Table of Selected Abbreviations/Defined Terms | |
Arbitration Rules | ICSID Rules of Procedure for Arbitration Proceedings (10 April 2006) |
BIT/Treaty | Agreement on the Encouragement and Reciprocal Protection of Investments Between the Government of the People’s Republic of China and the Government of the Republic of Yemen, which entered into force on 10 April 2002 (CL-001 (Revised)) |
C-[#] | Claimant’s Exhibit |
Cl. C-M | Claimant’s Counter-Memorial on Jurisdiction dated 4 January 2017 |
Cl. Mem. | Claimant’s Memorial on the Merits dated 12 August 2016 |
Cl. Rej. | Claimant’s Rejoinder on Jurisdiction dated 3 March 2017 |
CL-[#] | Claimant’s Legal Authority |
Hearing | Hearing on Jurisdiction held on 15-16 March, 2017 |
ICSID Convention | Convention on the Settlement of Investment Disputes Between States and Nationals of Other States dated 18 March 1965 |
ICSID or the Centre | International Centre for Settlement of Investment Disputes |
PRC | People’s Republic of China |
R-[#] | Respondent’s Exhibit |
Resp. Mem. | Respondent’s Memorial on Jurisdiction dated 14 October 2016 |
Resp. Reply | Respondent’s Reply on Jurisdiction dated 3 February 2017 |
RL-[#] | Respondent’s Legal Authority |
Tr. Day [#] [Speaker(s)] [page:line] | Transcript of the Hearing |
VCLT | Vienna Convention on the Law of Treaties |
• Witness Statement of Mr. Zhang Jinxun dated 12 August 2016;
• Witness Statement of Mr. Huang Kaibao dated July 2016;
• Witness Statement of Mr. Ji Qiuming dated 12 August 2016;
• Witness Statement of Mr. Ye Ruilin dated July 2016;
• Witness Statement of Mr. Sun Yifei dated 3 August 2016;
• Witness Statement of Mr. Guo Yongbin dated July 2016;
• Witness Statement of Mr. Liang Zhaolong dated July 2016;
• Witness Statement of Mr. Wang Zhiwen dated 12 August 2016; and
• Expert Report of Mr. Robert Chandler of Ernst & Young dated 12 August 2016 with Appendices 001 through 062 and Exhibits EY-001 through EY-224.
On 10 March 2017, the Tribunal issued Procedural Order No. 4 setting out arrangements for the Hearing on Jurisdiction, which was held at the International Dispute Resolution Centre in London, United Kingdom, from 15-16 March 2017 (the "Hearing"). In addition to the Members of the Tribunal and the Secretary of the Tribunal, the following persons were present at the Hearing:
For the Claimant:
Ms. Reza Mohtashami Freshfields Bruckhaus Deringer LLP
Mr. Sami Tannous Freshfields Bruckhaus Deringer LLP
Mr. Matei Purice Freshfields Bruckhaus Deringer LLP
Mr. Farouk El Housseny Freshfields Bruckhaus Deringer LLP
Ms. Ruba Ghandour Freshfields Bruckhaus Deringer LLP
Mr. David Merritt Hill International
For the Respondent:
Mr. Benjamin Knowles Clyde & Co LLP
Mr. Patrick Zheng Clyde & Co LLP
Mr. Ian Hopkinson Clyde & Co LLP
Ms. Milena Szuniewicz-Wenzel Clyde & Co LLP
Ms. Saadia Bhatty Clyde & Co LLP
Ms. Enas Al-Shaibi Clyde & Co LLP
Ms. Catherine Wang Clyde & Co LLP
In its Memorial on Preliminary Objections, the Respondent requests the following relief:
"For the foregoing reasons, the Respondent respectfully requests that the Tribunal issue an award:
(a) dismissing the Claimant's claims in their entirety and with prejudice on the grounds of lack of jurisdiction; and/or
(b) declaring that the Tribunal lacks rationae personae and / or rationae materiae jurisdiction in the present case; and / or
(c) ordering the Claimant to pay:
(i) the costs incurred by the Respondent in presenting its jurisdictional defence, including the cost of the Tribunal, ICSID and the legal and other costs incurred by the Respondent; and
(ii) interest on any costs awarded to the Respondent in an amount to be determined by the Tribunal; and / or
(d) awarding such further and other relief as the Tribunal may consider appropriate" (Resp. Mem., ¶ 182).
In its Counter-Memorial, the Claimant seeks the following relief:
"[...] BUCG respectfully requests from the Tribunal the following relief in the form of a Decision on objections to jurisdiction:
DISMISS all of the Respondent’s preliminary objections;
DECLARE that the dispute falls within the jurisdiction of ICSID and within the competence of the Tribunal; and
ORDER the Respondent to pay the costs of the proceeding related to the Respondent’s preliminary objections, including the Tribunal’s fees and expenses, and the cost of BUCG’s legal representation" (Cl.C-M, ¶ 148).
It is common ground that Article 25(1) of the ICSID Convention is not a State-to-State dispute resolution mechanism and is not open to State-owned companies as claimants when acting as agents of the State or when engaged in activities where they exercise governmental functions. It is common ground that in such circumstances State-owned enterprises are barred from bringing a claim under Article 25(1).9 In this respect, the Respondent cites Article 5 of the International Law Commission’s Draft Articles on State Responsibility.
The conduct of a person or entity which is not an organ of the State under article 4 but which is empowered by the law of that State to exercise elements of the government authority shall be considered an act of the State under international law, provided the person or entity is acting in that capacity in the particular instance.10
The Claimant contends that the emphasis should be on the words "in the particular instance."
Article 25(1) provides in pertinent part: "[T]he jurisdiction of the Centre shall extend to any legal dispute arising directly out of an investment, between a Contracting State (or any constituent subdivision or agency of a Contracting State designated to the Centre by that State) and a national of another Contracting State, which the parties to the dispute consent in writing to submit to the Centre. When the parties have given their consent, no party may withdraw its consent unilaterally" (emphasis added).
International Law Commission, Draft Articles on Responsibility of States for Internationally Wrongful Acts. Art. 5 (emphasis added) (CL-014).
Both Parties accept as applicable the functional test formulated in 1972 by Aron Broches, the first Secretary-General of ICSID and one of the principal drafters of the ICSID Convention, which he framed as follows:
[I]n today’s world the classical distinction between private and public investment, based on the source of the capital, is no longer meaningful, if not outdated. There are many companies which combine capital from private and governmental sources and corporations all of whose shares are owned by the government, but who are practically indistinguishable from the completely privately owned enterprise both in their legal characteristics and in their activities. It would seem, therefore, that for purposes of the Convention a mixed economy company or government-owned corporation should not be disqualified as a ‘national of another Contracting State’ unless it is acting as an agent for the government or is discharging an essentially governmental function.12 (Emphasis added)
The Tribunal notes the disjunctive "or" in the concluding sentence.
C. Schreuer, L. Malintoppi, A. Reinisch and A. Sinclair, The ICSID Convention: A Commentary (2nd edition, 2009), 161 (RL-003) (emphasis added).
The Broches test was adopted and applied in Ceskoslovenska Obchodini Banka, A.S. v. The Slovak Republic ("CSOB") as follows:
[I]t cannot be denied that for much of its existence, CSOB acted on behalf of the State in facilitating or executing the international banking transactions and foreign commercial operations the State wished to support and that the State’s control of CSOB required it to do the State’s bidding in that regard. But in determining whether CSOB, in discharging these functions, exercised governmental functions, the focus must be on the nature of these activities and not their purpose. While it cannot be doubted that in performing the above-mentioned activities, CSOB was promoting the governmental policies or purposes of the State, the activities themselves were essentially commercial rather than governmental in nature.13
In the result, having regard to the particular facts of the case, CSOB was permitted access to ICSID. The Respondent argues that the CSOB tribunal misapplied the Broches test,14 but in the view of the present Tribunal the important point about the CSOB case is the focus on a context-specific analysis of the commercial function of the investment, a focus with which the present Tribunal agrees.
Ceskoslovenska Obchodini Banka A.S. v. The Slovak Republic, ICSID Case No. ARB/97/4, Decision on Objections to Jurisdiction, 24 May 1999 (CL-053), ¶ 20 (emphasis added). See also Emilio Agustin Maffezini v. Kingdom of Spain, ICSID Case No. ARB/97/7, Decision on Objections to Jurisdiction, 25 January 2000 (CL-011, "Maffezini"), ¶ 80 and Rumeli Telekom A.S. and Telsim Mobil Telekomikasyon Hizmetleri A.S. v. Republic of Kazakhstan, ICSID Case No. ARB/05/16, Award, 29 July 2008 (CL-067), ¶ 212.
Resp. Reply, ¶ 13: "Two criticisms in particular have been levelled at the [CSOB] Tribunal. The first is that the Tribunal concluded that CSOB was an investor under the ICSID Convention despite finding that it had acted as a state agent - the first prong of the Broches Test. Second, the Tribunal failed to take into account the real purpose of CSOB’s activities in determining whether CSOB was performing governmental functions, focusing instead only on the nature of its activities." See M. Feldman, State-Owned Enterprises as Claims in International Investment Arbitration, ICSID Review, Vol. 31, No. 1 (2016) (RL-004) at 628-630.
the test that has been developed [to establish whether a particular entity in a state body] looks to various factors, such as ownership, control, the nature, purposes and objectives of the entity whose actions are under scrutiny, and to the character of the actions taken.18
The registration requirement under the Yemen Investment Law is the gateway to the privileges and protections set out in that law. But it does not serve as the gateway to the privileges and protections maintained by the China-Yemen BIT. The Tribunal thus agrees with the ICSID Tribunal in Desert Line v. Yemen:
The Arbitral Tribunal does not accept that a particular certificate from the Yemen General Investment Authority was necessary to bring the Claimant's investment under the Ambit of the BIT.
[...]
The [Yemeni Investment Law] does not purport to regulate all investments in Yemen, but only those whose promoters wish to benefit by license from its specific advantages, which are not coterminous with those in the BIT.25
B. Second Objection Ratione Materiae- Yemen Contends that it Consented to ICSID Arbitration Only in Respect of Disputes Limited to the Quantum of Compensation
The jurisdiction of the Centre shall extend to any legal dispute arising directly out of an investment between a Contracting State (or any constituent subdivision or agency of a Contracting State designated to the Centre by that State) and a national of another Contracting State, which the parties to the dispute consent in writing to submit to the Centre. When the parties have given their consent, no party may withdraw its consent unilaterally.26
At the heart of the Respondent’s objection in this respect is Article 10 of the BIT, which sets out a scheme providing options "at the choice of the investor" for the resolution of investment disputes as follows:
1. Any dispute between one Contracting Party and an investor of the other Contracting Party relating to an investment shall, as far as possible, be settled amicably through deliberations and negotiations between the parties to the dispute.
2. If the dispute cannot be resolved by the parties through direct arrangements for amicable negotiations within six months from the date on which a request for settlement is submitted in writing, such dispute may be submitted at the choice of the investor to:
(a) a competent court of the Contracting Party in the territory of which the investment has been made; or
(b) the International Centre for the Settlement of Disputes (ICSID) which was established by the Convention on the Settlement of Investment Disputes Between States and Nationals of Other States opened for signature at Washington DC on March 18, 1965, for arbitration.
For this purpose, either Contracting Party shall give its irrevocable consent to the submission of any dispute relating to the amount of compensation for expropriation for resolution under such arbitration procedure. Other disputes submitted under such procedure shall be mutually agreed upon between both Contracting parties.
3. No Contracting Party, being a party to a dispute, may raise any objection at any stage of the arbitration proceedings or during the course of the enforcement of an arbitral award on the ground that the investor, being the other party to the dispute, can receive compensation that covers all or part of its losses in accordance with an insurance policy.
4. The arbitral tribunal shall render its awards in accordance with the domestic laws (including rules relating to the conflict of laws) of the Contracting Party which is a party to the dispute and which accepts an investment, the provisions of this Agreement, the provisions of any special agreements entered into for the purpose of such investment and principles of international law.
5. The arbitral awards shall be final and binding upon both Contracting Parties. Each Contracting Party undertakes to enforce such awards in accordance with its domestic laws.27
CL-001 (Revised), BIT, Art. 10 (emphasis added).
Article 31(1) of the VCLT instructs the Tribunal to look to the text, context and both the object and purpose of the Treaty to ascertain its correct meaning, in conjunction with the other elements set out in subsections (2), (3) and (4) of Article 31. Reference is permitted to be made to "supplementary means" under Article 32 only where the meaning derived under Article 31 is otherwise ambiguous, obscure, manifestly unreasonable or absurd.32 As will be seen, the Tribunal does not consider it necessary in this case to resort to the "supplementary means" referenced in Article 32.
VCLT (RL-001), Arts. 31 and 32 provide as follows:
"Article 31. General Rule of Interpretation
1. A treaty shall be interpreted in good faith in accordance with the ordinary meaning to be given to the terms of the treaty in their context and in light of its object and purpose.
2. The context for the purpose of the interpretation of a treaty shall comprise, in addition to the text, including its preamble and annexes:
(a) Any agreement relating to the treaty which was made between all the parties in connection with the conclusion of the treaty;
(b) Any instrument which was made by one or more parties in connection with the conclusion of the treaty and accepted by the other parties as an instrument related to the treaty.
3. There shall be taken into account, together with the context:
(a) Any subsequent agreement between the parties regarding the interpretation of the treaty or the application of its provisions;
(b) Any subsequent practice in the application of the treaty which establishes the agreement of the parties regarding its interpretation;
(c) Any relevant rules of international law applicable in the relations between the parties.
4. A special meaning shall be given to a term if it is established that the parties so intended.
Article 32. Supplementary Means of Interpretation
Recourse may be had to supplementary means of interpretation, including the preparatory work of the treaty and the circumstances of its conclusion, in order to confirm the meaning resulting from the application of article 31, or to determine the meaning when the interpretation according to article 31:
(a) Leaves the meaning ambiguous or obscure; or
(b) Leads to a result which is manifestly absurd or unreasonable."
Much of the argument about Article 10 turns on its relationship with Article 4 of the BIT which provides that "nationalization, expropriation, or any other measures having a similar effect" will not violate the BIT provided that four stated conditions are satisfied; namely, that the expropriation is: (i) in the public interest of the contracting state; (ii) done by means of a "legal procedure"; (iii) without discrimination; and (iv) "against compensation". A forcible taking by the state that fails any one of the four conditions will constitute a violation of the treaty.33
CL-001 (Revised), BIT, Art. 4 provides:
"Article 4 Expropriation and Compensation
1. Any measures of nationalization, expropriation, or any other measures having a similar effect or of a similar nature (hereinafter referred to as ‘expropriation’) against the investments of investors of the other Contracting Party which might be taken by a Contracting Party shall satisfy all the following conditions:
(a) for the public interests;
(b) by legal procedure;
(c) without discrimination;
(d) against compensation.
2. The compensation mentioned in item (d) of Paragraph 1 of this Article shall be equivalent to the market value of the investments expropriated immediately before the time when the expropriation takes place or is known to the public.
3. The determination and payment of compensation shall be made promptly without undue delay. Compensation shall be paid to investors by means of a convertible currency, and be freely transferable" (emphasis added).
In terms of the options for dealing with the issue of liability, it is always open to the claimant in any event to sue the government, if it chooses, in its host state....
The other option they would have in terms of our argument, which is that liability has to be determined separately and naturally prior, is that it would be open to them to run a contractual arbitration and, in the event that contractual arbitration established some sort of liability, which liability fitted within the treaty, then they would be able to bring that finding from the first arbitration in order to try to get jurisdiction here.
So if they can say that - - if a Tribunal determined, if a contractual Tribunal determined, as it might do - - it might not, it might do - - that there had been expropriation, for example, then they could bring that to this Tribunal, but the natural way in which they would do it would be to go to court in Yemen.36
There is, of course, some irony in having English speaking lawyers making detailed and nuanced arguments dissecting an English text when the text itself has no official status whatsoever. The dissection focused on the words "relating to" the amount of compensation for expropriation. Learned argument was presented as to whether the words "relating to" constituted an overly broad interpretation of the Chinese character ("You Guan"). In the view of the Claimant, the Chinese character has a broad meaning equivalent to "involving" or "concerning" or "relating to". The definition of "You Guan" in the Oxford Chinese Dictionary is very broad:
[H]ave something to do with: [for example] The disease might have something to do with smoking.39
As "the amount of compensation" bears a necessary relationship to liability, or at least has "something to do with it", the Claimant says the words "relating to" are necessarily broad enough to support the jurisdiction of an ICSID Tribunal over questions of liability.
Oxford Chinese Dictionary (C-089), 911
The opening text of Paragraphs 1 and 2 of Article 10 is very broad. The opening language is repeated here for ease of reference:
1. Any dispute between one Contracting Party and an investor of the other Contracting Party relating to an investment shall, as far as possible, be settled amicably through deliberations and negotiations between the parties to the dispute.
2. If the dispute cannot be resolved by the parties through direct arrangements for amicable negotiations within six months from the date on which a request for settlement is submitted in writing, such dispute may be submitted at the choice of the investor to:
(a) a competent court of the Contracting Party in the territory of which the investment has been made; or
(b) the International Centre for the Settlement of Investment Disputes (ICSID) which was established by the Convention on the Settlement of Investment Disputes Between States and Nationals of Other States opened for signature at Washington DC on March 18, 1965, for arbitration.41
CL-001 (Revised), BIT, Art. 10.1, 10.2 (emphasis added).
In the English text, the words "any disputes" are followed in paragraph 2 by reference to "the dispute" followed by the fork in the road. According to orthodox principles of treaty interpretation, both of the investor’s options must be given meaning and substance. The principle of effet utile or "effective interpretation" requires that international agreements be interpreted "so as to give them their fullest weight and effect consistent with the normal sense of the words and with other parts of the text and in such a way that a reason and meaning can be attributed to every part of the text."43 An interpretation that nullifies either of the choices granted to the investor is to be avoided.
See, for example, the report of the Claimant’s argument in respect of the China-Laos BIT before the Singapore Court of Appeal in Sanum v. Laos: "Sanum contends that if the submission of the Lao Government is correct and if an investor must first go to a competent national court to determine whether an impermissible expropriation lias occurred (on the basis of the Narrow Interpretation of Art 8(3)), it would very likely find itself precluded from then submitting any dispute, on the amount of compensation it claims is due to it, to arbitration since the national court would already have determined the issue of compensation. This would render Art 8(3) wholly ineffective since, practically speaking, investors would never be able to bring a dispute to investor-state arbitration under the PRC-Laos BIT" (Sanum Investments Limited v. Government of the Lao People’s Democratic Republic, [2016] SGCA 57, Judgment, 29 September 2016 (CL-086, "Sanum"). ¶ 128).
The fork in the road ("or") is followed by the contentious language at the conclusion of paragraph 2 which is central to the jurisdictional objection, namely:
For this purpose, either Contracting Party shall give its irrevocable consent to the submission of any dispute relating to the amount of compensation for expropriation for resolution under such arbitration procedure. Other disputes submitted under such procedure shall be mutually agreed upon between both Contracting parties.45
For convenience this concluding language will be called the "proviso" in this ruling.
CL-001 (Revised), BIT, Art. 10.2 (emphasis added).
The Tribunal first refers to the specific wording used by Article 8(3). The BIT uses the word "involving" which, according to the Oxford Dictionary means "to enfold, envelope, entangle, include." A bona fide interpretation of these words indicate that the only requirement established in the BIT is that the dispute must "include" the determination of the amount of a compensation, and not that the dispute must be restricted thereto. Obviously, other wording was available, such as "limited to" or "exclusively", but the wording used in this provision reads "involving."47
On the Respondent’s interpretation, Yemen can unilaterally deny a claimant access to an ICSID tribunal simply by refusing to admit some aspect of liability. If Yemen puts in doubt the alleged expropriation, the claim must go to the courts of Yemen for determination.50 However, by reason of Article 4, the Yemeni court would not be able to determine the question of expropriation without addressing each of the four conditions listed in Article 4, including whether effective and appropriate compensation has been paid. The Respondent agrees that such is the mandate of the Yemeni court. It submits that:
Pursuant to Article 4.4 of the China-Yemen BIT, expropriation is permitted if it is "against compensation", which not only includes potential issues as to the amount of compensation, but also the means of such compensation and/or whether any compensation has been paid at all. In contrast, Article 10.2 specifically limits the Tribunal’s scope of jurisdiction to "the amount of compensation."51
However, having regard to the fork in the road, and the issue of quantum having then been decided by the courts of Yemen, the investor would be precluded from an ICSID arbitration to re-litigate the amount of compensation.
The Respondent states that in light of the hostilities in Yemen, it has been unable to collect accurate information about how a Yemeni court of competent jurisdiction would approach the issue of expropriation. As a result, and without objection on the part of the Claimant, the Respondent developed its argument in this respect by reference to the applicable laws of China and in particular a codification of Chinese Administrative Law adopted by the 7th National People’s Congress on 4 April 1989 with effect from October 1, 1990 in respect of which Mr. Patrick Zheng, one of the counsel appearing for the Respondent, made helpful submissions.
Article 70 of the Chinese law states that "this law shall be applicable to foreign nationals, stateless persons and foreign organizations..." as well as Chinese nationals. However, Article 72 provides that "if an international treaty concluded by the [PRC] contains provisions different from those found in [Chinese administrative] law, the provisions of the international treaty shall apply" (see Tr. Day 2, Mr. Benjamin Knowles, 297:5 et seq.).
Resp. Reply, ¶ 77.
In this situation, the ICSID tribunal in Tza Yap Shum interpreted the fork in the road provision on the China-Peru BIT to necessitate an interpretation of the equivalent provision to Article 10 to grant to the ICSID tribunal full jurisdiction over the issue of liability as well as quantum:
The Tribunal concludes that to give meaning to all the elements of the article, it must be interpreted that the words "involving the amount of compensation for expropriation" includes not only the mere determination of the amount but also any other issues normally inherent to an expropriation, including whether the property was actually expropriated in accordance with the BIT provisions and requirements, as well as the determination of the amount of compensation due, if any. In the opinion of the Tribunal, a contrary conclusion would invalidate the provision related to ICSID arbitration since according to the final sentence of Article 8(3), turning to the courts of the State accepting the investment would preclude definitely the possibility of choosing arbitration under the ICSID Convention. Consequently, since the Claimant has filed a prime facie claim of expropriation, the Tribunal, pursuant to Articles 25 and 41 of the ICSID Convention and Rule 41 of the Arbitration Rules, considers that it is competent to decide on the merits of the expropriation claim filed by Claimant.53
CL-033, Tza Yap Shum, ¶ 188 (emphasis added). The decision was upheld in Tza Yap Shum v. Republic of Peru, ICSID Case No. ARB/07/6, Decision on Annulment, 12 February 2015 (CL-082).
The Singapore Court of Appeal in Sanum v. Laos, in its analysis of the China-Laos BIT,55 concluded that the "fork in the road" provision would, if Article 10.2 were "narrowly" interpreted, effectively deprive the investor of both choice and protection:
... it is entirely open to the host State to avoid arbitration over the amount of compensation for indirect expropriation simply by not submitting the dispute on liability to its municipal courts. [...] In such cases, the investor would then be compelled to bring a claim to a national court for a ruling that the host State had committed an expropriatory act but in so doing, it may be barred from bringing a dispute on compensation to arbitration. It should also be added that even in the rare cases of direct expropriation, host States would be in a position effectively to avoid arbitration by simply denying that they had engaged in expropriatory acts.[...] This would once again compel the investor to resort to the national courts, thereby barring a claim in arbitration.56
See CL-086, Sanum, ¶ 123. Article 8 of the China-Laos BIT reads:
"Article 8
1. [..]
2. If the dispute cannot be settled through negotiation within six months, either party to the dispute shall be entitled to submit the dispute to the competent court of the Contracting State accepting the investment.
3. If a dispute involving the amount of compensation for expropriation cannot be settled through negotiation within six months as specified in paragraph 1 of this Article, it may be submitted at the request of either party to an ad hoc arbitral tribunal. The provisions of this paragraph shall not apply if the investor concerned has resorted to the procedure specified in the paragraph 2 of this Article" (emphasis added).
CL-086, Sanum, ¶ 133. The Singapore Court of Appeal dealt persuasively with this weakness in the Respondent’s approach: "In our judgment, the Lao Government’s interpretation of Art 8(3) of the PRC-Laos BIT is not tenable. The words of the provision do not seem to us to be capable of accommodating the segregation of an expropriation claim in the way it was suggested such that the question of liability may be determined by the national courts leaving the issue of the quantum of compensation to be heard by an arbitral tribunal. In our judgment, the words ‘[t]he provisions of this paragraph shall not apply if the investor concerned has resorted to the procedure specified in paragraph 2’ means that if any dispute is brought to the national court, the claimant will no longer be entitled to refer any aspect of that dispute to arbitration. Hence once an expropriation claim is referred to the national court, no aspect of that claim can then be brought to arbitration. It should be noted that this does not mean that any and every dispute relating to expropriation may be referred to arbitration. As provided in Art 8(3), this only avails if the dispute does involve a question as to the amount of compensation," CL-086, Sanum, ¶ 130 (emphasis in original).
[...]
Intending to create favourable conditions for investment by investors of one Contracting Party within the territory of the other Contracting Party;
Recognizing that the reciprocal encouragement, promotion and protection of investment will stimulate business communication of investors and will increase prosperity in both countries;
Desiring to intensify the economic cooperation between both countries on the basis of equality and mutual benefits;
Have agreed as follows [... ]58
The Tribunal agrees with the Respondent that a "balanced" approach to such general language is required.59 As stated in the RosInvest award, care must be taken not to use general aspirational treaty preambles to re-write a narrow jurisdictional clause in favour of an investor:
As derived from the fact that the protection and promotion of foreign investment is not the sole aim of investment treaties, particular emphasis is further placed on the need for a balanced interpretation rather than an interpretation in favour of the investor [...] Especially against the background that preambles usually contain broadly worded object and purpose clauses to protect and promote foreign investments even in case of investment treaties which do not contain any right to international arbitration, the interpretative exercise should not be diverted from the actual wording of Article 8(1) or lead to a re-write of a narrow jurisdictional clause [...].60
Resp. Reply, ¶ 89.
RosInvestCo UK Ltd. v. Russian Federation, SCC Case No. V 079/2005, Award on Jurisdiction, 5 October 2007 (CL-065, "RosInvest), ¶ 83 (emphasis added).
• Vladimir Berschader and Moise Berschader v. the Russian Federation (SCC Case No. 080/2004), Award, 21 April 2006, CL-059 ("Berschader");
• RosInvestCo UK Ltd. V. the Russian Federation, SCC Case No. Arb. V079/2005, Award on Jurisdiction, 5 October 2007, CL-065 ("RosInvest"); and
• Renta 4 SVSA et ctl v. the Russian Federation, SCC Case No. V 024/2007, Award on Preliminary Objections, 20 March 2009, CL-032 ("Renta 4").
In Berschader (award rendered in 2006), a Belgian construction contractor sought arbitration of a claim against the Russian Federation under an investment treaty concluded among Belgium, Luxembourg and Russia. The equivalent dispute resolution clause provided as follows:
ARTICLE 10
1. Any dispute between one Contracting Party and an investor of the other Contracting Party concerning the amount or mode of compensation to be paid under Article 5 of the present Treaty shall be the subject of a written notice, accompanied by a detailed memorandum, to be submitted by the investor to the Contracting Party involved in the dispute....65
CL-059/RL-019, Berschader, ¶ 47 (emphasis added).
In RosInvest (award rendered in 2007), a British investor in the Russian oil company Yukos complained that its investment was rendered "nearly valueless" by sham "arbitrary incremental tax assessments" imposed by the Russian Federation. It sought arbitration under the UK-Russia BIT. The dispute resolution clause in RosInvest provided as follows:
ARTICLE 8
Disputes between an Investor and the Host Contracting Party
(1) This Article shall apply to any legal disputes between an investor of one Contracting Party and the other Contracting Party in relation to an investment of the former either concerning the amount or payment of compensation under Articles 4 or 5 of this Agreement, or concerning any other matter consequential upon an act of expropriation in accordance with Article 5 of this Agreement, or concerning the consequences of the non-implementation, or of the incorrect implementation, of Article 6 of this Agreement.
(2) Any such disputes which have not been amicably settled shall, after a period of three months from written notification of a claim, be submitted to international arbitration if either party to the dispute so wishes.67
CL-065, RosInvest, ¶ 23 (emphasis added).
The Claimant, on the other hand, relies on the later case of Renta 4 v. Russia (award rendered in 2009), in which the dispute resolution clause provided:
Article 10
Disputes between one Party and investors of the other Party
1. Any dispute between one Party and an investor of the other Party relating to the amount or method of payment of the compensation due under Article 6 of this Agreement, shall be communicated in writing [...]. [The parties shall] as far as possible, endeavour to settle the dispute amicably.
2. If the dispute cannot be settled thus within six months of the date of the written notification referred to in paragraph 1 of this article, it may be referred to by [sic] either of the following, the choice being left to the investor:
- An arbitral tribunal in accordance with the Regulations of the Institute of Arbitration of the Chamber of Commerce in Stockholm;
- The ad hoc arbitral tribunal established in accordance with the Arbitration Rules of the United Nations Commission on International Trade Law (UNCITRAL).69
CL-032, Renta 4, ¶ 5 (emphasis added).
Ultimately, the Renta 4 tribunal’s decision is consistent with the importance attached by the present Tribunal to the object and purpose of the BIT, which the Renta 4 tribunal expressed as follows:
Yet some considerations of purpose have a solid foundation. It must be accepted that investment is not promoted by purely formal or illusory standards of protection. It must more specifically be accepted that a fundamental advantage perceived by investors in many if not most BITs is that of the internationalisation of the host state’s commitments. It follows that it is impermissible to read Article 10 of the BIT as vanishingly narrow internationalisation of either Russian’s or Spain’s commitment. [... ] [I]f there is no obligation to make compensation the arbitration clause would never operate. The dispute would not be internationalised if the respondent State could simply declare whether there is an obligation to compensate. Either signatory State could thus by its fiat (including that of its courts given the State’s responsibility for their acts under international law) ensure that there would never be an arbitration under Article 10. This would be an illusion which the Tribunal cannot accept as consonant with Article 31 of the Vienna Convention if ever that Article is to be given full weight.72
The Tribunal agrees with this aspect of the Renta 4 decision.
CL-032, Renta 4, ¶ 56 (emphasis added).
The MFN Clause (Article 3.1) provides as follows:
Article 3
Investment Treatment
1. Each Contracting Party shall ensure that fair and equitable treatment is given to the investments of the other Contracting Party in its territory, and such treatment shall, in accordance with its laws and regulations, be no less favourable than the treatment accorded to investments of the most favoured nation, if the latter is more favourable.
Each Contracting Party shall, in accordance with its laws and regulations, ensure that the treatment accorded to investors of the other Contracting Party in its territory with respect to the activities relating to their investments shall be no less favorable than the treatment accorded to its domestic investors or no less favourable than the treatment accorded to investors of the most favoured nation, with the more favourable treatment to apply.76
CL-001 (Revised), Art. 3.1 (emphasis added).
[D]ispute resolution provisions in a specific treaty have been negotiated with a view to resolving disputes under that treaty. Contracting States cannot be presumed to have agreed that those provisions can be enlarged by incorporating dispute resolution provisions from other treaties negotiated in an entirely different context.77
(i) within the meaning given to those terms in the BIT, which defines the framework of the consent given by the Respondent; and also
(ii) within the meaning given to those terms in the ICSID Convention.
The Joy Mining tribunal emphasised the pre-eminence of the ICSID Convention over the terms of the BIT in jurisdictional terms:
The parties to a dispute cannot by contract or treaty define as investment, for the purpose of ICSID jurisdiction, something which does not satisfy the objective requirements of Article 25 of the Convention.84
This passage was explicitly endorsed by other ICSID tribunals.
It is those bilateral and multilateral treaties which today are the engine of ICSID’s effective jurisdiction. To ignore or depreciate the importance of the jurisdiction they bestow upon ICSID, and rather to embroider upon questionable interpretations of the term "investment" as found in Article 25(1) of the Convention, risks crippling the institution.85
The jurisdiction of the Centre shall extend to any legal dispute arising directly out of an investment, between a Contracting State [...] and a national of another Contracting State, which the parties to the dispute consent in writing to submit to the Centre.
The doctrine generally considers that investment infers: contributions, a certain duration of performance of the contract and a participation in the risks of the transaction [...] In reading the Convention’s preamble, one may add the contribution to the economic development of the host State of the investment as an additional condition.
In reality, these various elements may be interdependent. Thus, the risks of the transaction may depend on the contributions and the duration of performance of the contract. As a result, these various criteria should be assessed globally even if, for the sake of reasoning, the Tribunal considers them individually here.87
1. Each Contracting Party shall encourage investors of the other Contracting Party to make investments in its territory and accept such investments in accordance with its laws and regulations.
[...]
2. Investments of investors of either Contracting Party shall be accorded fair and equitable treatment and shall enjoy full and complete protection and security in the territory of the other Contracting Party subject to any measures which are necessary for maintaining public order. [,..]91
The BIT contains a detailed definition of what constitutes an investment, under which the commitment of resources under a contract to be performed in the other Contracting State explicitly qualifies as an investment.
Article 1
Definitions
In this Agreement,
1. The term "investment" means, every kind of asset and capital invested directly or indirectly by investors of one Contracting Party in accordance with the laws and regulations of the other Contracting Party in the territory of the latter, including in particular but not limited to:
(a) movable and immovable property as well as any other property rights such as mortgages, pledges, real securities, usufructs and similar rights;
[...]
(c) creditor’s rights and claims to any performance having an economic value; [...]92
CL-001 (Revised), BIT, Art. 1 (emphasis added).
With regard to the risks incurred by the Italian companies, these flow from the nature of the contract at issue. The Claimants, in their reply memorial on jurisdiction, gave an exhaustive list of the risks taken in the performance of the said contract. Notably, among others, the risk associated with the prerogatives of the Owner permitting him to prematurely put an end to the contract, to impose variations within certain limits without changing the manner of fixing prices; the risk consisting of the potential increase in the cost of labour in case of modification of Moroccan law; any accident or damage caused to property during the performance of the works; those risks relating to problems of coordination possibly arising from the simultaneous performance of other projects; any unforeseeable incident that could not be considered as force majeure and which, therefore, would not give rise to a right to compensation; and finally those risks related to the absence of any compensation in case of increase or decrease in volume of the work load not exceeding 20% of the total contract price.
It does not matter in this respect that these risks were freely taken. It also does not matter that the remuneration of the Contractor was not linked to the exploitation of the completed work. A construction that stretches out over many years, for which the total cost cannot be established with certainty in advance, creates an obvious risk for the Contractor.93
• It was pointed out in Toto v. Lebanon (Jurisdiction) that a construction contract in which the execution of the works extends over a substantial period of time involves by definition an element of risk.94
• It is obvious that construction of an international air terminal worth in excess of a hundred million dollars contributes to the host State’s economic development.
Get access to the most extensive & reliable source of information in arbitration
REQUEST A FREE TRIALAlready registered ?