant commenced the present arbitration against Respondent pursuant to the Agreement between the Government of Canada and the Government of the Republic of Venezuela for the Promotion and Protection of Investments ("BIT" or "Canada-Venezuela BIT"), signed on 1 July 1996 and in force since 28 January 1998, and the AF Rules.40

131.

Article XII of the BIT provides as follows:

1. Any dispute between one Contracting Party and an investor of the other Contracting Party, relating to a claim by the investor that a measure taken or not taken by the former Contracting Party is in breach of this Agreement, and that the investor or an enterprise owned or controlled directly or indirectly by the investor has incurred loss or damage by reason of, or arising out of, that breach, shall to the extent possible, be settled amicably between them.

2. If a dispute has not been settled amicably within a period of six months from the date on which it was initiated, it may be submitted by the investor to arbitration in accordance with paragraph (4). For the purposes of this paragraph; a dispute is considered to be initiated when the investor of one Contracting Party has delivered notice in writing to the other Contracting Party alleging that a measure taken or not taken by the latter Contracting Party is in breach of this Agreement, and that the investor or an enterprise owned or controlled directly or indirectly by the investor has incurred loss or damage by reason of, or arising out of, that breach.

3. An investor may submit a dispute as referred to in paragraph (1) to arbitration in accordance with paragraph (4) only if:

(a) the investor has consented in writing thereto;

(b) the investor has waived its right to initiate or continue any other proceedings in relation to the measure that is alleged to be in breach of this Agreement before the courts or tribunals of the Contracting Party concerned or in a dispute settlement procedure of any kind;

(c) if the matter involves taxation, the conditions specified in paragraph 14 of this Article have been fulfilled; and

(d) not more than three years have elapsed from the date on which the investor first acquired, or should have first acquired, knowledge of the alleged breach and knowledge that the investor has incurred loss or damage.

The dispute may, by the investor concerned, be submitted to arbitration under:

(a) The International Centre for the Settlement of Investment Disputes (ICSID), established pursuant to the Convention on the Settlement of Investment Disputes between States and Nationals of other States, opened for signature at Washington 18 March. 1965 (lCSID Convention), provided that both the disputing Contracting Party and the Contracting Party of the investor are parties to the ICSID Convention; or

(b) the Additional Facility Rules of ICSID, provided that either the disputing Contracting Party or the Contracting Party of the investor, but not both, is a party to the ICSID Convention; or

In case neither of the procedures mentioned above is available, the investor may submit the dispute to an international arbitrator or ad hoc arbitration tribunal established under the Arbitration Rules of the United Nations Commission on International Trade Law (UNCITRAL).

5. Each Contracting Party hereby gives its unconditional consent to the submission of a dispute to international arbitration in accordance with the provisions of this Article.

6. (a) The consent given under paragraph (5), together with either the consent given under paragraph (3), or the consents given under paragraph (12), shall satisfy the requirements for:

(i) written consent of the parties to a dispute for purposes of Chapter II (Jurisdiction of the Centre) of the ICSID Convention and for purposes of the Additional Facility Rules; and

(ii) an "agreement in Writing" for purposes of Article II of the United Nations Convention for the Recognition and Enforcement of Foreign Arbitral Awards, done at New York. June 10, 1958 ("New York Convention").

(b) The venue for any arbitration under this Article shall be such so as to ensure enforceability under the New York Convention, and claims submitted to arbitration shall be considered to arise out of a commercial relationship or transaction for the purposes of Article 1 of that Convention.

7. A tribunal established under this Article shall decide the issues in dispute in accordance with this Agreement and applicable rules of international law. An interpretation of this Agreement to which both Contracting Parties have agreed shall be binding upon the tribunal.

A tribunal may order an interim measure of protection to preserve the rights of a disputing party, or to ensure that the tribunal's jurisdiction is made fully effective, including an order to preserve evidence in the possession or control of a disputing party or to protect the tribunal's jurisdiction. A tribunal may not order attachment or enjoin the application of the measure alleged to constitute a breach of this Agreement. For purposes of this paragraph. An order includes a recommendation.

A tribunal may award, separately or in combination, only:

(a) monetary damages and any applicable interest;

(b) restitution of property, in which case the award shall provide that the disputing Contracting Party may pay monetary damages and any applicable interest in lieu of restitution.

A tribunal may also award costs in accordance with the applicable arbitration rules.

Where an investor brings a claim under this Article regarding loss or damage suffered by an enterprise the investor directly or indirectly owns or controls any award shall be made to the affected enterprise.

10. An award of arbitration shall be final and binding. Each Contracting Party shall provide for the enforcement of an award in its territory.

11. Nothing in this Article shall deprive a Contracting Party of its right to seek compliance by the other Contracting Party with its obligations under this Agreement, including through use of the procedures set forth in Articles XIII and XIV.

12. (a) Where an investor brings a claim under this Article regarding loss or damage suffered by an enterprise the investor directly or indirectly owns or controls, the following provisions shall apply:

(i) both the investor and the enterprise shall be required to give the consent referred to in subparagraph (3)(a);

(ii) both the investor and the enterprise must give the waiver referred to in subparagraph (3)(b); and

(iii) the investor may not make a claim if more than three years have elapsed from the date on which the enterprise first acquired, or should have first acquired, knowledge of the alleged breach and knowledge that it has incurred loss or damage.

(b) Notwithstanding subparagraph 12(a), where a disputing Contracting Party has deprived a disputing investor of control of an enterprise, the following shall not be required of the enterprise:

(i) the consent referred to in subparagraph (3)(a); and

(ii) the waiver referred to in subparagraph (3)(b).

13. Where an investor submits a claim to arbitration and the disputing Contracting Party alleges as a defense that the measure in question is

(a) a reasonable measure for prudential reasons of the kind referred to in Article X, or

(b) a measure to limit or prevent transfers by a financial institution under paragraph 6 of Article VIII, the tribunal, at the request of such Contracting Party, shall request both Contracting Parties to submit a joint report in writing as to whether the defence is a valid one in that particular case. The Contracting Parties shall consult through their financial services authorities on the matter.

The tribunal may proceed to decide the matter if it does not receive, within 70 days of its referral, either

(a) the joint report requested, or written notification that the matter has been submitted to arbitration between the Contracting Parties under Article XIV.

If the joint report or, as the case may be, the decision of the arbitral tribunal under Article XIV finds that the defence is valid, the tribunal shall be bound by this finding.

Tribunals for disputes on prudential issues and other financial matters shall have the necessary expertise relevant to the specific financial service in dispute.

14. Subject to Article XI, a claim by an investor that:

(a) a taxation measure of a Contracting Party is in breach of an investment agreement between the central government authorities of that Contracting Party and the investor, or

(b) a taxation measure of a Contracting Party constitutes an expropriation under of Article VII, may be subjected to arbitration under this Article unless the Contracting Parties, through the competent taxation authorities designated by each, determine jointly, within six months of being notified of the claim by the investor, that the measure in question, as the case may be, is not in breach of the investment agreement or does not constitute an expropriation.

(emphasis as in the original)

132.
Respondent contests the jurisdiction of the Tribunal. It submits, in the first place, that the present dispute arises from the Transport Agreement signed on 26 June 1990 between the Government of Canada and the Government of Venezuela ("ATA") and not from the BIT. According to the ATA, disputes are to be resolved by State-to-State negotiations. The relevant provision of the ATA, i.e., Article XVIII on "Settlement of Disputes", provides as follows:41

1. If any dispute arises between the Contracting Parties relating to the interpretation or application of this Agreement, the Contracting Parties shall endeavor to settle it by negotiations.

2. Such negotiations shall commence as soon as practicable but in any event not later than forty-five (45) days from the date of receipt of the request for negotiations, unless otherwise agreed by the Contracting Parties.

3. Failure to reach a satisfactory settlement within a further one hundred and eighty (180) days shall constitute grounds for the application of Article VII of this Agreement, unless otherwise agreed by the Contracting Parties.

133.
Also, Article VII of the ATA, on "Revocation and Limitation of Authorization", provides as follows:

1. The aeronautical authorities of each Contracting Party shall have the right to withhold the authorizations referred to in Article V of this Agreement with respect to an airline designated by the other Contracting Party, to revoke or suspend such authorizations or impose conditions, temporarily or permanently:

a) in the event of failure by such airline to qualify before the aeronautical authorities of that Contracting Party under the laws and regulations normally and reasonably applied by these authorities in conformity with the Convention;

b) in the event of failure by such airline to comply with the las and regulations of that Contracting Party;

c) in the event that they are not satisfied that substantial ownership and effective control of the airline are vested in the Contracting Party designating the airline or its nationals; and

d) in case the airline otherwise fails to operate in accordance with the conditions prescribed under this Agreement.

2. Unless immediate action is essential to prevent infringement of the las and regulations referred to above, the rights enumerated in paragraph 1 of this Article shall be exercised only after consultations with the aeronautical authorities of the other Contracting Party in conformity with Article XVI of this Agreement.

Respondent submits that, in the alternative, this Tribunal does not have jurisdiction as Claimant failed to meet the waiver and statutory period requirements of the BIT. In the further alternative, Respondent argues that Claimant failed to meet the requirements for the existence of an investor and an investment under the BIT. The Tribunal will discuss these objections further on (see infra paras 148 et seq.).

2. The constitution of the Tribunal

134.
The Tribunal was validly constituted on 26 September 2017 (see supra para. 37). The Parties did not object to the appointment of the Members of the Tribunal.42

3. The arbitral procedure

135.
The details of the arbitral procedure have been described above (see supra paras 1 to 129). The main steps can be summarized as follows:

- On 12 January 2018, the Tribunal issued PO No. 1, including the Procedural Calendar (see supra para. 39).

- On 10 July 2018, the Tribunal issued PO No. 2, denying Respondent’s Application for Bifurcation (see supra para. 45) because the objections to jurisdiction were intertwined with the merits of the case, and even if it were otherwise, it would not be more efficient in terms of time and cost to deal with those objections separately.

- On 13 September 2018, the Tribunal issued PO No. 3 on the Parties’ requests for production of documents (see supra para. 51).

- On 29 October 2018, the Tribunal issued PO No. 4 on matters relating to document production, including the execution of a Confidentiality Agreement (see supra para. 59).

- On 20 November 2011, the Tribunal issued PO No. 5 on further matters relating to the production of documents (see supra para. 66).

- On 29 November 2018, the Tribunal issued PO No. 6 on the confidentiality conditions that should apply to the production of documents (see supra para. 68).

- On 28 May 2019, the Tribunal issued PO No. 7 on the issue of Respondent’s legal representation in this case (see supra para. 89).

In reaching that decision, the Tribunal had to determine "whether it may continue the present proceedings with Respondent's interests being represented by Respondent's Counsel on record, who at least until 4 February 2019, were indisputably the valid representatives of Venezuela". It held that the dispute between the Parties over the representation of Respondent concerned a political and constitutional issue that was beyond the authority and jurisdiction of the Tribunal. Nonetheless, the Tribunal had the authority to decide whether or not it could proceed in the case with Respondent’s representative on record. The Tribunal found that it could do so in order to preserve the integrity of the arbitration and the interests of all Parties.

- On 24 February 2020, the Tribunal issued PO No. 8 on the organization of the Hearing and Dr Flores’ absence from that Hearing (see supra para. 105).

In particular, the Tribunal ruled that Dr Flores’ expert report would remain admissible, but that in deciding the evidentiary weight to be accorded to it, it would take into account the fact that Dr Flores would not corroborate its content or be subject to cross-examination by Claimant. The Tribunal specifically noted that Respondent could have avoided the present procedural incident by choosing an expert who was not affected by the U.S. sanctions.

Further, the Tribunal ruled that the equal allocation of time originally agreed upon by the Parties would be upheld and applied in good faith and with flexibility.

In addition, it ruled that Claimant’s quantum expert be sequestered to avoid an imbalance between the Parties in their presentations and examinations.

- Between 10 and 12 March 2020, a hearing was held at the World Bank’s premises in Paris (see supra para. 111).

- On 3 April 2020, the Tribunal issued PO No. 9 regarding the Post-Hearing Briefs, including questions posed by the Tribunal to the Parties (see supra para. 114).

- On 7 July 2020, the Tribunal issued PO No. 10 on certain issues relating to the Parties’ Post-Hearing Briefs (see supra para. 125).

136.
The Parties expressly acknowledged that they had no objection to the manner in which the proceedings were conducted.43

4. The Parties’ prayers for relief

4.1 Claimant

137.
In its final submission, Claimant requests the Tribunal to grant the following relief:44

[Claim. 1] a declaration that the dispute is within the jurisdiction of the tribunal;

[Claim. 2] a declaration that Venezuela has breached its obligations under the BIT and international law with respect to Air Canada's investments;

[Claim. 3] an order that Venezuela pay compensation to Air Canada for all damages suffered, plus pre-award compound interest up to February 29, 2020, in the amount of US$ 213,140,023 or, alternatively, in the amount of US$ 72,118,369;

[Claim. 4] an order that Venezuela additionally pay Air Canada pre-award compound interest calculated from March 1, 2020 until the date of the Tribunal's award using Venezuela's cost of borrowing or, alternatively, Air Canada's cost of debt;

[Claim. 5] an order that Venezuela additionally pay all of Air Canada's costs of this proceeding, including (but not limited to) Air Canada's attorney's fees, experts, and all costs associated with the tribunal and the conduct of the proceeding;

[Claim. 6] an order that Venezuela additionally pay Air Canada post-award compound interest calculated using Venezuela's cost of borrowing or, alternatively, Air Canada's cost of debt until the date of Venezuela's final satisfaction of the award; and

[Claim. 7] any other relief the Tribunal deems fit and proper.

4.2 Respondent

138.
Respondent’s prayers for relief in its Counter-Memorial are more detailed than those in its Rejoinder, Post-Hearing Brief and Reply Post-Hearing Brief. Therefore, the Tribunal will refer to the relevant versions in its analysis if it deems it necessary.
139.
In its final submission, Respondent requests that the Tribunal:45

[Resp. 1] Declare that the dispute is not within the jurisdiction of the Arbitral Tribunal and is, in any event, not admissible;46

[Resp. 2] Dismiss Air Canada's claims of liability under Articles II, VII and VIII of the Agreement between the Government of Canada and the Government of the Republic of Venezuela for the Promotion and Protection of Investments;47

[Resp. 3] Dismiss Air Canada's claim for compensation, as well as its claim for interest, or alternatively, reduce any amounts ordered as compensation on account of Air Canada's contributory fault, its unwise conduct or its improper actions;48

[Resp. 4] Order Air Canada to pay all costs incurred by the Republic in connection with this arbitration, including all of the Arbitral Tribunal's and ICSID's fees and expenses, and all legal fees and expenses incurred by the Republic (including but not limited to lawyer's fees and expenses);

[Resp. 5] Order Air Canada to pay interest as the Arbitral Tribunal may consider appropriate on the amounts owed to the Republic as from the date of the award on costs and complete payment; and

[Resp. 6] Order any additional measure it may deem appropriate.

5. Roadmap

140.
The Tribunal will proceed as follows:

- First, it will set out the law applicable to the present dispute (Section II).

- Second, it will rule on Respondent’s jurisdictional and admissibility objections (Section III).

- Third, to the extent that it finds it has jurisdiction over the present dispute, it will rule on Claimant’s claims on the merits, i.e., the alleged violations of the BIT (Section IV).

- Fourth, and to the extent it finds that Respondent breached the BIT, it will decide on issues relating to quantum (Section V).

- Firth, and in any event, the Tribunal will decide on the issue of costs of the arbitration (Section VI).

141.
Having carefully considered all the arguments and evidence presented by the Parties in the course of these proceedings, the Tribunal does not consider it necessary to repeat all of them in the Award. The Tribunal will address in its reasoning only the decisive factors necessary to rule on the Parties’ prayers for relief. When summarizing the Parties’ positions, the Tribunal reproduces the positions as they were presented in the first two rounds of submissions on jurisdiction and the merits; reference is made to all other submissions (including Post-Hearing Briefs) to the extent necessary for the Tribunal’s analysis.

II. Applicable law

142.
The Parties made certain arguments in the first round of their written submissions regarding the applicable law.49 Although the issue appears to become relevant if and after the Tribunal determines that it has jurisdiction, the Tribunal considers that it is appropriate to address it beforehand because the applicable law may also become relevant to the Tribunal’s assessment of its jurisdiction (see infra para. 146).
143.

The relevant provisions in relation to the applicable law in the present case are Article 54(1) of the AF Arbitration Rules and Article XII(7) of the BIT.

144.
Article 54(1) of the AF Arbitration Rules provides as follows:

The Tribunal shall apply the rules of law designated by the parties as applicable to the substance of the dispute. Failing such designation by the parties, the Tribunal shall apply (a) the law determined by the conflict of laws rules which it considers applicable and (b) such rules of international law as the Tribunal considers applicable.

145.
Further, Article XII(7) of the BIT provides as follows:50

A tribunal established under this Article shall decide the issues in dispute in accordance with this Agreement and applicable rules of international law. An interpretation of this Agreement to which both Contracting Parties have agreed shall be binding upon the tribunal. (emphasis as in original)51

146.

The Parties agree, and the Tribunal confirms, that in accordance with the foregoing provisions, the BIT itself and international law govern this dispute.52 However, the Parties appear to differ as to the application of Venezuelan law by this Tribunal. Specifically:

- Claimant points to the fact that the Vienna Convention on the Law of Treaties ("VCLT") provides that "treaties are governed by international law" and must be interpreted in light of "any relevant rules of international law". This makes international law supreme over domestic law in the area of state responsibility. This is also confirmed by the International Law Commission's Draft Articles on Responsibility of States for Internationally Wrongful Acts ("ILC Articles"). These rules, together with the BIT’s governing law provision, which does not mention domestic law, confirm that Venezuelan law may not be used by the Tribunal to determine the outcome of this dispute.53

- Respondent submits that that the Tribunal must indeed consider Venezuelan law when assessing Claimant’s claims, Respondent’s defenses and the conduct of both Parties, particularly with respect to civil aviation, labor law, exchange control, and administrative procedures, all matters governed by rules of Venezuelan law.54 In the present case, the "territorial nexus" is undeniable, as the BIT requires that the investment be made "in the territory of Venezuela".55 Moreover, Claimant was operating in an environment regulated by Venezuelan law, namely civil aviation. In conducting its business in the Republic, Claimant was also subject to Venezuelan labor regulations.56 The same is true of Claimant’s AAD requests, in the sense that they are also subject to Venezuelan law. Only by considering these provisions of Venezuelan law will the Tribunal be able to determine the proper scope and content of Claimant’s alleged "right to U.S. dollars". This is consistent with the position taken by numerous arbitral tribunals.57

147.
The Tribunal agrees with Respondent. Domestic law, in this case Venezuelan law, "is likely [to be] relevant" to the determination of the claims and defenses at hand.58 This being said, the role of domestic law is not to be confused with that of the BIT and/or international law. In particular, it is not part of the regime governing the present dispute (see supra para. 146). Instead, it must be considered from a factual perspective in order to determine, where appropriate, the scope and extent of the rights and obligations of the Parties alleged to give rise to the existence of an "investment" for jurisdictional purposes, as well those alleged to give rise to the claims on the merits.59

III. Jurisdiction and Admissibility

1. The issue

148.
The issue is whether this Tribunal has jurisdiction over the present dispute and whether the claims are admissible.
149.
Respondent requests that the Tribunal "[d]eclare that the dispute is not within the jurisdiction of the Arbitral Tribunal and is, in any event, not admissible" [Resp. 1] (see supra paras 138 and 139).60 Specifically, that:

- "the dispute is not within the jurisdiction of the Arbitral Tribunal because the dispute is governed by and must be resolved as per the terms of the ATA";

- "the dispute is not within the jurisdiction of the Arbitral Tribunal or is inadmissible because: i. Claimant has not complied with the waiver requirement of Article XII(3)(b) of the BIT, and/or ii. Claimant has referred the dispute to arbitration after the expiry of the three year statutory period of Article XII(3)(d) of the BIT";

- "the dispute is not within the jurisdiction of the Arbitral Tribunal because Claimant does not meet the ratione materiae and/or ratione personae requirements of Article I of the BIT".61

150.
Claimant requests that the Tribunal find that "the dispute is within the jurisdiction of the tribunal" [Claim. 1] (see supra para. 137).62
151.
The Tribunal recalls that it is constituted in accordance with the BIT and the AF Rules. Its jurisdiction should therefore in principle be determined only by reference to the criteria set out in the BIT and the AF Rules.63 In the present case, however, Respondent contests the appropriateness of the BIT forum for the present dispute and, more specifically, whether it is affected by the ATA forum. In these circumstances, the Tribunal must first assess whether the present dispute is appropriately brought before it before considering if necessary, whether the jurisdictional requirements are met.64
152.
The Tribunal is therefore concerned with the following questions:

- First, whether the ATA exclusively governs the present dispute (see infra Section 2).

- Second, and if necessary, whether an arbitration agreement has been reached under the BIT (see infra Sections 3 and 4); and/or

- Third, and if necessary, whether Air Canada qualifies as a protected investor that has made a protected investment within the meaning of the BIT (see infra Section 5).

2. Objection to jurisdiction based on the ATA

2.1 The Parties ’ positions

(i) Respondent

153.
Respondent submits that the ATA is the lex specialis applicable to this dispute to the exclusion of the BIT.65
154.
According to Respondent, Claimant invokes the BIT when it needs to resort to arbitration, and the ATA when it needs to substantiate its claims.66 As such, Claimant’s case is nothing more than an ATA claim disguised as a BIT claim.67 In fact, Claimant’s alleged protected investment under the BIT has only one source: the ATA.68 Further, each of Claimant’s alleged claims point to the ATA.69
155.
Claimant is mistaken that (i) the BIT is the lex specialis applicable to the dispute and governs, as such, jurisdictional issues, and (ii) the rules contained in the ATA are "applicable rules of international law" in the meaning of Article XII(7) of the BIT and as such may supplement the BIT.70
156.
The lex specialis maxim seeks to resolve a situation where there is a conflict of norms, by ruling that the special norms should apply instead of the general ones.71 In absence of any express exclusion of "aviation industry investors" from the scope of the BIT, the ATA and the BIT prima facie both provide protection to Claimant. However, they also provide for conflicting dispute settlement mechanisms.72 While the ATA provides that disputes must exclusively be resolved through State-to-State negotiations, the BIT only offers an option for the investor to refer the dispute to arbitration.73
157.
Further, the ATA already regulated the operation of airlines such as Air Canada for six years prior to the signature of the BIT. Moreover, as evidenced by official statements of the Legal Bureau of Department of legal Affairs of Canada of 1990, both Canada and Venezuela were aware that more specific treaties prevail over the general ones such as the BIT.74
158.
Therefore, the Tribunal must apply the lex specialis maxim in order to first determine whether the ATA prevails over the BIT.75 This determination requires the analysis of (i) the subject-matter of the studied norms and (ii) the number of actors whose behavior is regulated.76 Respondent makes seven comparisons between the two instruments in this connection that confirm that the ATA has a more specific subject-matter than the BIT and that it specifically protects designated airlines, such as Claimant (i.e., in relation to the objective, scope, regulation of behavior of actors, subject-matter, reference to domestic law, MFN clause and national treatment clause).77 In this connection, Respondent replies to Claimant’s defense as follows:

- It is evident that the ATA and the BIT are international bilateral treaties entered into between the same parties, i.e., Venezuela and Canada.78 Respondent does not agree with Claimant that in order for the lex specialis principle to apply, parties to the conflicting norms must be the same.79

- The subject matter of a treaty is defined by its general scope. It does not depend on the typology of the specific substantive provisions but on the situations regulated by such provisions. The ATA, which regulates the activity of and offers protection to "aviation industry investors", overlaps with the BIT that, in essence regulates and offers protection to investors in general, including, prima facie, those of the aviation industry.80 In any event, the lex specialis applies even in the absence of a conflict between the subject matter of the ATA and the BIT.81

159.
Even if the Tribunal were to accept that for the principle to apply there must be some inconsistency between the ATA and the BIT, the MFN, national treatment, free transfer of funds, as well as the dispute resolution clauses of the ATA and the BIT are inconsistent with each other.82
160.
The relevant question is not whether specific provisions are similar but whether the ATA and the BIT are in conflict.83 Article XVIII of the ATA covers all disputes arising out of the interpretation and application of that treaty, including any grievance that one of the beneficiaries of the ATA may have against either Venezuela or Canada. Air transportation carriers have always resorted to their home sovereigns to resolve disputes arising out of air transportation agreements.84 Thus, the ATA cannot be deemed to be silent on the question of the resolution of disputes arising between the airlines designated thereunder and one of its member States. Instead, such disputes are to be resolved at the inter-State level through State-to-State negotiation.85
161.
In the present case, neither the BIT nor the ATA contain a rule resolving the conflict between the two treaties. This is where the lex specialis doctrine plays its role. Accepting Claimant’s argument that just because nothing in the ATA prevents it from bringing claims before this Tribunal in relation to the rights and protection it has under the ATA would amount to (i) simply negating the lex specialis principle used by Claimant itself and (ii) permitting shopping by any interested party amongst conflicting treaties.86
162.
The Tribunal should therefore decline its jurisdiction in light of the more "special" procedure to which Venezuela and Canada agreed in the ATA.87

(ii) Claimant

163.

Claimant submits that the ATA cannot and does not deprive the Tribunal of its jurisdiction under Article XII of the BIT.88

164.

First, the BIT is the lex specialis applicable to the dispute and governs therefore jurisdictional issues.89 The Tribunal’s jurisdiction is to be determined solely by reference to the criteria set forth in the BIT, which Claimant has satisfied.90 Claimant has not asserted any claim under the ATA. Instead, it relies on the ATA primarily to provide factual context and background for its claims under the BIT. Article XII(7) of the BIT positively requires this Tribunal to "decide issues in dispute in accordance with [the BIT] and applicable rules of international law". These international rules necessarily include the ATA.91

165.

Second, if Canada and Venezuela had wanted to exclude investments by designated airlines under the previously signed ATA or aviation generally from the scope of the BIT’s protections, including its investor-state dispute resolution provisions, then they could have done so, just as they expressly excluded investments in "cultural industries" from protection. Indeed, Canada and Venezuela were clearly mindful of the aviation sector when they entered into the BIT, because they specifically excluded third-party bilateral agreements relating to aviation from the scope of certain protections contained in Article II(3) and Article III(1) and (2) of the BIT.92

166.
Third, it is well-established that the principle lex specialis applies only where the parties and the subject-matter of conflicting norms are identical. Here neither the parties nor the subject-matter of treaties is identical. Claimant alleges breaches by Respondent of the investment protections contained in the BIT, including its provisions governing FET and expropriation. The ATA does not contain such investment protection provisions.93 In addition, Article XII of the BIT covers disputes between different parties and concerning different subject-matters than Article XVII of the ATA. This is not an inter-State dispute between Venezuela and Canada relating to the interpretation or application of the ATA. Even though the ATA contains free transfer rights and obligations that are similar to those in the BIT, a dispute arising under the latter is different from a dispute concerning the interpretation and application of the former, most notably because the parties are different.94 Moreover, there is no indication that Venezuela or Canada intended the ATA to limit or otherwise curtail a designated airline's legal rights to those found in the ATA, to the exclusion of any other rights it might have under domestic or international law.95
167.
Fourth, pursuant to the ILC Articles, for the lex specialis principle to apply there must be some actual inconsistency between the two provisions. Dispute settlement mechanisms are considered inherently cumulative in nature in the absence of a clear indication that they were intended to be exclusive. Thus, even if Claimant were a party to the ATA, it would not be precluded from bringing arbitration under the BIT, absent express language in either treaty to the contrary.96

2.2 The Tribunal’s analysis

(i) The issue

168.
The issue is whether the present dispute is governed exclusively by the ATA so that it must be resolved in accordance with the dispute settlement provision contained therein (see supra paras 153, 162, 163, 164).
169.
First, the Tribunal notes that in its Post-Hearing and Reply Post-Hearing Briefs, Claimant developed in detail its defense to Respondent's jurisdictional objection under the ATA and in particular the lex specialis argument. Specifically, Claimant further developed its arguments97 and sought to present new legal authorities on the issue,98 which the Tribunal admitted into the record (see supra para. 117). Respondent indicated that it disagreed, arguing that Claimant had "used its Post-Hearing Brief to present a fully new case [...] and adduced new authorities of its choice", that "these limitations undoubtedly generate a procedural unfairness to the detriment of the Republic, in breach of the principle of equal treatment" and that "[t]he fact that the Republic was provided with an opportunity to respond to Air Canada's new case is not sufficient to cure this procedural unfairness".99
170.
The Tribunal considers that Claimant could indeed have developed such arguments at a much earlier stage in these proceedings. At the same time, it cannot overlook the fact that, following the Hearing, the Tribunal asked specific questions about jurisdiction and, in particular, about Respondent’s objection under the ATA which may have guided Claimant’s recent and more elaborate position.
171.
Second, the Tribunal considers that it has given both Parties an equal and sufficient opportunity on this point. In particular, it has also granted Respondent the right to address new and more detailed arguments and even to submit legal authorities with its Reply Post-Hearing Brief. Nonetheless, the Tribunal will address Respondent’s jurisdictional objection under the ATA by reference to the Parties submissions up to the Hearing (including oral testimony). This does not mean that the Tribunal will not consider the Parties’ Post-Hearing Briefs in this regard. Instead, to the extent that new avenues are developed or explored with respect to this objection, the Tribunal will consider them only if they are sufficiently presented by both Parties and to the extent necessary for the Tribunal to resolve this issue under the law applicable in this case.
172.
In any event, the main question to be answered by the Tribunal is Respondent’s question whether the Tribunal lacks jurisdiction because the allegedly applicable lex specialis governing the dispute, the ATA, does not contain an arbitration agreement.100 Therefore, the Tribunal will address this issue as follows:

- First, it will set out the principle of lex specialis (Section (ii)).

- Second, it will analyze whether the principle of lex specialis applies by examining the "competing" treaties, i.e., the ATA and the BIT (Section (iii)).

- Third, it will examine whether the ATA supersedes the BIT in the present case, in the event that the lex specialis principle is applicable, or otherwise (Section (iv)).

- Finally, it will conclude (Section (v)).

(ii) The lex specialis principle

173.
The Parties dispute the relevance, applicability, and scope of the lex specialis maxim to the present dispute.101
174.
The Tribunal notes that, contrary to Respondent’s submission, the Parties do not agree on the appropriateness of the lex specialis principle for determining the Tribunal’s jurisdiction. Indeed, Claimant stated during the Hearing that the principle does not apply. The Parties also disagree on the requirements of the principle itself. Therefore, in order to determine whether the principle is relevant in this case, it is important for the Tribunal to understand the function and scope of the principle.
175.

According to the Report of the Study Group of the ILC on the "Fragmentation of international law: Difficulties arising from the diversification and expansion of international law" - an authority relied upon by Respondent102 - the lex specialis maxim in international law functions as follows:

- As Respondent submits, the maxim, that "suggests that if a matter is being regulated by a general standard as well as a more specific rule, then the latter should take precedence over the former", is both a "maxim of legal interpretation of a conflict and a technique for the resolution of normative conflicts".103

- As such, the Report clarifies that "[t]he relationship between the general standard and the specific rule may, however be conceived in two ways": (i) where the specific rule should read and understood within the confines or against the background of the general standard, typically as an elaboration, updating or a technical specification of the latter";104 (ii) "where two legal provisions that are both valid and applicable, are in no express hierarchical relationship, and provide incompatible direction on how to deal with the same set of facts. In such a case, lex specialis appears as conflict-solution technique." In both cases, primacy falls on the "special" provision.105

- The Report adds, however, that "the maxim does not admit of automatic application". In this context, there are the following two sets of difficulties: "First, it is often hard to distinguish what is "general" and what is "particular" and paying attention to the substantive coverage of a provision or to the number of legal subjects to whom it is directed one may arrive at different conclusions. An example would be provided by a relationship between a territorially limited general regime and a universal treaty on some specific subject. Second, the principle also has an unclear relationship to other maxims of interpretation or conflict-solution techniques such as, for instance, the principle lex posterior derogate legi priori (later law overrides prior law) and may be offset by normative hierarchies or informal views about "relevance" or importance."106 (emphasis added)

- Indeed, "lex specialis is usually discussed as one factor among others in treaty interpretation (articles 31-33 VCLT) or in dealing with the question of successive treaties (article 30 VCLT, especially in relation to the principle of lex posteriori)"107 It may operate "(a) within a single instrument; (b) between two different instruments; (c) between a treaty and a non-treaty standard and (d) between two non-treaty standards".108 "Inasmuch as "general law" does not have the status of jus cogens, treaties generally enjoy priority over custom and particular treaties over general treaties".109

- Further, "[a] rule is never "general" or "special" in the abstract but in relation to some other rule" and "[a] rule may be general or special in regard to its subject-matter (fact description) or in regard to the number of actors whose behavior is regulated by it."110 (emphasis added)

- With respect to specificity in relation to the "subject-matter", "lex specialis can only apply where both the specific and general provisions concerned deal with the same substantive matter". This is in line with Article 55 of the ILC Articles.111 However, "the criterion of the "same subject-matter" as a condition for applying a conflict rule is too unspecific to be useful" and "[d]ifferent situations may be characterized differently depending on what regulatory purpose one has in mind".112

- In this regard, the Report refers to the ILC's explanation in its commentary on the drafting of Article 55 which states that "[f]or the lex specialis principle to apply it is not enough that the same subject matter is dealt with by two provisions; there must be some actual inconsistency between them, or else a discernible intention that one provision is to exclude the other".113 (emphasis added)

176.
The Tribunal can, therefore, infer the following from the foregoing in the context of the present case.
177.
First, the present case concerns two different and successive instruments, namely (i) the ATA, concluded between Canada and Venezuela in 1990,114 and (ii) the BIT, signed between Canada and Venezuela in 1996 and in force since 1998.115
178.
Second, the lex specialis functions both as a rule of interpretation and as a conflict of laws rule. In the present case, Respondent refers to the primacy of the ATA and the incompatibility of the dispute settlement clauses of the ATA and the BIT: the clauses allegedly provide incompatible direction on how to deal with Claimant's claims. As such, if applicable, the lex specialis can only become relevant here as a conflict rule.
179.
Third, and in any event, the lex specialis principle is not automatically applicable. The Tribunal must first "distinguish what is 'general’ and what is 'particular'". This distinction cannot be made in the abstract; rather, the Tribunal must look at the relevant subject matter and the actors whose conduct is to be regulated. This is consistent with Respondent's position that the subject matter and the number of actors whose behavior is regulated are the relevant criteria.116
180.
Fourth, and with respect to subject matter, the Tribunal considers that in order to properly assess the relevant subject matter in the present case, it must consider both the overall subject matter of the instruments and that of the allegedly conflicting norms. In the present case, this means the subject matter of the ATA and the BIT as well that of their dispute settlement provisions.
181.
Fifth, and in relation to the relevant actors, again the Tribunal finds it pertinent to see the relevant actors in each respect, that is, with respect to the Treaties themselves and with respect to their respective dispute resolution provisions.
182.
Finally, and in any event, it is of paramount importance for the application of the principle that there is an actual contradiction or intention that one instrument or provision excludes the other. In this regard, the Tribunal must evaluate other considerations in its analysis, such as, for example, the wording of the instruments and the intent of the Contracting Parties, if any can be inferred.

(iii) The ATA and the BIT

a. In general

183.
Having set out the relevant principles in the context of the lex specialis maxim and in the context of the present case, the Tribunal will examine the "competing" instruments in light of these principles.
184.
It is recalled that the present case concerns the ATA, concluded between Canada and Venezuela in 1990, and the BIT, signed between Canada and Venezuela in 1996 and in force since 1998 (see supra para. 177). While the instruments are consecutive, and Claimant only argues in its Post-Hearing Brief that lex specialis must be considered even in the midst of related principles such as lex posterior derogate priori found in Article 30(3) VCLT, Respondent objects, inter alia, that this argument is new.117 Indeed, no such principle was raised by Claimant in its earlier submissions.118 However, the Tribunal notes that the lex posterior principle is part of the international law applicable in this case through Article XXI(1) of the BIT. It may therefore take it into account only to the extent necessary and only if Respondent has adequately responded to Claimant’s submissions in this regard in its Reply Post-Hearing Brief (see also the Tribunal’s reasoning supra at paras 169-171).
185.

Similarly, in its Post-Hearing Brief, Claimant develops the argument that it is clear from the text of the BIT itself that Canada and Venezuela had a common intention to apply the BIT and in particular Article XII of the BIT, to investors in the aviation sector.119 Respondent challenges the correctness of this argument.120 The Tribunal reiterates its above considerations on its approach (see paras 169-171 and 184) and emphasizes that an interpretation of the instrument on which it is based, including the intention of the relevant signatory parties, when its jurisdiction is challenged is an exercise it must undertake in any case, including on its own motion, in order to comply with its mandate.

b. The ATA

186.

With regard to the ATA, the Tribunal observes the following:

- Its purpose is set forth in its preamble, which states that the Contracting Parties "[d]esir[ed] to conclude an agreement supplementary to the [Convention on International Civil Aviation, i.e., the Chicago Convention] for the purpose of establishing commercial air services".121 Further, Article II on the "Applicability of the Chicago Convention" states that the ATA "shall be subject to the provisions of the Chicago Convention to the extent that these provisions are applicable to international air services’".122 At this point, it is important to note that the Chicago Convention is a multilateral treaty concluded for the purpose of agreeing "on certain principles and arrangements in order that international civil aviation may be developed in a safe and orderly manner and that international air transport services may be established on the basis of equality of opportunity and operated soundly and economically".123 In the context of its purpose, the ATA grants each Contracting Party "the right to designate an airline or airlines to operate the agreed services on the specified routes".124

- In the context of the substantive rights of designated airlines, Article XXI provides that "[e]ach designated airline shall have the right to engage in the sale of air transportation in the territory of the other Contracting Party" and "the right to convert and remit to its country on demand earnings obtained in the normal course of its operations [...] at the foreign exchange market rates for current rates prevailing at the time of the transfer [...] in accordance with national legislation […] under legislative and regulatory conditions no less favourable than those applied to any other foreign airline operating international air services to and from the territory of the other Contracting party".125

- In the context of procedural rights in general, Article XVIII, set out above (see para. 133), provides for settlement by negotiation in the event of disputes "between the Contracting Parties relating to the interpretation or application" of the ATA.126 If no satisfactory settlement is reached within 180 days, and unless the Contracting Parties agree otherwise, Article VII applies.127 Article VII, also set out above (see para. 134), provides for the possibility for the aeronautical authorities of the Contracting Parties to refuse operating licenses in respect of certain airlines if those airlines fail to comply with certain laws or regulations or "operate in accordance with the conditions prescribed under the" ATA.128 In addition, according to Article XXIII, any Contracting Party may "give notice in writing through diplomatic channels to the other Contracting Party of its decision to terminate" the ATA.129

187.
Thus, in the context of the ATA, the following can be deduced:

- Its purpose is to develop and establish commercial air services in a bilateral context, subject to and in addition to the Chicago Convention. Air Canada, as the designated airline for Canada, plays an indispensable role in the establishment of such services. As such, the ATA, like the Chicago Convention, provides certain rights and obligations for the designated airlines. Thus, the ATA governs the conduct of three actors, namely the Contracting States and the respective designated airline through the assurance of the Contracting States.

- In the event of a dispute between Canada and Venezuela over the interpretation and application of the ATA, such dispute can be referred to negotiations. In the event that no satisfactory agreement is reached between Canada and Venezuela, the appropriate aeronautical authority may revoke the designated airline’s authorization if it fails to comply with the relevant laws or the ATA. Negotiation is thus only provided as a State-centric remedy130 and apparently only when the designated airline is in the wrong. The designated airline certainly has no right to bring a claim, or no right to do so without the proxy of its State. Even if such a claim were made and successful, the ATA does not provide for any monetary compensation to the designated airline itself.

c. The BIT

188.
In relation to the BIT, the Tribunal finds the following:

- Its purpose is set out in its first and second preambles. According to its first preamble, the BIT "establishes the framework for cooperation in the cultural, economic and technological fields between them".131 According to its second preamble, the BIT "recognizes that the promotion and the protection of investments of investors of one Contracting Party in the territory of the other Contracting Party will be conductive to the stimulation of business initiative and to the development of economic cooperation between them".132

- The BIT provides, inter alia, the following relevant substantive protections: Article II(2) provides for "fair and equitable treatment" of investments or returns of investors.133 Article III prohibits the expropriation of investors’ investments or returns unless certain conditions are met.134 Article VIII protects the investor’s "unrestricted transfer of investments and returns", "without delay in the convertible currency in which the capital was originally invested or in any other convertible currency agreed by the investor and the Contracting Party concerned" and "[u]nless otherwise agreed by the investor", "at the rate of exchange applicable on the date of the transfer". This protection is subject, inter alia, to "the equitable, non-discriminatory and good faith application" of certain laws of the Contracting Party.135

- The BIT also provides for the following procedural safeguards: In the context of a dispute between an investor and a Host Contracting Party "relating to a claim by the investor that a measure taken or not taken by the [...] Contracting Party is in breach of [the BIT]", Article XII already outlined above (see para. 132) provides for the possibility of investor-state arbitration. In deciding the dispute, the investor-state tribunal "shall decide the issues in dispute in accordance with this Agreement and applicable rules of international law" and is bound by an interpretation of the BIT contained in an annex.136 In the context of a dispute between the Contracting Parties over the "interpretation or application" of the BIT, Article XIV provides for amicable settlement through consultations followed by arbitration.137

- The interpretation of the BIT, agreed to by the Parties in an Annex that forms "an integral part" of the BIT,138 provides the following with respect to certain exceptions to the protection of the BIT: Pursuant to Article II(4) of the Annex, Article II(3) and Article III(1) and (2) of the BIT, "do not apply to treatment by a Contracting Party pursuant to any existing or future bilateral or multilateral agreement: [...] (b) relating to aviation; telecommunications transport networks and telecommunications transport services; fisheries, maritime matters, including salvage; or financial services" (emphasis added). Pursuant to Article III(8) of the Annex, Articles II, III, IV and V of the BIT and the related provisions of the Annex "do not apply to (a) procurement by a government or state enterprise [...]; (b) subsidies or grants [...]; (c) any measure denying investors [...] and their investments any rights […] provided to the aboriginal peoples of either country; or (d) any current or future foreign aid program [...]". According to Article III(9) of the Annex, "[i]nvestments in cultural industries are exempt from the provisions" of the BIT.

189.
In the context of the BIT, therefore, the following can be deduced:

- Its purpose is to develop economic cooperation in general at the respective bilateral level. An important way to achieve this is through the promotion and protection of investment. In terms of content, the BIT is therefore entirely focused on the rights and obligations of the Contracting State vis-à-vis the investor of the other Contracting State. As such it primarily regulates the conduct of these two actors.

- Procedurally, the Tribunal envisages two options: first, the possibility of arbitration where there is a dispute between the investor and the host State over the investment as defined by the BIT itself; second, any dispute over the interpretation and application of the BIT, to be resolved by negotiation and then by arbitration at the inter-State level.

- Disputes relating to the cultural industries appear to be excluded from the BIT's protections. Disputes over treatment under a bilateral agreement relating to the aviation sector are excluded only to the extent set out in Article II(4) of the Annex to the BIT.

d. The application of the lex specialis

190.
It follows from the above conclusions on the ATA (see supra para. 187) and on the BIT (see supra para. 189) that, contrary to Respondent's view,139 there is not or cannot be any overlap between the ATA and the BIT.
191.
First, the subject-matters of the ATA and of the BIT are generally different. The ATA deals with the establishment of relationships between commercial airlines in accordance with the principles and agreements of the Chicago Convention (see supra para. 186). The BIT, on the other hand, deals with the protection of investors who have made an investment for the purpose of developing economic cooperation in general (see supra para. 188). It does not deal with the legal regulation of cross-border air operations when such operations are directly related to an air carrier's investment in the destination State. However, the BIT requires that such operations, to the extent that they qualify as an investment, be treated in a specific manner.
192.
Moreover, the subject-matter of the dispute settlement provision of the ATA does not overlap with that of the BIT. While the latter aims to provide the investor with an opportunity for financial redress in the form of a private lawsuit, the former does not provide for such an opportunity. Instead, the ATA provides for negotiations between states. If no settlement or agreement is reached after such negotiations, the only consequence appears to be the revocation of the airline's operating authorization or the termination of the ATA, both at the option of the state designating the airline. If anything, the dispute settlement clause of the BIT may overlap with that of the ATA if disputes arise over the interpretation or application of the ATA (see infra para. 195). There is therefore nothing to compensate the airline as a private actor or investor in the event of a complaint. For this reason, the Tribunal does not consider relevant any argument that:

- Aviation disputes are resolved through state-to-state negotiation and there are no arbitrations involving air transportation.140

- The BIT provides an optional dispute settlement clause, while the ATA provides a mandatory clause.141

- The ATA provides substantive protections for the designated airlines that are inconsistent with the protections for investors set forth in the BIT.142

193.
Similarly, it does not consider it necessary to address Claimant’s new argument on the principle of harmonization in this context,143 or Claimant’s lex posterior argument under Article 30 VCLT, or any investment arbitration jurisprudence interpreting and applying this provision (see supra para. 184).144
194.
Regardless, it is emphasized that the fact that two treaties - in this case the ATA and the BIT - may apply to the same facts, does not imply their subject matter is the same.
195.
Second, the ATA regulates the conduct of states, which in turn control the conduct of their national carriers through the agreement in the ATA. This means that it is the states themselves that bear the consequences when these carriers misbehave. Rather, the BIT regulates the conduct of the states towards the investor of the other state. Thus, it is either the host state or the investor that bears the consequences of applying the BIT. The home State is not regulated and bears consequences for the conduct of its national investor in the host state. Again, and at best, the BIT also raises the possibility of interstate negotiation on the interpretation and application of the BIT for the sole purpose of defining standards of investment protection that are to the benefit of both states.
196.
Third, the Tribunal sees no discernible intention from the Contracting Parties to the BIT to exclude investments in the aviation industry from the scope of the BIT and thus to make the ATA the proper and sole forum in relation thereto. It is true that the Contracting States Parties to the BIT excluded the application of Articles II(3) and III(1) and (2) to treatment under an existing bilateral agreement relating to aviation. The relevance of this exclusion to the present case has no bearing on the jurisdiction of the Tribunal. If anything, it is a question of admissibility and is relevant only if there are claims under those provisions, which there are not in this case. That is not the case with respect to investments in cultural industry, where the parties have expressly stipulated an exception in that regard. As to its authority in relation to the ATA,145 the Tribunal refers to its reasoning in paragraph 202 below.
197.
Accordingly, the Tribunal is not of the opinion that this is a situation where there is a general and a specific treaty or general or specific provisions therein providing for different directions. As such, there can be no inconsistency and the principle of lex specialis principle cannot be applied.
198.
For the same reasons developed above, Respondent’s argument that lex specialis applies even in the absence of a conflict146 has no merit.

(iv) Does the ATA supersede the BIT in the present case?

199.
Having found that the lex specialis does not apply to the present case, the Tribunal will examine whether the ATA still supersedes the BIT.
200.
First, the Tribunal has already examined the BIT and the ATA. It did so in the context of the examination of the lex specialis principle and having regard to the wording of the instruments, as well as any related agreements. The Tribunal found no overlap between the subject matters of the two instruments or between their respective dispute settlement provisions. It also found no conflict or discernible intent to exclude the aviation industry from the scope of the BIT.
201.
Second, the Tribunal does not find that its conclusions in the context of the lex specialis examination are influenced by the facts presented by Respondent regarding the Parties’ position and practice with respect to the ATA. Specifically:

- The fact that Air Canada participated in the negotiations147 is not relevant to its possible status as an investor bringing a private claim for pecuniary loss under a different instrument.

- The fact that the ATA had already governed the operations of airlines such as Air Canada six years prior to the signing of the BIT148 has no bearing on Canada’s and Venezuela’s express intention to have investment-related disputes, including those involving their commercial airlines, settled by arbitration under the BIT.

- The official statements of the Legal Bureau of Legal Affairs of Canada in 1990149 show no intention to make the ATA relevant to an investment dispute in the manner advocated by Respondent.

- Air Canada’s 10 December 2013 email referencing the Embassy of Canada in Venezuela addressing the issue of repatriation of funds under the ATA150 does not negate the fact that Air Canada had or has the ability to pursue investor-state claims through the BIT. Nor does the view expressed by INAC and ALAV view in a letter to Air Canada dated 19 March 2014 on the application of the ATA.151

202.
Equally, there is no merit in Respondent’s argument that a refusal by this Tribunal to give effect to the ATA will nullify the ATA and deprive it of any purpose.152 Neither does the contention that there are no prior Tribunals that have entertained claims by airlines, given that such claims require the authority of the airlines' states.153 The Tribunal has already found on the basis of the wording of the relevant Treaties, that this is not the case in the present dispute (see supra paras 183-189). Instead, it is clear to the Tribunal it that the ATA becomes relevant and vital to the present dispute by Article XII(7) of the BIT, which requires this Tribunal to "decide issues in dispute in accordance with [the BIT] and applicable rules of international law". There is no question that the Chicago Convention provides for the establishment of bilateral relations on the regulation of the aviation sector and establishment of commercial airline activities. There is also no question that the ATA itself explicitly affirms that it stands to complement the Chicago Convention itself. There is therefore no doubt that the ATA falls within the international law reference of Article XII(8) of the BIT. Therefore, consideration of the substantive provisions of the ATA would not be impermissible in this case.
203.
The Tribunal therefore reiterates that neither the wording nor the purpose of the two Treaties, nor any purported intention of the States concerned or of the Parties, lead to the conclusion that there is a conflict between them such that the ATA would override the BIT in a case such as the present.

(v) Conclusion

204.
Based on the foregoing, the Tribunal concludes that Respondent’s objection to jurisdiction based on the ATA is dismissed.

3. Objection to jurisdiction based on the waiver provision of the BIT

3.1 The Parties ’ positions

(i) Respondent

205.

Respondent submits that paragraph 43 of the Request for Arbitration does not meet the waiver requirement of Article XII(3)(b) of the BIT and, in the alternative, that Claimant has failed to comply with its own waiver.154

206.

First, a good faith interpretation in accordance with the ordinary meaning of the language "dispute settlement procedure" of Article XII(3)(b) of the BIT in the context of dispute resolution encompasses non-adversarial mechanisms such as negotiation.155 Respondent points to the negotiation references in Article XII(1) of the BIT and Article XVIII of the ATA in support of its position that negotiation is a dispute settlement procedure and was considered as such by Venezuela and Canada at the time the BIT was entered into.156

207.
There can be no controversy as to the good faith and ordinary meaning of "dispute settlement procedure of any kind" which may only be constructed as inclusive of all kinds of dispute settlement procedures.157 Nothing indicates that Venezuela and Canada intended to ascribe any other meaning to those terms than their ordinary one. An interpretation that encompasses negotiation is in line with the letter and spirit of Article XII of the BIT. Allegedly protected investors must waive their rights to negotiate a dispute in order to be allowed to refer the same dispute to arbitration in circumstances where arbitration is only meant to be initiated in case negotiation fails.158 Further, the only thing that such a waiver prevents is cumulating arbitration with any other kind of dispute settlement mechanism.159
208.
Claimant’s most recent submission is a clear, unequivocal and express recognition that it never intended to waive such a right because it does not and did not consider at the time it issued its waiver that "negotiation" was a dispute resolution procedure encompassed by Article XII(3)(b). Therefore, Claimant cannot be deemed to have waived such a right through paragraph 43 of its Request for Arbitration.160
209.
Second, and in the alternative, if the Tribunal were to find that Claimant formally waived its rights to any kind of dispute settlement procedure and not just to "legal actions" at paragraph 43 of its Request for Arbitration, Respondent maintains that Claimant has failed to comply with the waiver requirement in breach of the BIT.161
210.
Claimant does not deny having been involved in negotiations relating to the measures alleged to be in breach of the BIT; such negotiations were engaged or continued by the ALAV, the Venezuelan Airlines Association, with officials of the Republic and with other international airlines directly and/or through IATA, both after the Request for Arbitration was filed.162
211.
Claimant must therefore be deemed to have directly or indirectly continued, after the submission of the Request for Arbitration, to take part into negotiations in relation to the measures allegedly contravening the BIT, therefore multiplying parallel dispute resolution procedures, which is precisely what the waiver requirement of the BIT precludes.163

(ii) Claimant

212.
Claimant submits that it waived its right to initiate or continue any other proceedings under Article XII(3)(b) of the BIT in paragraph 43 of its Request for Arbitration.164
213.
The first prong of Article XII(3)(b) focuses on formal proceedings before Venezuela’s domestic courts, while the second prong focuses on other dispute proceedings.165 In this way, Article XII(3)(b) guarantees against the possibility of duplicative proceedings and inconsistent judgments in multiple fora. In this connection, Claimant points to the explanation of the tribunal in Supervision v. Costa Rica that the point of these type of waiver provisions is to "avoid the duplication of procedures and claims, and therefore to avoid contradictory decisions".166
214.
Paragraph 43 of the Request for Arbitration unequivocally confirmed that Claimant had not commenced either of the types of proceeding described in Article XII(3)(b) and that it waived to do so in the future. Further, Claimant confirmed the broad scope of that waiver again in its Response to the Application for Bifurcation.167
215.
Respondent’s position is also inconsistent with its prior arguments regarding the interpretation of Article XII(3)(b) in other disputes brought under the BIT.168
216.
There is no basis therefore for the argument that the second prong of Article XII(3)(b) encompasses non-adversarial proceedings. Such interpretation would bar any attempts at amicable dispute resolution, an illogical result because a party cannot be compelled to settle and there is no risk that amicable settlement talks will lead to a contrary binding decision or to double recovery, the concerns that underlie the requirement for waivers in bilateral investment treaties. Such interpretation would also be impossible to define as it would preclude assertions of rights, requests to comply, exchanges between parties or discussion, thereby effectively preventing recourse to the BIT’s dispute resolution provisions.169
217.
Concerning the negotiations through the IATA and ALAV on which Respondent relies, Claimant submits that Respondent has inaccurately described the nature of these events as neither of these negotiations constitute proceedings for the purposes of Article XII(3)(b). Negotiations which are no more than discussions are not legal proceedings.170
218.
Consequently, Respondent’s waiver objection must be dismissed.171

3.2 The Tribunal’s analysis

(i) The issue

219.
The issue is whether Claimant has complied with the waiver requirement of Article XII(3)(b) of the BIT so that this Tribunal has jurisdiction to decide the dispute before it or that the claims are admissible (see supra paras 205 and 212).

The Tribunal will address this issue as follows:

- First, it will set out Article XII(3)(b) of the BIT and determine its scope (Section (ii)).

- Second, it will assess whether Claimant has complied with said provision (Section (iii)).

- Finally, it will conclude (Section (iv)).

(ii) Article XII(3)(b) of the BIT

220.

The Parties disagree on whether Article XII(3)(b) of the BIT includes non-adversarial measures such as negotiations.172 To decide this question, the Tribunal will set out Article XII in full and then determine the scope of the provision.

221.
First, Article XII of the BIT, which deals with the "Settlement of Dispute between and Investor and the Host Contracting Party" (already set out supra para. 131), provides in the relevant part the following:

1. Any dispute between one Contracting Party and an investor of the other Contracting Party, relating to a claim by the investor that a measure taken or not taken by the former Contracting Party is in breach of this Agreement, and that the investor or an enterprise owned or controlled directly or indirectly by the investor has incurred loss or damage by reason of, or arising out of, that breach, shall to the extent possible, be settled amicably between them.

2. If a dispute has not been settled amicably within a period of six months from the date on which it was initiated, it may be submitted by the investor to arbitration in accordance with paragraph (4). For the purposes of this paragraph, a dispute is considered to be initiated when the investor of one Contracting Party has delivered notice in writing to the other Contracting Party alleging that a measure taken or not taken by the latter Contracting Party is in breach of this Agreement, and that the investor or an enterprise owned or controlled directly or indirectly by the investor has incurred loss or damage by reason of, or arising out of, that breach.

3. An investor may submit a dispute as referred to in paragraph (1) to arbitration in accordance with paragraph (4) only if:

[...]

(b) the investor has waived its right to initiate or continue any other proceedings in relation to the measure that is alleged to be in breach of this Agreement before the courts or tribunals of the Contracting Party concerned or in a dispute settlement procedure of any kind;

[...] (emphasis added)

222.

The Tribunal must interpret this provision in accordance with the rules of treaty interpretation set forth in Article 31 of the VCLT173 and, "in good faith in accordance with the ordinary meaning to be given to the terms of the treaty in their context and in the light of its object and purpose".174 For the purposes of interpretation, the "context" includes the text, the preamble of the Treaty and its Annexes, and matters referred to in Article 31(1)(a) and (b) of the VCLT. In addition, the Tribunal "must take into account together with context: (a) any subsequent agreement between the parties regarding the interpretation of the treaty or the application of its provisions"175 In addition, the Tribunal may have recourse to "supplementary means of interpretation, including the preparatory work of the treaty and the circumstances of its conclusion, in order to confirm the meaning resulting from the application of Article 31, or to determine the meaning when the interpretation according to Article 31: (a) leaves the meaning ambiguous or obscure; or (b) leads to a result which is manifestly absurd or unreasonable".

223.

The BIT imposes certain conditions on Respondent’s consent to arbitrate claims under the BIT. This follows from the wording of Article XII(3)(b) that the investor, in this case allegedly Air Canada, may submit its claims to arbitration "only if" it "has waived its right to initiate or continue any other proceedings in relation to the measure that is alleged to be in breach of this Agreement before the courts or tribunals of the Contracting Party concerned or in a dispute settlement procedure of any kind" (emphasis added).

224.
Accordingly, the so-called "waiver" provision, is a condition of Respondent’s consent to arbitration. It is therefore a precondition to the jurisdiction of the Tribunal.
225.
Second, as Respondent correctly submits, the waiver requirement has a formal and a material aspect.176
226.

The formal aspect requires that, in the same way that a claimant must satisfy the procedural and jurisdictional requirements in its Request for Arbitration, it must do so with respect to the waiver requirement, i.e., the existence of a conforming written waiver.177 Accordingly, Claimant in the present case, must provide a written waiver of "its right to initiate or continue any other proceedings in relation to the measure that is alleged to be in breach of this Agreement before the courts or tribunals of the Contracting Party concerned or in a dispute settlement procedure of any kind".

227.
The material aspect requires that a claimant has not actually initiated or continued such proceedings, i.e., the investor’s compliance with the waiver. Unlike the formal aspect of the requirement, compliance with this requirement requires proof of the negative or proof of absence. The Tribunal therefore considers that compliance with the formal requirement also requires an intent on the part of a claimant to have complied with the material requirement. It is at this moment, that the respondent party must prove the non-fulfilment of the material aspect, in which case the burden shifts.
228.
Third, as to the scope of the waiver requirement, the Tribunal considers the following:

- The phrase "any other proceedings in relation to the measure that is alleged to be in breach of this Agreement" includes proceedings commenced or continuing at the time of the filing of the Request for Arbitration and during the pendency of the arbitration. The temporal scope of the requirement therefore includes the period during which the alleged breach is filed and pursued.

- The purpose of the waiver provision is to protect a respondent State from having to defend itself in multiple fora with respect to the same measure and to minimize the risk of inconsistent decisions and double recovery with respect to such measure.178

- While the Parties agree on the meaning of "the courts or tribunals of the Contracting Party concerned", i.e., the first part of the provision per Claimant, they disagree on the meaning of "in a dispute settlement procedure of any kind", i.e., the second part of the provision.179 It is true that "negotiations" between the Parties in an attempt to reach settlement of a dispute with respect to a measure alleged to be in violation of the BIT can in principle be categorized as "dispute settlement procedures".180 If anything, the subsequent term "any kind" expands the category of dispute settlement procedures. However, this category cannot include a procedure that has no third-party adjudicator or neutral, such as the "negotiation process" alleged in the present case.181 Further, it cannot include a procedure the result of which can be complied with by a party at its choice.182 To hold otherwise would be contrary to the purpose of the waiver provision. Further, it would mean that every time the parties to an arbitration agreement enter into good faith negotiations to resolve their dispute, the tribunal must automatically find that it lacks jurisdiction or that it loses its jurisdiction. In such a case, the parties themselves - and in particular the claimant - would do their utmost not to engage in any settlement options.

229.
It would therefore appear that the second part of Article XII(3)(b) does not cover negotiations, but a procedure in which Respondent defends itself against a binding result in a dispute with Claimant concerning the measures alleged to have violated the BIT.

(iii) Has Claimant complied with Article XII(3)(b)?

230.
The Tribunal refers to paragraph 43 of Claimant’s Request for Arbitration, which states as follows:

In accordance with Article XII(3)(a) of the BIT, Air Canada consented to arbitration in its notice letter of June 15, 2016, and it does so here again. In regard to Article XII(3)(b), Air Canada has not commenced any other proceedings in relation to the measures of Venezuela that are at issue in this dispute, and it expressly waivers its right to initiate any such proceedings. (emphasis added)

231.

The Tribunal finds that Claimant has satisfied the formal requirement of the waiver provision of Article XII(3)(b) by making the foregoing statement. The statement is clear and unambiguous. The fact that Claimant did not reproduce the entire text of the provision to include its two parts and the possible procedures waived is not relevant. Claimant’s express reference to Article XII(3)(b) and its intent to waive "proceedings" is sufficient.

232.
With respect to Respondent’s assertion that documentary evidence produced by Claimant confirm that it participated in at least two third-party dispute settlement procedures after the alleged waiver was made,183 the Tribunal notes the following.

- Concerning the "Application of IATA for Approval and Antitrust Immunity of Certain Discussions" of 28 April 2016,184 this procedure does not fall within the scope of Article XII(3)(b). This is because the application was made by a party other than Claimant and has the negotiation features that the provision excludes. In this regard, the Tribunal agrees with Claimant that the Application does not involve Claimant’s assertion of any action or claims against Venezuela before any court, tribunal, or similar forum, but instead is a request by a third party trade association to the U.S. authorities to "meet and discuss joint courses of action" rather than an impermissible dispute settlement proceeding.185

- Concerning the December 2017 meeting between representatives of ALAV - of which Claimant is a member - with the Ministry of Popular Power for Foreign Trade and International Investment of Venezuela and the General Director of INAC to discuss the "repatriation of the outstanding amounts of the airlines",186 this "procedure" does not fall within the scope of Article XII(3)(b). For the same reasons as with the IATA Application, and as Claimant correctly submits, this meeting of a third-party industry group does not constitute the assertion by Claimant of separate formal actions or claims against Venezuela before a court, tribunal or similar forum.187

233.
As a result, Claimant has also not violated the material requirement of Article XII(3)(b).
234.
Accordingly, Claimant has not breached the waiver provision of the BIT.

(iv) Conclusion

235.
Based on the foregoing, the Tribunal concludes that Respondent’s objection to jurisdiction based on the waiver is dismissed.

4. Objection to jurisdiction based on the time-bar provision of the BIT

4.1 The Parties ’ positions

(i) Respondent

236.
Respondent submits that the Tribunal lacks jurisdiction because Claimant initiated the arbitration after the statutory period provided by Article XII(3)(d) of the BIT had expired.188 As Claimant bears the onus to establish the jurisdiction of the Tribunal, it must show that it submitted the dispute to arbitration no more than three years from the date on which it first acquired knowledge or should have first acquired knowledge of the alleged BIT breaches. Given that the Request for Arbitration was submitted on 16 December 2016, the cut-off date is 16 December 2013. Claimant nonetheless has not specified with precisions the date(s) on which it considers that Respondent allegedly breached its BIT obligations. This, in and of itself, suffices to dispose of Claimant’s entire case. All the more as Respondent has pointed to a number of specific admissions by Claimant that show that it had acquired or should have acquired knowledge of the alleged BIT breaches well before 16 December 2013.189 In fact, Claimant modified three times its position on the alleged timeliness of its Request for Arbitration.190
237.
The record shows that Claimant first acquired knowledge of the alleged refusal to authorize the 15 AAD requests at the very least on 28 November 2013.191 Claimant’s account of its own knowledge as of 28 November 2013 is in line with the information to which Claimant had access through its active participation in IATA and is further confirmed by documents obtained during the document production phase.192 Further, contemporaneous evidence also show that Claimant had already organized its departure from the country well before the cut-off date.193 Moreover, by admission of one of Claimant’s high representatives, Claimant was at the very least aware of the alleged breaches before the cut-off date of 16 December 2013.194
238.

Claimant’s Request for Arbitration was therefore filed in breach of the requirement of Article XII(3)(d) of the BIT. Consequently, the precondition to Respondent’s consent embodied in the BIT is not met and the Tribunal must declare that it lacks jurisdiction to hear Claimant’s claims.

(ii) Claimant

239.
Claimant submits that it is well within the three-year period allowed under Article XII(3)(d) of the BIT as it filed its Request for Arbitration on 16 December 2016.195
240.

Article XII(3)(d) also requires an investor’s actual or constructive knowledge of the loss or damages it has suffered as a result of the measures not only knowledge of the measures.196

241.
Prior to 16 December 2013, Claimant did not have actual or constructive knowledge that Respondent would ultimately not approve the outstanding AADs, or that Claimant would suffer loss due to Respondent’s failure to do so. Claimant had knowledge of Respondent’s acts and omissions leading up to 16 December 2013 - specifically its failure to approve, by that date, Claimant’s outstanding AADs - but that omission did not give rise to actual or constructive knowledge that Respondent would not subsequently approve the AADs or that Claimant would suffer loss or damage as a result. Indeed, Respondent had always complied with its AAD approval obligations, albeit often with delay, and Respondent was giving every indication that this would again be the case in the weeks leading up to and after 16 December 2013.197
242.
Further, throughout the ten years during which Claimant ran the Toronto-Caracas-Toronto route, there had been instances where Claimant had been concerned about CADIVI’s delay. Each time, CADIVI periodically assured the airlines that it would approve the airlines currency conversion requests promptly or would approve multiple AADs at the same time. Through this process, Claimant had been able to convert and transfer U.S.$ 91 million of returns to its bank account in New York and for use in its global operations. Therefore, the state of affairs in December 2013 was not entirely out of the ordinary.198
243.
Moreover, Respondent approached Claimant and other airlines on 28 November with an offer to negotiate settlement.199
244.
In addition, Respondent’s own actions following 16 December 2014 contradict its arguments. As late as 28 January 2014, Claimant still had no basis to conclude that Venezuela would breach its obligations under the BIT or that Claimant would suffer harm. Respondent’s agents themselves were reassuring Claimant that none of Respondent’s delays were going to crystalize into permanent rejections, and that several potential payment methods were being assessed.200
245.
Therefore, Respondent’s argument that Claimant’s claims are time-barred under the BIT is unfounded and should be rejected.201

4.2 The Tribunal’s analysis

(i) The issue

246.
The issue is whether Claimant’s claims are time-barred under Article XII(3)(d) of the BIT so as to affect the Tribunal’s jurisdiction or the admissibility of those claims (see supra paras 236 and 239). The Tribunal will address this issue as follows:

- First, it will set out the requirements of Article XII(3)(d) (Section (ii)).

- Second, it will consider whether Claimant has complied with that provision (Section (iii)).

- Finally, it will conclude (Section (iv)).

(ii) The requirements of Article XII(3)(d)

247.

The Parties disagree on the requirements of Article XII(3)(d) of the BIT.202 However, both Parties agree that the concept of knowledge set forth therein is governed both by the text of the BIT itself and by international law.203 Accordingly, in order to decide, the Tribunal will set out the provision encompassing Article XII(3)(d) and interpret that provision in accordance with the rules of treaty interpretation of Article 31 of the VCLT204 (which form part of customary international law) and as set out above (see supra para. 222).

248.
Article XII(3)(d) of the BIT, which is found in the provision on "Settlement of Dispute between and Investor and the Host Contracting Party" (already set out above in para. 132), reads in relevant part as follows:

1. Any dispute between one Contracting Party and an investor of the other Contracting Party, relating to a claim by the investor that a measure taken or not taken by the former Contracting Party is in breach of this Agreement, [...].

2. If a dispute has not been settled amicably within a period of six months from the date on which it was initiated, it may be submitted by the investor to arbitration in accordance with paragraph (4). For the purposes of this paragraph, a dispute is considered to be initiated when the investor of one Contracting Party has delivered notice in writing to the other Contracting Party alleging that a measure taken or not taken by the latter Contracting Party is in breach of this Agreement, and that the investor or an enterprise owned or controlled directly or indirectly by the investor has incurred loss or damage by reason of, or arising out of, that breach.

3. An investor may submit a dispute as referred to in paragraph (1) to arbitration in accordance with paragraph (4) only if:

[…]

(d) not more than three years have elapsed from the date on which the investor first acquired, or should have first acquired, knowledge of the alleged breach and knowledge that the investor has incurred loss or damage.

[…] (emphasis added)

249.
First, as with the waiver provision, it is clear from the wording of Article XII(3)(d) that the investor may submit its claims to arbitration "only if [...] not more than three years have elapsed from the date on which the investor first acquired, or should have first acquired, knowledge of the alleged breach and knowledge that the investor has incurred loss or damage" (see supra para. 248). Therefore, the time-bar is also a condition of Respondent’s consent to arbitration in the present case.205
250.
Second, it is undisputed that the relevant time-frame set by the time-bar rule is three years. For purposes of counting that time-frame, it is apparent form the first sentence of paragraph (3) - "[a]n investor may submit a dispute as referred to in paragraph (1) to arbitration" (emphasis added) - that it is the date of submission of the Request for Arbitration that is relevant, not the date of the Notice of Dispute.206 In this regard, the Tribunal notes that the fact that Claimant submitted in its Memorial that the relevant date is that of the notice of dispute,207 Claimant referred to the date of the Request for Arbitration in its responses to Respondent’s time-bar objection,208 is not an indication of bad faith or a situation that would require the Tribunal to draw adverse inferences, as Respondent requests; the Tribunal simply disagrees with Claimant’s interpretation and agrees with Respondent’s interpretation regarding the setting of the dies ad quern.209
251.
Third, with respect to the "knowledge" requirement, the provision provides for two possibilities: (a) the date on which knowledge was first acquired; or (b) the date on which knowledge should have been first acquired. The latter, i.e., the date on which a reasonable person in circumstances would have first acquired knowledge, is usually more relevant, as the date of actual knowledge is often difficult to determine.210
252.

Finally, the wording of Article XII(3)(d) is clear in that it requires both "knowledge of the alleged breach and knowledge that the investor has incurred loss or damage", not one or the other (emphasis added). Thus, the Tribunal agrees with Claimant that the relevant date must involve knowledge of both the BIT breach and the resulting consequences, i.e., that a loss would or did occur. This does not require quantification of the loss itself.211

253.
More specifically, it must be sufficiently clear that Claimant had clear knowledge of a clear breach of the BIT with the resulting consequences in terms of loss - but not quantification thereof - so that Claimant is in a position to arbitration immediately.
254.
The Tribunal should now assess whether Claimant has complied with the requirements of Article XII(3)(d) of the BIT.

(iii) Has Claimant complied with Article XII(3)(d) of the BIT?

255.
In the present case, Claimant filed its Request for Arbitration on 16 December 2016. Accordingly, Claimant must prove that it had or should have had first knowledge of the BIT violations and resulting damages or losses as of 16 December 2013, and not before, for this Tribunal to have jurisdiction. This is in dispute between the Parties.212
256.
The Tribunal recalls that the present dispute concerns Respondent’s alleged breaches of the BIT arising from Respondent’s failure to approve the 15 AAD requests filed by Claimant. Relevant for the purposes of the time-bar rule, therefore, is the date on which Claimant first knew or ought to have known that Respondent’s failure to approve the 15 AAD requests or its "omission" to do so, breached its treaty obligations and caused Claimant damage or loss. In this regard, the following facts are relevant.
257.
First, Claimant filed the 15 AAD requests between 20 September 2013 and 22 January 2014. These AAD requests covered the period between October 2012 and July 2013 (see supra para. 21). According to Mr. Blanco’s testimony, a normal process required CADIVI to approve, reject, or suspend an AAD request within a few days of each request. At the same time, it appears that Respondent had a practice of processing AAD requests somewhat late and collectively.213 And, pursuant to Article 60 in conjunction with Article 4 of the Administrative Procedure Law (or Ley Orgánica de Procedimientos Administrativos214) administrative files need to be processed and resolved within four months; absent an express decision, the interested party can assume that the request has been denied and seek judicial recourse - Air Canada, as the interested party, could in no way have presumed that a breach had occurred before the lapse of these four months. Therefore, it appears that any failure by Respondent in this regard resulting in a breach of international obligations could not have commenced prior to 2014.215 As such, Respondent’s reliance on statements by IATA in November 2013 - of which Claimant’s CEO was a member - regarding the delay in repatriating U.S.$ 1.5 billion to all corners of the world, including Respondent, cannot be considered evidence that attributes knowledge of Respondent’s BIT breaches on Claimant.216
258.
Second, it is true, and Claimant does not dispute this, that as of November 2013, CADIVI had not yet approved the AAD requests submitted by Claimant (out of the 15 AAD requests).217 On 28 November 2013, the President of INAC, Mr. Pedro González Díaz, allegedly approached Claimant and other airlines to discuss a number of pending applications for AAD requests and proposed to pay outstanding AADs with jet fuel or through government bonds.218 While the content of this meeting itself indicates knowledge of Respondent’s failure to approve AADs for several airlines, there is nothing to indicate any knowledge of Respondent’s breach of the BIT and resulting loss or damage with respect to its 15 AADs, the first of which was filed two months before the meeting. If anything, the meeting itself evidences an effort on Respondent’s part to find a solution to the situation that existed at that time well into 2014.219 Accordingly, the Tribunal rejects Respondent’s argument that Claimant’s perception of this meeting as an offer to negotiate a settlement is sufficient to be considered knowledge or notice of the BIT breach and resulting loss.220 Similarly, it rejects Respondent’s argument that the fact that Claimant had already arranged its departure from the country in 2021 is in any way relevant to early knowledge.221
259.
Equally irrelevant is the letter sent by the Ministry of the Presidency to ALAV on 8 November 2013, which asked ALAV to provide information on ticket sales by the 26 member airlines of ALAV, including Claimant, in 2012 and between January and October 2013. The fact that Claimant cites this letter in support of its argument in its Memorial that Respondent prevented Claimant from repatriating its revenues does not demonstrate that Claimant had first knowledge of Respondent’s BIT violations with respect to the 15 AAD requests and the resulting losses or damages.222 To the extent necessary, and if the Tribunal finds that it has jurisdiction, it will evaluate Claimant’s reliance on this document if and when it addresses the Merits.
260.
Third, Respondent relies on Claimant’s December 2013 internal communications to argue that Claimant had constructive knowledge of and was preparing to resolve the breach of the BIT and the resulting harm: (i) on 5 December 2013, by which BASSA informed Claimant that "the government has halted payments since what they own to the airline industry is $3B (significant amount for a struggling economy) and thus want us to consider accepting USD denominated government bonds instead of case"";223 (ii) on 6 December 2013, with Claimant’s Senior Sale Assistant stating: "there is a strong possibility that we will never see our money - so I suggest we expedite the negotiations to understand if there is good faith and really an option to receive fuel in exchange and how quickly we can offset our credit"224; (iii) dated 9 December 2013, with Claimant’s Senior Sale Assistant proposing to "take this to a higher level";225 (iv) in which the same refers to "rescue[ing] at least some of [Air Canada’s] money""; and (v) dated 10 December 2013, in which Claimant’s Vice President-Alliances & Regulatory Affairs insists that Claimant’s liaison officer with the Canadian officer participate on the conference call scheduled on 11 December 2013, along with various top Claimant executives, to discuss the repatriation of the funds,226 stating that Claimant was "now waking up internally".227 This internal correspondence may prima facie indicate recognition of the impending impairment. However, it suggests that Claimant is willing to engage in discussions and explore bona fide alternatives, implying that there can be no form of knowledge of a breach of the BIT, much less of the resulting loss or damage with respect to its 15 AADs, the first of which was filed two or three months before and the last of which was filed two months after.228 Had the negotiations resulted, for example, in an agreement to settle the amount (allegedly) due with fuel payments, no loss or damage would have resulted. Certainty as to the loss or damage associated with the breach of the BIT breach could only be obtained at a much later stage, when the negotiations proved unsuccessful.
261.
Fourth, Respondent also relies on Claimant’s references in its submissions to argue that Claimant knew or should have known of the situation it describes as causing its alleged harm prior to the 16 December 2013 cut-off date:229

- Claimant’s Notice of Dispute states that "[b]eginning in October 2012, however, Venezuela ignored Air Canada’s properly submitted AADs, simply refusing to act on the company’s requests to exchange Bolivars for Dollars, thereby preventing from Air Canada repatriating its funds. Specifically, Venezuela has refused to adjudicate Air Canada's fifteen AADs filed from October 2012 to December 2013. Venezuela, thus, prevented Air Canada from exchanging 330 million Bolivars earned through local ticket sales into Dollars and repatriating them".230 (emphasis added by Respondent)

- Claimant’s Request for Arbitration states that "[b]eginning in 2013, however, Venezuela ignored Air Canada’s properly submitted AADs, simply refusing to act on the company’s requests to exchange Bolivars for US Dollars, thereby preventing Air Canada from converting and repatriate its earnings. Specifically, up to the present date, Venezuela has refused to process fifteen AADs submitted by Air Canada in relation to domestic ticket sales between October 2012 and December 2013".231 (emphasis added by Respondent)

- Claimant’s Memorial states that "[s]tarting in late 2012 and throughout 2013, Venezuela took a series of measures that made it much harder for airlines, including Air Canada, to file their AADs. CADIVI and other Government agencies significantly increased the level of paperwork, information, and bureaucratic interaction necessary to process each AAD"232 (emphasis added by Respondent)

- Mr. Babun’s witness statement states that "[t]hroughout 2013 [...] Air Canada, and airlines in general, became increasingly concerned about the Government's failure to grant exchange requests".233 (emphasis added by Respondent)

- Mr. Pittman’s witness statement states that "[b]y the end of 2012 and during 2013, CADIVI increased the level of paperwork and information necessary to process each Authorization for Currency Acquisition".234 (emphasis added by Respondent)

262.
The Tribunal does not find that any of these statements show that Claimant first became aware of a material breach of the BIT prior to 16 December 2013. Consistent with the documents discussed above, these statements relate to what was undisputed at that time (Venezuela’s delay in adjudicating requested AADs), but not knowledge of actual breach of the BIT for failure to adjudicate all 15 AADs and resulting in losses and damages, since it was still feasible that Venezuela - albeit with some delay - would process the AADs.
263.
As a result, the Tribunal does not find that it is sufficiently clear that Claimant had first knowledge of Respondent’s alleged breaches of the treaty and resulting consequences prior to 16 December 2013. Instead, the Tribunal considers that, in the circumstances of the case, such knowledge should not reasonably have been first acquired sometime between Claimant’s decision to suspend its flights to and from Venezuela in 2014 and Claimant’s notice of dispute in relation to Respondent’s alleged breaches of the in 2016: that is, at time when Claimant could realize that the 15 AADS would not be processed and assess whether it might commence the present proceedings.
264.
Accordingly, the Tribunal finds that Claimant has complied with the time-bar provision of the BIT.

(iv) Conclusion

265.

Based on the foregoing, the Tribunal concludes that Respondent’s objection to jurisdiction based on the time-bar provision of Article XII(3)(d) of the BIT is dismissed.

5. Objections to jurisdiction ratione materiae and ratione personae

5.1 The Parties ’ positions

(i) Respondent

266.
Respondent submits that Claimant has failed to demonstrate that it meets (i) the ratione materiae requirement of the BIT and (ii) the ratione personae requirement of the BIT.235