Ruling on Power of Tribunal to Issue Provisional Measures Whilst Proceedings are Suspended, 24 September 2018; Interim Decision on Application for Provisional Measures, 30 September 2018; Decision on Application for Provisional Measures, 17 April 2019.
(i) grant the Commission leave to intervene in the present proceedings;
(ii) set a deadline for the Commission to file a written amicus curiae submission;
(iii) allow the Commission access to the documents filed in the case, to the extent necessary for its intervention in the proceedings;
(iv) allow the Commission to attend hearings in order to present oral argument and reply to the questions of [the] Tribunal at those hearings, should [the] Tribunal and the parties deem that useful.
By letter of 23 January 2019, the Respondent advised the Tribunal that twenty-two Member States of the European Union (“EU”), including Latvia and the UK, had signed a “Declaration of the Representatives of the Governments of the Member States of 15 January 2019 on the legal consequences of the judgment of the Court of Justice in Achmea and on investment protection in the European Union.”2 (“15 January 2019 Declaration” or “Declaration”) The Respondent’s correspondence attached that declaration, and two related declarations from the other EU Member States concerning Achmea dated 16 January 2019.3
“Declaration of the Representatives of the Governments of the Member States of 15 January 2019 on the legal consequences of the judgment of the Court of Justice in Achmea and on investment protection in the European Union” (Declaration of the UK, Latvia and 20 other Member States), (“Declaration” or “15 January 2019 Declaration”), R-00256.
“Declaration of the Representatives of the Governments of the Member States of 16 January on the enforcement of the judgment of the Court of Justice in Achmea and on investment protection in the European Union” (Declaration of Finland, Slovenia, Luxembourg, Sweden, Malta), R-00257; and “Declaration of the Representative of the Government of Hungary of 16 January 2019 on the legal consequences of the judgment of the Court of Justice in Achmea and on investment protection in the European Union” (Declaration of Hungary) (“Hungary's Declaration”), R-00258.
Now, therefore, the Tribunal:
(i) decides to bifurcate the proceedings and deal with the Respondent’s objection to the Tribunal’s jurisdiction based on the alleged unavailability of the investor-State arbitration mechanism under the UK-Latvia BIT as a preliminary matter;
(ii) asks that the Parties confer and attempt to reach agreement on the dates on which the above submissions will be made;
(iii) directs the Parties to submit agreed dates to the Tribunal within two weeks of the date of this Decision and if the Parties are unable to reach agreement on such dates, each side should submit proposed dates by the same time.
On 15 March 2019, the Respondent submitted a letter to the Tribunal with the proposed dates to brief the bifurcated issue. In the same letter, the Respondent also informed the Tribunal that it understood the Claimants wished to submit their Memorial on the Merits on 17 May 2019. The Respondent stated that, in principle, it did not object to the submission of the Claimants’ Memorial on that date, but indicated that it was “necessary for the Tribunal to formally suspend the proceedings on the merits thereafter and until a decision on the bifurcated issue is rendered.” The Respondent thus requested the suspension of the proceedings on the merits pursuant to the ICSID Arbitration Rules, in particular Rule 41(3).
(i) The schedule for submissions on the bifurcated issue, as agreed by the parties, is confirmed. [...]
(iv) The Claimants shall file their Memorial on the Merits by Friday 17 May 2019.
(v) The Tribunal defers any decision on the application to suspend the proceeding on the merits for the period following the filing of the Memorial on the Merits by the Claimants.
On 2 July 2019, the Tribunal rendered its Decision on Application to Reconsider the Decision on Bifurcation, ordering as follows:
(i) the decision to address as a preliminary matter the Respondent's objection to the Tribunal's jurisdiction based on the alleged unavailability of the investor-State arbitration mechanism under the UK-Latvia BIT is maintained;
(ii) the Claimants are directed to provide, with their Counter-Memorial on the bifurcated issue, a list of exhibits that they intend to rely upon during the hearing on the bifurcated issue, as the Respondent has recently done;
(iii) the Claimants are not to adduce evidence to establish it has legitimate expectations under EU law at the hearing on the bifurcated issue;
(iv) the Claimants are not to adduce at that hearing expert evidence on the content of the EU law of legitimate expectations;
(v) the Tribunal will not have regard at that hearing to any evidence by the Respondent directed to the content or existence of legitimate expectations, including the relevant sections of Professor Tridimas’ report;
(vi) the Tribunal confirms that it will hold its hearing on the bifurcated issue as scheduled on 19-21 September 2019.
I note that the Claimants rely on an expert opinion on EU law by David Neuberger. As he mentions, he is a member of One Essex Court. As the parties know, I am a door tenant at those chambers, although I live in Sydney.
David Neuberger and I are also both members of the Hong Kong Court of Final Appeal. As only one foreign judge sits at one time, we never sit together.
Finally, as the parties will be aware I was a member of the Tribunal in Cube Infrastructure v. Spain to which Lord Neuberger and the Claimants refer.
19. The Tribunal rejects the Claimants’ contention that an application for suspension by a party is a condition precedent to the exercise of the Tribunal’s discretion under Rule 41(3). Further, nothing in the text suggests that a request for suspension should be contained in the Request for Bifurcation. In any event, the Respondent made a request by letter of 15 March 2019.
20. There are two critical considerations which, in the opinion of the Tribunal, guide the exercise of the discretion to suspend in the present case. First, is the justifiable concern that suspension will significantly delay the hearing on the merits. Secondly, is the waste of resources involved in preparing for a hearing in the event that the Tribunal upholds the jurisdictional objection.
21. The Tribunal has determined that in all the circumstances, including the proximity of the jurisdictional Hearing, the latter outweighs the former and orders suspension of the proceedings.
22. The Tribunal notes the Respondent’s contention that recent developments may require amendment of the Claimants’ Memorial on the Merits. That is a matter for the Claimants.
23. The Tribunal indicates that it would be favorably disposed to an application by the Claimants to lift the suspension for the limited purpose of permitting the amendment of the Memorial if the Claimants should choose to make such an application.
Tribunal
The Honourable James Spigelman QC President
H.E. Judge Peter Tomka Co-Arbitrator
Mr John M. Townsend Co-Arbitrator
ICSID Secretariat
Mr Francisco Abriani Secretary of the Tribunal
Assistant to the President of the Tribunal
Mr Adam Butt Assistant to the President of the Tribunal
For the Claimants
Dr Anthony Sinclair Quinn Emanuel Urquhart & Sullivan UK LLP
Mr Armando Neris Quinn Emanuel Urquhart & Sullivan UK LLP
Dr David Pusztai Quinn Emanuel Urquhart & Sullivan UK LLP
Mr James Mohajer Quinn Emanuel Urquhart & Sullivan UK LLP
Experts
The Rt. Hon. Lord Neuberger of Abbotsbury One Essex Court
Prof Stefan Talmon University of Bonn, University of Oxford, 20 Essex Street
For the Respondent
Mr Pierre-Olivier Savoie Savoie Arbitration
Ms Justine Touzet Savoie Arbitration
Ms Léna Kim Savoie Arbitration
Mr Lucas Mathieu Savoie Arbitration
Ms Marie-Pier Michon
Prof. Angelos Dimopoulous Queen Mary University of London
Party Representatives:
Dr Ilze Dubava The State Chancellery
Mr Dainis Pudelis The State Chancellery
Ms Nerika Lizinska The State Chancellery
Mr Gvido Romeiko Financial and Capital Market Commission
Ms Nora Dambure Financial and Capital Market Commission
Ms Daiga Birite Financial and Capital Market Commission
Expert
Prof. Takidis Tridimas King’s College, London; Matrix Chambers
Court Reporter
Ms Anne-Marie Stallard The Court Reporter
The Tribunal wishes to receive post-hearing submissions on the following topics:
1. Directed to the Respondent:
Provide particulars of each specific EU law, or provision thereof, which, if the proceeding goes to the merits, there is
(i) a risk and/or
(ii) on the balance of probabilities, it is likely
that the Tribunal will have to interpret that law or, alternatively, that the Tribunal may apply the law as facts without interpreting them.
2. Directed to the Respondent: the Tribunal refers to the submission at paragraph 31 of the Counter-Memorial on the Bifurcated Objection, including specifically the assertion that the Tribunal “has directed” that the issue of the application of the EU law of legitimate expectations has been “deferred to the merits”, and to paragraph 13 of the Decision of July 2, 2019 on Reconsideration of the Decision on Bifurcation. The Tribunal invites the Respondent to reply.
3. Directed to the Claimants: the Tribunal requests a submission on the issue of inadmissibility.
a. defer question one to the merits phase;
b. withdraw question two, thus deferring all issues concerning the EU law and international law of legitimate expectations to the merits phase; and
c. confirm that the scope of the requested submissions on question three is limited to the admissibility objections previously raised in the Respondent's submissions, which have been summarised at paragraph 36 of the Claimants' letter dated 7 October.
i. The Tribunal amends Question 1 to read: The Tribunal invites the Respondent to reply further to the Claimants' contention that the Tribunal should treat EU law as a fact. It is a matter for the Respondent whether it wishes to do so or not.
ii. The Tribunal maintains Question 3. It is a matter for the Claimant whether it wishes to respond or not.
iii. In the case of each of i and ii, it is for the party requested to determine the content, if any, of its response. The other party's reply should be confined to the matters raised in the first submission. If the first party elects not to respond to a question, no reply will be called for.
iv. The Tribunal has reconsidered Question 2 and has determined that it does not require a submission from the Respondent. The Question is withdrawn.
a. The Tribunal recognises Mr. Krastins as the representative of the Bank for the purposes of completing submissions on the Bifurcated Issue in answer to the Tribunal questions.
b. Mr. Krastins will be given access to the submissions on the Bifurcated Issue.
c. Until further order, the Tribunal rejects Mr. Behrends' application to be accepted as the representative of the Bank. The parties are directed to continue to copy Mr. Behrends on any communication relating to the representation of the Bank.
d. The Tribunal accepts that both Mr. Krastins, in the exercise of his statutory powers, and the former Directors or the current shareholders, reflecting the separate legal personality of the Bank, are entitled to be heard if the Tribunal rejects the Respondent's jurisdictional challenge on the Bifurcated Issue.
e. If that occurs, further submissions will be sought at that time.
On 17 February 2020, Mr Behrends filed a proposal to disqualify all of the Members of the Tribunal on behalf of AS PNB Banka.
On 20 February 2020, the Secretary-General notified the Parties that pursuant to ICSID Arbitration Rule 9(6), the proceeding was suspended.
The Parties’ subsequent filings on Mr Behrends’ and the Shareholder Claimants’ disqualification proposals are detailed in the Decision on the Proposals to Disqualify Messrs. James Spigelman, QC, Peter Tomka and John M. Townsend of 16 June 2020 (“Decision on the Disqualification Proposals”). In its Decision on the Disqualification Proposals, the Chairman of the Administrative Council decided that Mr Behrends had no standing to file a proposal for disqualification on behalf of AS PNB Banka and rejected the Shareholder Claimants’ proposal for disqualification.
On 25 June 2020, the Tribunal invited the Parties to comment in their post-hearing submissions, on the Decision on Jurisdiction in the case Addiko Bank AG v. Croatia (ICSID Case No. ARB/17/37) rendered on 12 June 2020 ("Addiko v Croatia”).
By letter of 1 September 2020, the Shareholder Claimants notified the Tribunal that the Agreement for the Termination of Bilateral Investment Treaties between the Members States of the European Union (the “Termination Agreement”), submitted as legal authority CL-336, had entered into force on 29 August 2020. They further noted that (i) the UK-Latvia BIT had not been terminated under Article 2 and Annex A; (ii) the UK was not a Contracting Party; (iii) Latvia had not terminated all of its “intra-EU” BITs; and (iv) the UK and Latvia had not sought to inform the Tribunal of “the legal consequences of the Achmea judgment” in accordance with Article 7 and the pro forma statement in Annex C of the Agreement.
CJEU, Slovak Republic v. Achmea BV, Case C-284-16, 6 March 2018, RL-0001 (“Achmea”); CJEU, Opinion 1/17 of the Court, 30 April 2019, TT-0060 (“CETA Opinion” or “Opinion 1/17”).
Achmea concerned a request by the Bundesgerichtshof (Federal Court of Justice, Germany) for a preliminary ruling from the CJEU with respect to the interpretation of Articles 18, 267 and 344 Treaty on the Functioning of the European Union (“TFEU”).
1. All disputes between one Contracting Party and an investor of the other Contracting Party concerning an investment of the latter shall if, possible, be settled amicably.
2. Each Contracting Party hereby consents to submit a dispute referred to in paragraph 1 of this Article to an arbitral tribunal, if the dispute has not been settled amicably within a period of six months from the date on which either party to the dispute requested amicable settlement.
3. The arbitral tribunal referred to in paragraph (2) of this Article will be constituted for each individual case in the following way: each party to the dispute appoints one member of the tribunal and the two members thus appointed shall select a national of a third State as Chairman of the tribunal. Each party to the dispute shall appoint its member of the tribunal within two months, and the Chairman shall be appointed within three months from the date on which the investor has notified the other Contracting Party of his decision to submit the dispute to the arbitral tribunal.
4. If the appointments have not been made in the abovementioned periods, either party to the dispute may invite the President of the Arbitration Institute of the Chamber of Commerce of Stockholm to make the necessary appointments. If the President is a national of either Contracting Party or if he is otherwise prevented from discharging the said function, the Vice-President shall be invited to make the necessary appointments. If the Vice-President is a national of either Contracting Party or if he too is prevented from discharging the said function, the most senior member of the Arbitration Institute who is not a national of either Contracting Party shall be invited to make the necessary appointments.
5. The arbitration tribunal shall determine its own procedure applying the United Nations Commission on International Trade Law (UNCITRAL) arbitration rules.
6. The arbi[tral] tribunal shall decide on the basis of the law, taking into account in particular though not exclusively:
- the law in force of the Contracting Party concerned;
- the provisions of this Agreement, and other relevant agreements between the Contracting Parties;
- the provisions of special agreements relating to the investment;
- the general principles of international law.
7. The tribunal takes its decision by majority of votes; such decision shall be final and binding upon the parties to the dispute.8
In October 2008, Achmea commenced arbitration proceedings against the Slovak Republic under Article 8 of the Slovakia-Netherlands BIT and the UNCITRAL Arbitration Rules for damages caused by its legislative measures. The tribunal determined Frankfurt am Main to be the place of the arbitration. The Slovak Republic objected to the tribunal’s jurisdiction on the basis that, due to its accession to the EU, recourse to arbitration provided for in Article 8(2) of the Slovakia-Netherlands BIT was incompatible with EU law.
On 26 October 2010, the tribunal dismissed the objection. Set aside applications before the courts of Germany, the place of arbitration, were unsuccessful at first instance and on appeal. By an award of 7 December 2012, the tribunal ordered that the Slovak Republic pay Achmea damages of EUR 22.1 million. The Slovak Republic brought a further set aside action before the Frankfurt Higher Regional Court which dismissed the action.
The Slovak Republic then appealed to the Bundesgerichtshof On 3 March 2016, it requested a preliminary ruling from the CJEU under Article 267 of the TFEU. Given the numerous BITs still in force between Member States with similar arbitration clauses to the one in question, the Bundesgerichtshof sought a ruling on the following questions:
(1) Does Article 344 TFEU preclude the application of a provision in a bilateral investment protection agreement between Member States of the European Union (a so-called intra-EU BIT) under which an investor of a Contracting State, in the event of a dispute concerning investments in the other Contracting State, may bring proceedings against the latter State before an arbitral tribunal where the investment protection agreement was concluded before one of the Contracting States acceded to the European Union but the arbitral proceedings are not to be brought until after that date?
If Question 1 is to be answered in the negative:
(2) Does Article 267 TFEU preclude the application of such a provision?
If Questions 1 and 2 are to be answered in the negative:
(3) Does the first paragraph of Article 18 TFEU preclude the application of such a provision under the circumstances described in Question 1?
EU law is characterised by the fact that it stems from an independent source of law, the Treaties, by its primacy over the laws of the Member States, and by the direct effect of a whole series of provisions which are applicable to their nationals and to the Member States themselves.9
The CJEU reasoned that EU law is based on the fundamental premise that each EU Member State shares with the other Member States a set of common values on which the EU is founded (Treaty on European Union (“TEU”) Article 2), implying and justifying the existence of mutual trust between Member States that those values will be recognised and respected. In that context, Member States must, by reason, inter alia, of the principle of sincere cooperation set out in Article 4(3) of the TEU, ensure in their territories the application of, and respect for, EU law.
The CJEU explained that to ensure that the autonomy of the EU legal order is preserved, the EU Treaties have established a judicial system which is intended to ensure consistency and uniformity in interpreting EU law.10 Pursuant to Article 19 of the TEU, national courts, tribunals and the CJEU, are to ensure the full application of EU law in all Member States and the judicial protection of the rights of individuals. The “keystone” of this judicial system is the preliminary ruling procedure provided for in Article 267 of the TFEU, which intends to secure uniform interpretation of EU law.11
The CJEU assessed whether the disputes which the arbitral tribunal was called on to resolve are liable to relate to the interpretation or application of EU law.12 While the tribunal was being called on to rule on possible infringements of the Slovakia-Netherlands BIT, in order to do so pursuant to Article 8(6), it had to “take account” of the law in force of the contracting party concerned and other relevant agreements between the contracting parties.
This finding was reinforced by the notion that any award would not meet the requirements of Article 19 of the TEU, i.e., being subject to review by a court of a Member State. Within this framework, under Article 8(7) of the Slovakia-Netherlands BIT, the decision of the arbitral tribunal provided for in that Article is final. Further, under Article 8(5), the tribunal was also to determine its own procedure applying the UNCITRAL rules, including choosing its seat and consequently the law applicable to the procedure governing judicial review of the validity of the award by which it puts an end to the dispute before it.
Articles 267 and 344 TFEU must be interpreted as precluding a provision in an international agreement concluded between Member States, such as Article 8 of the [Slovakia-Netherlands BIT], under which an investor from one of those Member States may, in the event of a dispute concerning investments in the other Member State, bring proceedings against the latter Member State before an arbitral tribunal whose jurisdiction that Member State has undertaken to accept.
Is Section F (‘Resolution of investment disputes between investors and states') of Chapter Eight (‘Investment') of the Comprehensive Economic and Trade Agreement between Canada, of the one part, and the European Union and its Member States, of the other part, signed in Brussels on 30 October 2016 (OJ 2017 L 11, p. 23; ‘the CETA') compatible with the Treaties, including with fundamental rights?21
The Comprehensive Economic and Trade Agreement (“CETA”) is a free trade agreement that contains rules relating to, inter alia, investment. Section F of Chapter Eight of CETA contains Articles 8.18 to 8.45 which pertain to the establishment of a mechanism for the resolution of investment disputes between investors and States (“ISDS mechanism”). Article 8.27 provides for the creation of a Tribunal (“CETA Tribunal”) upon the entry into force of the CETA. Article 8.28 provides for the creation of an Appellate Tribunal (“CETA Appellate Tribunal”). Article 8.29 provides for the eventual establishment of a multilateral investment tribunal and appellate mechanism, the establishment of which will end the operation of the CETA Tribunal and the CETA Appellate Tribunal.22
- Section F of Chapter Eight of the CETA does not confer on the envisaged tribunals any power to interpret or apply EU law other than the power to interpret and apply the provisions of that agreement having regard to the rules and principles of international law applicable between the Parties, and
- Section F of Chapter Eight of the CETA does not structure the powers of those tribunals in such a way that, while not themselves engaging in the interpretation or application of rules of EU law other than those of that agreement, they may issue awards which have the effect of preventing the EU institutions from operating in accordance with the EU constitutional framework.
“in determining the consistency of a measure with [CETA], the Tribunal may consider, as appropriate, the domestic law of a Party as a matter of fact” and further states that, “in doing so, the Tribunal shall follow the prevailing interpretation given to the domestic law by the courts or authorities of that Party,” adding that “any meaning given to domestic law by the Tribunal shall not be binding upon the courts or the authorities of that Party.”
Those provisions serve no other purpose than to reflect the fact that the CETA Tribunal, when it is called upon to examine the compliance with the CETA of the measure that is challenged by an investor and that has been adopted by the investment host State or by the Union, will inevitably have to undertake, on the basis of the information and arguments presented to it by that investor and by that State or by the Union, an examination of the effect of that measure. That examination may, on occasion, require that the domestic law of the respondent Party be taken into account. However, as is stated unequivocally in Article 8.31.2 of the CETA, that examination cannot be classified as equivalent to an interpretation, by the CETA Tribunal, of that domestic law, but consists, on the contrary, of that domestic law being taken into account as a matter of fact, while that Tribunal is, in that regard, obliged to follow the prevailing interpretation given to that domestic law by the courts or authorities of that Party, and those courts and those authorities are not, it may be added, bound by the meaning given to their domestic law by that Tribunal.
The fact that there is no jurisdiction to interpret the rules of EU law other than the provisions of the CETA is also reflected in Article 8.21 of that agreement...
Nor will the CETA Appellate Tribunal be called upon to interpret or apply the rules of EU law other than the provisions of the CETA. (see Article 8.28.2(a)).
(1) by the Declaration, informing intra-EU investment arbitration tribunals about the legal consequences of Achmea;
(2) defending Member States by requesting any court (including in third countries) which is to decide proceedings relating to intra-EU investment arbitration awards, to set the awards aside or not enforce them due to a lack of valid consent;
(3) by the Declaration, informing the investor community that no new intra-EU investment arbitration proceeding should be initiated;
(4) taking steps under national laws to withdraw pending cases where Member States control undertakings that are involved in pending investment arbitration cases against other Member States;
(5) terminating all BITs concluded between them by means of a plurilateral treaty or, if mutually more expedient, bilaterally;
(6) not challenging settlements and arbitral awards in intra-EU investment arbitration cases that can no longer be annulled or set aside and were voluntarily complied with or definitively enforced before Achmea;
(7) making best efforts to deposit their instruments of ratification, approval or acceptance of the plurilateral treaty or of any bilateral treaty terminating BITs between Member States by 6 December 2019;
(8) discussing whether any additional steps are necessary to draw all the consequences from Achmea generally or in relation to the intra-EU application of the ECT.47
5. In light of the Achmea judgment, Member States will terminate all bilateral investment treaties concluded between them by means of a plurilateral treaty or, where that is mutually recognised as more expedient, bilaterally.
6. Member States will ensure effective legal protection pursuant to the second subparagraph of Article 19(1) TEU under the control of the Court of Justice against State measures that are the object of pending intra-EU investment arbitration proceedings.
7. Settlements and arbitral awards in intra-EU investment arbitration cases that can no longer be annulled or set aside and were voluntarily complied with or definitively enforced before the Achmea judgment should not be challenged. Member States will discuss, in the context of the plurilateral Treaty or in the context of bilateral terminations, practical arrangements, in conformity with Union law, for such arbitral awards and settlements. This is without prejudice to the lack of jurisdiction of arbitral tribunals in pending intra-EU cases.
8. Member States will make best efforts to deposit their instruments of ratification, approval or acceptance of that plurilateral treaty or of any bilateral treaty terminating bilateral investment treaties between Member States no later than 6 December 2019. They will inform each other and the Secretary General of the Council of the European Union in due time of any obstacle they encounter, and of measures they envisage in order to overcome that obstacle.48
(1) That the CJEU held in Budëjovickÿ Budvar50 that provisions laid down in an international agreement between two Member States cannot apply in the relations between them if the provisions are found to be contrary to the EU Treaties.
(2) That Member States must draw the necessary consequences from Union law as interpreted in Achmea.
(3) That investor-State arbitration clauses in intra-EU bilateral investment treaties are contrary to the EU Treaties and cannot be applied after the date on which the last of the parties to an intra-EU bilateral investment treaty became a Member State.
(4) That there is a common understanding between the parties to the EU Treaties and intra-EU bilateral investment treaties that such a clause cannot serve as legal basis for Arbitration Proceedings.
(5) That the Termination Agreement should cover all investor-State arbitration proceedings based on intra-EU bilateral investment treaties under any arbitration convention or set of rules, including inter alia under the ICSID Convention.
(6) That the Termination Agreement was without prejudice to the question of compatibility with the EU Treaties of substantive provisions of intra-EU bilateral investment treaties.
(7) That the Termination Agreement addresses intra-EU bilateral investment treaties but not intra-EU proceedings on the basis of Article 26 of the Energy Charter Treaty.51
(8) That Member States are obliged under the Article 19(1) TEU to provide remedies sufficient to ensure effective legal protection of investors' rights under Union law. In particular, every Member State must ensure that its courts/tribunals, within the meaning of Union law, meet the requirements of effective judicial protection.52
(1) Article 2 provides that Annex A lists the bilateral treaties which are terminated under the Termination Agreement.
(2) Article 4 confirms that investor-State arbitration clauses in intra-EU bilateral investment treaties are contrary to the EU Treaties and inapplicable. As a result of this incompatibility, as of the date on which the last of the parties to a relevant bilateral investment treaty became a Member State, the arbitration clause cannot serve as a legal basis for Arbitration Proceedings.
(3) Article 6 provides that the Termination Agreement shall not affect concluded arbitration proceedings or an agreement to settle an applicable arbitral proceeding.
(4) Article 7 provides that contracting parties which are parties to BITs on the basis of which pending or new arbitration proceedings were initiated, must inter alia cooperatively inform arbitral tribunals about the legal consequences of Achmea.53
(5) Article 8 sets out transitional measures related to pending arbitration proceedings.
(6) Article 9 sets out a settlement procedure for pending arbitration proceedings.
(7) Article 10 sets out investors’ entitlements to access national courts in pending arbitration proceedings.
(8) Article 17 enables contracting parties to apply the Termination Agreement provisionally.
It is common ground that the law applicable to the Tribunal’s jurisdiction includes Article 25 of the ICSID Convention, Article 8 of the BIT if in force, and general international law. Latvia asserts, and the Claimants deny, that the applicable law includes EU law.
(1) Article 8 of the BIT is precluded by EU law as a matter of principle and specifically by Articles 267 and 344 TFEU, as authoritatively interpreted by the CJEU.
(2) Article 8 of the BIT is precluded by EU law as a matter of fact since this Tribunal will necessarily have to interpret or apply EU law in the present case.
(3) The entire BIT is precluded by EU law since the BIT has insufficient safeguards in its substantive provisions to ensure that the EU Member States' right to regulate and obligation to apply EU law will be sufficiently protected.
(4) The entire BIT is precluded because its interpretation and application can lead to a change in the division of powers of EU institutions within the EU's constitutional framework.
Hearing, Day 1, 63:13-17, citing, e.g. Eskosol S.pa.A in Liquidazione v Republic of Italy, ICSID Case No. ARB/15/50, Decision on Italy’s Request for Immediate Termination and Italy’s Jurisdictional Objection Based on Inapplicability of the Energy Charter Treaty to Intra-EU Disputes, 7 May 2019, RL-00189 (“Eskosol”), para. 181. Further, in Kadi, Advocate General Maduro delineated EU law as “a municipal legal order of trans-national dimensions”, and “distinct from the existing legal order of public international law.” CJEU, C-402/05, P - Kadi v. Council and Commission, Opinion of Advocate General Poiares Maduro, 16 January 2008, ST-15 (“Kadi”), para. 21.
Citing Vattenfall AB and others v. Federal Republic of Germany, ICSID Case No. ARB/12/12, Decision on the Achmea issue, RL-00088 (“Vattenfall”), paras. 141, 148, 150; Christoph Schreuer, ‘Jurisdiction and Applicable Law in Investment Treaty Arbitration', (2014) McGill Journal of Dispute Resolution 1, ST-10, p. 24.
Citing PCIJ, Case Concerning the Payment in Gold ofBrazilian Federal Loans Contracted in France, PCIJ Series A, No. 21, Judgment, 12 July 1929, TT-0176, p. 124 (for the purposes of stating that this is what the PCIJ held regarding domestic law); ICJ, Case Concerning Ahmadou Sadio Diallo (Republic of Guinea v. Democratic Republic of the Congo), ICJ Reports 2010, Judgment, 30 November 2010, RL-00310, p. 664, para. 67 (ICJ decision in context of African Charter on Human and People’s Rights).
(1) in 1994, Latvia and the UK signed the BIT, which entered into force in 1995;
(2) on 12 June 1995, Latvia signed the EU Association Agreement which entered into force in 1998;
(3) in 1998, Latvia’s progress report on EU accession confirmed that it had signed BITs with all EU Member States except Ireland;
(4) on 1 May 2004, Latvia acceded to the EU.
See e.g. UP and C.D Holding Internationale v. Hungary, ICSID Case No. ARB/13/35, Award, 9 October 2018, RL-00138 (“UP and C.D v Hungary Award”), para. 253. See also United Utilities (Tallinn) B.V. and Aktsiaselts Tallinna Vesi v. Republic of Estonia, ICSID Case No. ARB/14/24, Award, 21 June 2019, RL-00308 (“United Utilities”). In their Fourth PHS, the Claimants also assert that, in contrast to the Strabag Award of 4 March 2020 (CL-337), this Tribunal is not subject to any domestic legal system and derives its jurisdiction exclusively from the BIT and the ICSID Convention, the latter being selfcontained, delocalised and transnational in nature. There is asserted to be no basis for EU law to intrude. SC PHS 4, p. 2.
The EU treaties are, certainly, international agreements of a kind familiar in international law, binding as between the States Parties; but they also function as the constitution of an autonomous community. The rules established by EU secondary legislation are essentially supra-national regulations rather than part of the corpus of international law as such... Within the system of international law, EU law does not have supremacy, and has no hierarchical priority over the laws of non-Member States, or over rules of international law.
Since the ECJ is empowered by the EU Treaties to give preliminary rulings on the interpretation of EU law, including the EU Treaties (see Article 19 TEU and Article 267 TFEU), the Tribunal considers the ECJ Judgment’s interpretation of the EU Treaties likewise to constitute a part of the relevant international law.
Any such claim to priority [of EU law over the ECT] would challenge the basis of the ECT as a multilateral treaty, unilaterally asserting for the EU and its Member States a right to be treated differently from all other ECT Contracting Parties.91
The Respondent submits that Article 42 of the ICSID Convention applies to the question of the Tribunal’s jurisdiction, as well as to merits, and requires the Tribunal to apply EU law to this case. Latvia cites various matters in support of this assertion, including the Declaration, certain ICSID tribunals decisions,92 and leading commentary.93
E.g. Tidewater Investment SRL and Tidewater Caribe, C.A. v. Bolivarian Republic ofVenezuela, ICSID Case No. ARB/10/5, Decision on Jurisdiction, 8 February 2013, RL-00261 (“Tidewater”), para. 86; Interocean Oil Development Company and Interocean Oil Exploration Company v. Federal Republic of Nigeria, ICSID Case No. ARB/13/20, Decision on Preliminary Objections, 29 October 2014, RL-00266 (“Interocean”), para. 65; also Inceysa Vallisoletana, S.L. v. Republic ofEl Salvador, ICSID Case No. ARB/03/26, Award, 2 August 2006, RL-0004, para. 225-226.
Christoph Schreuer et al., The ICSID Convention - A Commentary, Cambridge University Press, 2nd edn. (2009), RL-00267, p. 552.
(1) it is agreed by the UK and Latvia that EU law is part of the law applicable to an intra-EU BIT;94
(2) EU law applies under Article 42 of the ICSID Convention on the basis of applicable principles of international law95 (e.g. Articles 31(3)(c) and 5 of the VCLT and conflicts rules); and
(3) EU law applies on the basis of Latvia's conflict-of-law rules (e.g. constitutional rules requiring that EU law prevail over other legal norms).
Citing German Federal Court of Justice in Slowakische Republik v. Achmea, Order, 31 October 2018, R-00212, para. 18; Declaration, R-00256, fn. 1; and Declaration No. 17 on Primacy, Annexed to the Final Act of the Intergovernmental Conference Which Adopted The Treaty of Lisbon signed on 13 December 2007, Official Journal of the European Union, No. 326/227, 26 October 2012, (“Declaration 17”), R-00266, p. 10.
(1) the “law of the Contracting State party to the dispute (including its rules on the conflict of laws);” or
(2) “such rules of international law as may be applicable”.96
(1) EU law is part of the law “agreed” to by Latvia and the UK to be applicable to a BIT dispute. Under Article 31(3)(c) of the VCLT, in interpreting the BIT, this Tribunal “shall” take into account international agreements in force between the UK and Latvia. Such international agreements include EU law as derived from the EU Treaties. In this dispute, it is argued, EU law will include EU regulations and directives on banking law.
(2) The Declaration confirms that EU law applies to the determination of this dispute. For the same reasons, says Latvia, EU law necessarily comes within the text of “such rules of international law as may be applicable” in the Article 42(1) definition.
See M.C.I. Power Group L. C. and New Turbine, Inc. v. Republic of Ecuador, ICSID Case No. ARB/03/6, Decision on Annulment, 19 December 2009, CL-222, para. 37; Vattenfall, paras. 118-119; Landesbank Baden-Württemberg and others v. Kingdom of Spain, ICSID Case No. ARB/15/45, Decision on the “Intra-EU” Jurisdictional Objection, 25 February 2019, ST-9 (“Landesbank”), para. 161; See also First Talmon Report, para. 47; Christoph Schreuer, ‘Jurisdiction and Applicable Law in Investment Treaty Arbitration', (2014) McGill Journal of Dispute Resolution 1, ST-10, p. 3.
Citing Vattenfall, para. 154; Eskosol, para. 126. See also Strabag which is relied on to assert that Article 31(3) cannot be used to rewrite the ordinary meaning of the text of the treaty under interpretation. Strabag, paras. 8.125-8-125.6.
Latvia addresses the Declarations in connection with inter alia Magyar Farming.106 In Magyar Farming, it says, the tribunal's reasoning which rejected the intra-EU objection rests essentially on two grounds: (1) that the 15 January 2019 Declarations cannot be considered to retroactively withdraw Hungary’s consent to arbitration; and (2) that the conditions of Article 30 VCLT are not met in that case.
Latvia also similarly addresses the Declarations in connection with the Claimants' arguments relating to Addiko. Addiko Bank AG and Addiko Bank d.d. v. Republic of Croatia, ICSID Case No. ARB/17/37, Decision on Croatia's Jurisdictional Objection Related to the Alleged Incompatibility of the BIT with the EU Acquis, 12 June 2020, CL-284 or RL-00419 (“Addiko v Croatia” or “Addiko”).
(1) The Termination Agreement is not a relevant source of law under Article 31(3)(c) of the VCLT.
(2) The EC’s notice of infringement recognises that the BIT remains in force.
(3) The signatories of the Termination Agreement recognise that Achmea did not have the effect of terminating the intra-EU BITs.
(4) Several EU Member States, including the UK, did not agree to terminate their intra-EU BITs.
(5) All non-EU States continue to enforce international arbitration awards based on intra-EU BITs, showing that there is no international consensus on Achmea as alleged.
(6) The BIT is now an extra-EU BIT, thus any comparison with Achmea is inapposite.
See First and Second Talmon Reports; cf Vattenfall, para. 217; Cube Infrastructure, para. 132 (ECT context).