"Leave to appeal is granted on the following question of law, namely whether there was an implied term of the subject time charter having the effect that where the vessel was off hire under clause 69 after a failed holds inspection and the Master advised that hold cleaning had been completed and called for a reinspection, the charterer was obliged 'to have the vessel re-inspected without delay'."
"Vessel's holds on delivery or on arrival 1st load port to be clean swept/washed down by fresh water and dried so as to receive Charterers intention cargoes in all respects free of salt, rust scale and previous cargo residue to the satisfaction of the independent surveyor.
If vessel fails to pass any holds inspection the vessel to be placed off-hire until the vessel passes the same inspection and any expense/time incurred thereby for Owners' account."
i. The holds were inspected by a surveyor from the cargo and vessel inspection service, SGS, between 0700 and 1230 on 16 February 2017 but were failed due to the presence of rust, paint flakes and cargo residue: Award, para 9.
ii. The Owners submitted that SGS was not an independent surveyor, being appointed by the shippers, but the Tribunal considered that the complaint was raised too late in the proceedings to be considered and in any event that nothing was said contemporaneously: Award, para 10.
iii. At 1530 on 19 February 2017, the Master of the vessel notified the agents that the vessel had been cleaned and requested a reinspection: Award, para 11. The vessel's holds were clean at that point: Award, para 16.
iv. The vessel had been ordered off-berth at 1430 that day (para. 17) and she shifted to the inner anchorage at 2218: Award, para 11.
v. The vessel reberthed at 2042 on 3 March 2017: Award, para 11.
vi. At 0700 on 4 March 2017, the vessel holds were re-inspected by SGS with reinspection completed some four hours later, by 1100, and the vessel passed the inspection: Award, para 12.
"[I]t appeared that a reinspection taking place at anchorage was not possible to arrange but no persuasive reasoning was given for this which we concluded caused further delay to the vessel passing the reinspection which could not be the fault of the Owners": Award, para 24.
"The Owners contended that it was an implied term of the charter party that required the Charterers to carry out any reinspection with reasonable diligence and without any undue delay and the Charterers were in breach of that implied term because the reinspection took so long to arrange": Award, para 12.
"We found the Owners' implied term argument most persuasive. We decided that, once the vessel advised that cleaning had been completed and the Master called for a reinspection, it was reasonable for the Charterers to be under an implied obligation to have the vessel re-inspected without delay. We concluded that keeping the vessel at anchor from 19 February until 3 March, a period of about 12 days, was unreasonable. The Charter Party did not contain any provision for dealing with such a situation and consequently without such an implied obligation the Charterers would be under no obligation to keep any delays to a minimum. In fact, without such an implied obligation they would have been under no pressure to expedite the re-berthing at all and we did not accept that the Owners could be responsible for such delays or loss of time in such circumstances and therefore we find that their claim succeeds in full in the amounts of USD$106,611.92 (US$110,765.63 less 3.75% address commission) in respect of hire plus US$16,308.93 in respect of bunkers."
"The commercial arbitrators [in LMLN 17/10] accepted the need for the implied term… We adopt the arbitrators' reasoning for that…. Commercially any other interpretation would permit [the charterers] to do nothing, potentially for months – during which time they paid no hire while the ship sat there ready."
"In the tribunal's view, it seemed wholly reasonable that, in circumstances such as prevailed in the present case, the charterers should be under some duty to act reasonably in ensuring that their surveyor did not delay any reinspection. Not only was that reasonable, but it was necessary to give business efficacy to the contract, since otherwise the charterers might delay reinspection until whatever time suited them, e.g., when a berth became available or when they had a cargo stem. Further, there was no doubt that, if asked at the time of entering into the contract, the parties would both have said that of course some such term was to be implied."
(a) any available arbitral process of appeal or review, and
(b) any available recourse under section 57 (correction of award or additional award)".
"27(a) In addition to the powers set out in section 57 of the Act, the tribunal shall have the following powers to correct an award or to make an additional award:
(i) The tribunal may on its own initiative or on the application of a party correct any accidental mistake, omission or error of calculation in its award.
(ii) The tribunal may on the application of a party give an explanation of a specific point or part of the award."
"Questions as to the proper construction of a contract (or the existence of a contractual obligation) are treated as pure questions of law. However, often these questions are fact specific, for example whether a term is to be implied as a matter of business efficacy, and will depend on the relevant factual matrix, including market practice and what was reasonably known to the parties. If the question is highly fact specific a judge may be more likely to give weight to the tribunal's market experience and will only reverse the decision if satisfied that the tribunal has come to the wrong answer."
Get access to the most extensive & reliable source of information in arbitration
REQUEST A FREE TRIALAlready registered ?