¶(¶) | Paragraph(s) |
§(§) | Section(s) |
p(p). | Page(s) |
Addvante | AddVANTE FORENSE and CONCURSAL SLL, the Claimant's expert for the evaluation of damages suffered |
ATA | Astrom Technical Advisors, SL, Claimant's expert for the technical-economic valuation of La Isabela. |
CESCE | Spanish Export Credit Insurance Company |
CDEEE | Dominican Corporation of State Electric Companies |
ICSID | International Center for Settlement of Investment Disputes |
CNE | National Energy Commission |
Final Concession or Concession Agreement or Final Concession Agreement | Final Concession Agreement for the Exploitation of Electric Generation Works from Primary Renewable Sources of Wind Energy entered into between Dominicana Renovables, SL, and the Dominican State, dated January 23, 2013 |
Provisional Concession | Resolution CNE-CP-0005-2009, by which the CNE grants Dominicana Renovables a provisional concession, dated February 9, 2009 |
Answer to the Petition | Answer to the Petition for Arbitration presented by the Respondent on May 28, 2018 |
PPA | Power purchase agreement |
International Tribunal of Arbitration of the International Chamber of Commerce | |
Timeline | Timeline of events, prepared by the Parties by mutual agreement, dated May 29, 2020. |
Dominicana Renovables, Company, Concessionaire or Claimant | Dominicana Renovables, SL |
State or Respondent | The sovereign State of the Dominican Republic |
ETED | Dominican Electrical Transmission Company |
General Electricity Law | General Electricity Law No. 125-01, dated July 26, 2001 |
Law 57-07 | Law No. 57-07 on Incentives for the Development of Renewable Energy Sources and Special Regimes, dated May 7, 2007 |
Organic Law of Public Administration | Law No. 247-12, dated August 14, 2012 |
MEM | Ministry of Energy and Mines of the Dominican Republic |
Opinion | Letter sent by the former legal director of the Ministry of Energy and Mines, Susana Gautreau, Esq., to the Vice Minister of Energy, Ernesto Vilalta, on March 13, 2017 |
La Isabela Wind Farm, Wind Farm, Park, or Project | Renewable energy project to be developed by Dominicana Renovables in the Province of Puerto Plata, Dominican Republic, authorized by the Dominican State through the Final Concession granted on January 4, 2013 |
Parties | Dominicana Renovables, SL, and the Dominican Republic, jointly |
Special Power | Presidential Special Power No. 121-15 granted to the Executive Vice President of CDEEE, dated November 27, 2015 |
Protocol | Protocol of mandatory general conditions for the signing of contracts for the sale of electrical energy from renewable energy sources by the Dominican Corporation of State Electric Companies, dated September 9, 2014 |
Rules | Decree No. 202-08 by which Law 57-07 on Renewable Energy Incentives and Special Regimes dated May 7, 2007 is regulated |
ICC Rules | International Chamber of Commerce Rules of Arbitration, effective as of March 1, 2017 |
Secretariat | Secretariat of the International Tribunal of Arbitration of the International Chamber of Commerce |
SENI | National Interconnected Electric System |
SIE | Superintendency of Electricity |
Request for Arbitration | Request for Arbitration presented by Dominicana Renovables, SL, dated January 16, 2018 |
Francisco A. Rodriguez
Luis A. Pérez
Rebeca E. Mosquera
AKERMAN LLP
Three Brickell City Centre
98 Southeast Seventh Street, Suite 1100
Miami, Florida 33131-1714
United States
francisco.rodriguez@akerman.com
luis.perez@akerman.com
rebeca.mosquera@akerman.com
Luis Soto
SOTO ABOGADOS
Calle C (El Cayao) No. 11
Ensanche Serrallés
Santo Domingo, Dominican Republic
luis@sotolaw.com
Antoliano Peralta
Noelia Rivera
Nathalie Hernández
Sara Patnella
Legal Advisor to the Executive Branch
Office of the Legal Advisor to the Executive Branch (CJPE)
National Palace, Avenida México esq. Dr. Delgado
Gascue, Santo Domingo D.N.
Dominican Republic
antolianoperalta@consultoria.gov.do
noeliarivera@consultoria.gov.do
nhernandez@consultoria.gov.do
spatnella@consultoria.gov.do
Eduardo Silva Romero
Catalina Echeverri Gallego
DECHERT (PARIS) LLP
32, rué de Monceau
75008 París
Francia
eduardo.silvaromero@dechert.com
catalina, echeverrigall ego@dechert.com
Juan Felipe Merizalde
DECHERT LLP
1900 K Street, NW
2006 Washington D.C.
United States
juanfelipe.merizalde@dechert.com
alldominicanarenovables@dechert.com
Alvaro Galindo
114 Franklin St.
Alexandria
Virginia 22314
United States
ahg5@georgetown.edu
CONFLICT RESOLUTION: Any Dispute arising from this Agreement, or related thereto, including its breach, termination, validity or arbitrability will be submitted to arbitration and decisively resolved, in accordance with the Rules of Arbitration, by three (3) arbitrators with a command of the English and Spanish languages. The petitioner will nominate one (1) arbitrator in the Request for Arbitration (the "Request"), the respondent will nominate one (1) arbitrator within thirty (30) days of receipt of the Request, and the ICC will nominate a third arbitrator, who will act as chair of the Arbitration Tribunal, within thirty (30) days of the appointment of the Second Arbitrator. If either Party does not nominate an arbitrator in accordance with the provisions of this Article, then the ICC will appoint such arbitrator. These arbitrators appointed by the ICC will be experienced in matters related to concessions or licenses for the establishment or operation of electric companies. power purchase agreements, and if possible, in agreements between independent energy producers or generators and distribution or state-owned companies, in the Dominican Republic or in any other jurisdiction. No arbitrator may be an employee or agent, or have previously served as an employee or agent, of any Party. It is expressly agreed that the Parties may reach an agreement, at any time, that resolves the dispute that gave rise to the arbitration process. The International Arbitration Process will be conducted in Spanish, or through simultaneous interpretation into that language, and will be based in Miami, Florida, United States of America.
Paragraph I: The Parties, individually, bear full responsibility for any expenses they may incur during the course of the International Arbitration Process, for the payment of professional fees, and any other additional expenses, notwithstanding the right of reimbursement to which the prevailing party of the International Arbitration Process is entitled.
Paragraph II: THE DOMINICAN STATE unconditionally and irrevocably waives the defense of sovereign immunity with respect to its person and/or its property under the Applicable Laws of any jurisdiction, including, without limitation, in relation to: (a) the submission to arbitration of any disputes inherent to the Wind Farm and this Agreement: (b) the recognition, confirmation and/or enforcement of any arbitration award issued in the context of this arbitration: (c) notifications, jurisdiction, precautionary measures, garnishments, and coercive and enforceable procedures.
Paragraph III: THE DOMINICAN STATE AND THE CONCESSIONAIRE accept and agree that any award issued by the Tribunal will be final and binding and will not be subject to appeal, as well as that any competent court may issue a ruling recognizing and confirming the award. (...)
Oscar M. Garibaldi
809 Wincrest Place
Great Falls, Virginia 22066
United States
ogaribaldi@garibaldiarbitrator.com
Juan Pablo Cárdenas Mejía
Avenida Calle 72 No. 6-30 Piso 11
Bogotá, D.C.
Colombia
jpcm2001@yahoo.com
Stanimir A. Alexandrov
STANIMIR A. ALEXANDROV PLLC
1501 K Street N.W.
Suite C-072
Washington D.C., 20005
United States
salexandrov@alexandrovlaw.com
Members of the Arbitration Tribunal:
Mr. Stanimir Alexandrov, Chair
Mr. Oscar M. Garibaldi, Co-Arbitrator
Mr. Juan Pablo Cárdenas Mejía, Co-Arbitrator
Claimant's Representatives:
Francisco A. Rodríguez (Akerman, LLP)
Luis A. Pérez (Akerman, LLP)
Rebeca E. Mosquera (Akerman, LLP)
Alejandro E. Chevalier (Akerman, LLP)
Tracy Leal (Akerman, LLP)
Luis Soto (Soto Abogados)
Esteban Fernández Rosado (Dominicana Renovables)
Alejandro Bertola (Grupo BTD)
Andrés Llorden (Grupo BTD)
Victor Cusí Puig (Witness - Normawind)
Pablo Valera (Expert - ATA Renovables)
Ignacio Becares (Expert - ATA Renovables)
Iván Fernández (Expert - ATA Renovables)
David Martínez (Expert - AddVANTE)
Joan Jiménez (Expert - AddVANTE)
Julio Miguel Castaños (Expert - Castaños & Castaños)
Juan Luis Sendín Cifuentes (Expert - Garrido Forensic SL)
José Manuel Báez (Expert - Báez Mueses & Assoc.)
Respondent's Representatives:
Eduardo Silva Romero (Dechert LLP)
José Manuel García Represa (Dechert LLP)
Alvaro Galindo (Outside Consultant)
Juan Felipe Merizalde (Dechert LLP)
Catalina Echeverri (Dechert LLP)
Ana Durán (Dechert LLP)
Santiago Rojas Molina (Dechert LLP)
Laura Arboleda Gutiérrez (Dechert LLP)
Santiago Soto García (Dechert LLP)
Anne Driscoll (Dechert LLP)
Judith Alves (Dechert LLP)
Sofía Galindo Reyes (Dechert LLP)
Ernesto Lima (Dechert LLP)
Samuel Jegou (Dechert LLP)
Loïc Cropage (Dechert LLP)
Donnie Villanueva (Dechert LLP)
Flavio Darío Espinal (Office of the Legal Advisor to the Executive Branch - CJPE)
Jimena Conde (Office of the Legal Advisor to the Executive Branch - CJPE)
Nathalie Hernández (Office of the Legal Advisor to the Executive Branch - CJPE)
Sara Patnella (Office of the Legal Advisor to the Executive Branch - CJPE)
Johanna Frías (Office of the Legal Advisor to the Executive Branch - CJPE)
Raysa Paulino (Ministry of Energy and Mines - MEM)
Manuel Batista (Dominican Corporation of State Electric Companies - CDEEE)
Nelson Burgos (National Energy Commission - CNE)
Matilde Balcácer (National Energy Commission - CNE)
Bons Blanco (National Energy Commission - CNE)
Michael de Lancer (Administrative Office of the President)
Gerardo Guzmán (Administrative Office of the President)
Moisés Mejía (Administrative Office of the President)
Pedro Espinal (Administrative Office of the President)
Santa Ramos (Witness - Dominican Corporation of State Electric Companies -CDEEE)
María Susana Gautreau (Witness - Ministry of Energy and Mines - MEM)
Rubén Jiménez Bichara (Witness - Dominican Corporation of State Electric Companies - CDEEE)
Juan Luis Villanueva (Witness - Independent Consultant)
George Reinoso (Expert - Independent Consultant)
Daniel Flores (Expert - Quadrant Economics LLC)
Juan Femando Riveros (Expert - Quadrant Economics LLC)
Darío Gatti (Expert - Quadrant Economics LLC)
Notwithstanding the aforementioned remittance, at the direction of the Executive Vice President of this CDEEE, it is our duty to inform you that the CDEEE is not adding new projects to the list of producers with whom it is in the process of closing on potential power purchase agreements (PPAs) for renewable energy at this time, until it is possible to determine how much energy from the source indicated can be tapped by the National Interconnected Electric System (SENI) in the short term, from these projects, without creating risks to its efficient operation. It is important to note that these producers were selected based on the age of their projects and their advanced status of administrative processing with the authorities in question.
In this respect, we wish to express to you that it is currently impossible for this CDEEE to initiate negotiations aimed at signing a PPA based on your project without first definitively establishing which of the ongoing projects will be effectively implemented and can be commercially operated. In any case, we note that any future contract for the purchase and sale of energy from renewable sources must be the result of a public bidding process carried out under the applicable regulations.
[It is aware of] the terms of the Protocol of general conditions for the signing of contracts for the sale of electrical energy from renewable energy sources established in Special Power No.121-15, and [wants] to declare [its] agreement and formal acceptance of the terms and the purchase price of energy for wind projects established therein.
PURPOSE OF THE AGREEMENT. The DOMINICAN STATE authorizes THE CONCESSIONAIRE to construct, install, operate and exploit, for its own benefit and at its own risk, ONE (1) wind farm for the generation of electricity, with a maximum capacity of FIFTY (50) MW ... The total capacity may be expanded to double its size when THE CONCESSIONAIRE has installed at least 50% of the original size granted, subject to meeting the timelines established by the regulations.
RIGHTS OF THE CONCESSIONAIRE: Under this agreement, the CONCESSIONAIRE will have the right to perform the following activities, including, but not limited to:
c) Build, operate and exploit, under its sole and direct ownership, the Generation Facilities up to a maximum of 50MW;
d) Execute power purchase agreements and/or sell its energy production in SENI under the conditions provided by current legislation, as applicable, including within the framework of the provisions of Article 65 Subparagraph (a) of the Regulation for Implementation of Law No. 57-07. or within the framework of Paragraph II of said Article 65 (...):
…
h) Receive, as remuneration for the generation of electricity from primary renewable sources, the wholesale market price, plus the incentives provided for in Law 57-07 on Incentives for the Development of Renewable Energy Sources and its Special Regimes, dated May 7, 2007 and its regulation for implementation, with their respective amendments;
…
k) All other conditions established in the Regulation for Implementation of Law No. 57-07 on Incentives for the Development of Renewable Energy Sources and their Special Regimes, with their respective amendments;
…
m) Any other right granted under Dominican legislation, and in particular, subject to the terms and conditions provided for such purpose under Law 57-07 and its Regulation for Implementation with regard to tax incentives and other rights established therein.
Article 65.- PPA. Any companies benefiting from a Final Concession, included in the Register of the Special Regime. will establish an agreement for the supply of electricity from primary renewable sources, with the CDEEE. by virtue of which they will receive from it any payments that correspond to them in accordance with this Regulation. (...)
SUBSECTION I: In each case, the agreement will be negotiated by the parties, based on their respective commercial interests.
SECTION II: The heads of Renewable Energy Power Companies may sign renewable energy supply contracts with any other agent of the wholesale electricity market, in adherence with the provisions of Law No. 57-07.
Timeline for Start and End of Works: THE CONCESSIONAIRE will have a period of three hundred and sixty (360) days from the signing of this document, to present evidence of the formalization of a Power Purchase Agreement with the Dominican Corporation of State Electric Companies (CDEEE) that allows the sale of all energy of THE CONCESSIONAIRE, notwithstanding any right of THE CONCESSIONAIRE to sell energy to any other agent on the Wholesale Electricity Market [MEM, by its Spanish acronym] or on the Spot Market.
RIGHT OF THE PARTIES TO SIGN THIS AGREEMENT.
13.1 THE GENERATOR states that:
a It justifies its right to sign this Contract under its holding of the Final Concession Agreement, as well as its registration in the Register of the Special Regime established in the Regulations for the Implementation of Law No. 57-07. (...)
13.2 THE CDEEE states that:
...
b. It signs this Agreement by mandate of Law No. 57-07 and Article 65 of the Regulation for the Implementation of Law No. 57-07.
THE CONCESSIONAIRE will have the right to collect the list price of the electricity sold and the corresponding premiums from the distribution companies, the CDEEE or other agents of the Wholesale Electricity Market, as established in the applicable regulations in force.
[Know] the terms of the Protocol of General Conditions for the signing of Contracts for the Sale of electrical energy from renewable energy sources established in the Special Power No. 121-15. and [wants] to express [its] agreement and formal acceptance of the conditions and energy sale price for the wind power projects established in the said protocol.
8.3. Notwithstanding that the following events or circumstances may be considered as exempt or exempting circumstances from liability for THE CONCESSIONAIRE under this Contract, and allowing it to validly suspend its obligations under it because such events or circumstances are considered to be breaches of essential obligations of the DOMINICAN STATE assumed under this Contract, they may not be used by the DOMINICAN STATE, or any of its dependencies, including the CNE and the SIE as an allegation of force majeure or exemption that justifies the suspension of its obligations under this Contract, namely:
c) Any modification to the current legislation and regulations of the Dominican Republic that has as a direct or indirect effect the impossibility of continuing in an economically viable manner with the operation of the Wind Farm.
8.4 In the event of any of the events described above in paragraph 8.3, to the extent that the termination or rescission of this Contract is decided due to causes attributable to the DOMINICAN STATE, the latter acknowledges and accepts the obligation to compensate THE CONCESSIONAIRE for the damages suffered. due to the event in question, as a breach by the DOMINICAN STATE. The Parties accept that the amount of compensation to which THE CONCESSIONAIRE would be entitled will be established by the arbitration award to be issued. The amount of these damages will in no case be less than the debt that THE CONCESSIONAIRE has pending with THE FINANCIAL CREDITORS.
2. It will be understood that body includes any person or entity considered as such according to the internal law of the State.)
economically viable operation of the Park. According to Dominicana Renovables, neither the spot market nor the alternative market have the capacity to absorb the 100 megawatts granted under the concession agreement, nor is this amount a financially viable option. Without the PPA Agreement, Dominicana Renovables could not close the financing agreement for the Project.
Any breach attributable to the Dominican State, to any of its dependencies, agencies, ministries, secretariats, autonomous bodies, public companies, and other related institutions, under any contract signed with the Concessionaire necessary for the construction and operation of the Wind Farm in an economically viable manner. including, any breach attributable to any of the parties to this Contract, whether it is the Dominican State., the CNE. or the Superintendency of Electricity, the Dominican Electricity Transmission Company, or the Dominican Corporation of State Electric Companies ICDEEE1
(i) The attorney Gautreau always had at her disposal the communication whereby the CDEEE sent the Protocol to Dominicana Renovables. The State has stated that the CDEEE always kept the MEM informed of the negotiations of the PPA Agreements.
(ii) The Protocol sent in January 2015 is not the amended PPA Agreement that the CDEEE promised to the Company.
(iii) The CDEEE sent the Protocol to Dominicana Renovables under different conditions than it was sent to other developers. The Company never had the opportunity to accept or reject the conditions of the Protocol, as it was informed that the Protocol would be amended and it had to wait for the new protocol.
(iv) The CDEEE never sent it the Formal Declaration of Acceptance of Terms and Conditions for the Signing of a Contract for the Sale of Energy from Renewable Sources with the CDEEE
(i) Dominicana Renovables denies that in that conversation Mr. Fernández admitted that the Company was negligent in the negotiation process with the CDEEE.124
(ii) The Company denies admitting that the contacts with the CDEEE were mainly verbal and not very specific.125
(iii) It is not true that the Invenergy company was not mentioned in the Complaint nor that the relationship with the said company was not serious. One of the annexes to the Claim is an item of correspondence with the aforementioned company. Additionally, engineer Ramos met with them personally on July 22, 2016 so that they could persuade the CDEEE to formalize the PPA Agreement with the Company.126
(iv) The mention of Invenergy to the Vice Minister of Energy did not mean that Dominicana Renovables did not have the financing. The Claimant reiterates that its financial capacity was proven by that time. The Company found it necessary to partner with a company with political influence in the Dominican Republic, taking into account that the State was not going to fulfil, as in fact happened, the signing of the PPA Agreement.127
(v) Mr. Fernández's comment on the price update does not exclude the fact that the State used arbitrary mechanisms to change prices.128
(vi) It should be clarified that when Mr. Fernández stated that “[Dominicana Renovables] [has not] been insistent enough,” at the same time he was making a gesture with his hands simulating a payment of cash. According to the Claimant, this gesture is understandable with the level of corruption that has occurred in the projects in the Dominican Republic.
c) Any modification to the current legislation and regulation of the Dominican Republic that has as a direct or indirect effect the impossibility of continuing in an economically viable way with the operation of the Wind Farm.
d) Any breach attributable to the DOMINICAN STATE, to any of its dependencies, agencies, ministries, secretariats, autonomous bodies, public companies, and other related institutions, under any contract signed with THE CONCESSIONAIRE necessary for the construction and operation, in an economically viable way of the Wind Farm, including any breach attributable to any of the parties to this Contract, be it the DOMINICAN STATE, the CNE or the Superintendency of Electricity, the Dominican Electrical Transmission Company or the Dominican Corporation of State Companies ...
(i) The price depends on "arbitrary decisions of the political authorities;"135
(ii) The sale price of energy is not determined by market forces but by the Superintendency of Electricity (“SIE”);
(iii) Historically it has been unattractive to investors;
(iv) Due to the high volatility and the marked drop in prices on the spot market, no bank is willing to finance a generator to invest in the spot market;
(v) The examples presented by the Dominican State of other developers operating in the spot market are not comparable with Dominicana Renovables. The Los Cocos project was able to be financially viable because it was covered under the umbrella of a PPA Agreement. Additionally, it was a project that obtained additional fiscal benefits on the basis of being registered in the Clean Development Mechanism.
(i) Wind Farm Construction Time Frame. The 24 month period estimated by the Dominican State to complete the construction of the Park is based on non-credible sources such as press releases or non-technical documents. Conversely the 14-month estimate by Dominicana Renovables was made by Grupo Cobra and is supported by the expert's experience.
(ii) Investment cost. The production costs presented by the Respondent's expert based on a ratio of US $ 2.41 million per MW, compared to the US $ 1.4 estimated by the Claimant, are based on non-technical journalistic reviews and therefore cannot be taken into account.
(iii) Wind Farm expansion recess. The Respondent's expert does not provide any evidence to support that it generally takes 24 months to go from the first 50 MW phase to the second 100 MW phase. According to the Claimant, it is possible to build 100 MW installations continuously.
(iv) Lack of lease contracts. The assertion made by the Respondent's expert is not true. Dominicana Renovables has leased 100% of the land necessary for the development of the Project.
(v) Useful life of the Wind Farm. The Respondent's own expert acknowledges that the Park can have a useful life of 20 to 25 years. No However, the expert arbitrarily assumes that the Project will only last 20 years.
(vi) Wind Farm Production. The State proposes that the production be based on the studies of Normawind and World Watch Institute (which were used to obtain the Final Concession) and not the studies of ATA Renovables and AWS True Power, since the latter use generators with different characteristics. Although the generators used to calculate the production of the Park are different from those stipulated in the Concession Agreement, “it is usual to start the processing of a concession based on an existing wind turbine model at that time, and once the promotion is advanced and the time has elapsed, request the change of model to a more modern and developed one."145
On the other hand, the Respondent's assertion that the generation of the Wind Farm could not be greater than 30% cannot be taken into account. The conclusion of the expert of the Dominican Republic is based on generic data, whereas the Claimant relied on the exhaustive measurements of AWS True Power.
(vii) Applicable rates. The Claimant reiterates that Law 57-07 and the Regulations establish a fixed rate. The fact that the other generators have been forced to accept the CDEEE's unilateral rates only demonstrates the abuse of power by the entity.
(viii) Operation and Maintenance Cost. Although the Respondent affirms that the Claimant's estimate of US $ 2.7 million in OPEX is unreasonable, Dominicana Renovables' calculations are based on a proposal received by the Company, so this estimate reflects the reality of the market and is more than reasonable.
(ix) Availability of financing. The Claimant reiterates that the financial capacity of the Company is more than proven.
(x) Risk discount rate. The greatest difference between the discount rate proposed by the Claimant (10.05%) and the Respondent (16.9%) lies in the country risk discount. It is not admissible for the State to affirm that the country risk is much higher than 3.47 / 3.59 reflected in the Country's Performance. The Duff & Phelps survey used by the State to calculate the cost of callable capital in the Dominican Republic is exaggerated in terms of exchange risk and the stability of the Dominican market.
(xi) Discount rate for liquidity. The 18% illiquidity rate proposed by the Respondent is not appropriate since what is sought is to assess the impossibility of achieving a flow if the project has been carried out.
Thus, if we use the IRR or gross profitability of the La Isabela Wind Farm of 25.5% and. to this we add the financing of the project of up to 70%, this necessarily yields a shareholder IRR of 44.6%. Even assuming the rate established in the Special Power is used, the gross IRR of the La Isabela Wind Farm would be 20.1% and the leveraged IRR would be 31.8%.
(i) The Final Concession Agreement was not signed "on behalf of the entire state apparatus", much less the CDEEE. The Contract was signed on behalf of the State, represented by the Executive Director of the CNE.
(ii) The Concession Agreement cannot be extended "to the entire state apparatus" because the principle of specialty and autonomy of public service companies such as the CDEEE would be annulled.
(iii) Only the acts of the bodies that make up the "central public administration" are attributable to the Dominican State. The central public administration is comprised of the President of the Republic, the Vice President of the Republic, the Council of Ministers and the ministries.
(iv) The Claimant confuses the concept of attribution under international law with that of Dominican law. International law is not applicable to the present case. According to the Dominican Constitution, the State is an administrative entity with its own legal personality under public law, distinct from the CDEEE, which is an autonomous and decentralized body.
(i) The President does not exercise any kind of control over decentralized entities according to Law No. 247-12 of August 14, 2012.
(ii) The ministry of each sector is in charge of exercising a supervisory control over the assigned entities. However, this control only began to take effect as of September 30, 2018; prior to this date the CDEEE enjoyed full autonomy and freedom to exercise its functions.
(iii) The authority exercised by the ministries over the attached entities allows them to guide their conduct, but not to revoke their actions.
(i) Article 8.3 (d) of the Concession Agreement does not define who are parties to it. This provision sets out to regulate the events that the State cannot invoke as exemptions of responsibility for the breach of its obligations according to the Final Concession Agreement.
(ii) When Article 8.3 (d) refers to the CDEEE as the signatory of the contract, it refers to the contract "necessary for the construction and operation of the Wind Farm in an economically viable manner."
(iii) The CDEEE is not a party to the Concession Agreement as shown by: (1) the fact that the Contract indicates that the parties are THE DOMINICAN STATE and THE CONCESSIONAIRE, so the Contract was only signed by the President of the CNE on behalf of the State; (2) the CDEEE is not empowered to sign final concessions; (3) Dominicana Renovables was always clear that the CDEEE was not its counterparty in the Final Concession Agreement, otherwise it would have filed the arbitration claim against the CDEEE; (4) the CDEEE did not sign the Concession Agreement either.
Enter into energy sales contracts and / or sell their energy production in the SENI under the conditions set out in the current applicable regulations thereto, either within the framework of the provisions of sub-paragraph (a) of Article 65 of the Regulations for the Application of Law No. 57-07. or within the framework of Paragraph II of said Article 65. Regarding the understanding that the suspension, termination, or cancellation by any other means of an Energy Purchase Agreement within the framework of the previous provisions, will not entail the rescission, termination or revocation of this Final Concession Agreement.
(i) Law 57-07 and the Regulations use express language when they set forth contract obligations. By way of example, Article 64 of the Regulations, at the time of regulating the electricity grid connection contract, provides that: “[t] he distribution or transmission company will have the obligation to sign this contract even if there is no net generation at the facility."165
Another example mentioned by the Respondent is Article 20 of Law 57-07, which, when regulating the management of electricity surpluses, establishes that: “[the] Distribution Companies will be obliged to purchase their surpluses from them at prices regulated by the SIE following a study and recommendation of the CNE, to regulated and unregulated users to install systems to take advantage of renewable resources to produce electricity with the possibility of generating surpluses that can be sent to the SENI networks."166
(ii) The regulations that govern the functions of the CDEEE do not impose on it the obligation to enter into Concession Agreements. Article 138 of the General Electricity Law only indicates that the CDEEE is in charge of “the administration and application of the electricity supply contracts of the Independent Producers of Electricity (IPPs),” without making any mention of the obligation to purchase energy from the holders of a final concession.167
(iii) Paragraph I of Article 65 of the Regulations establishes that any Concession Agreement "will be negotiated by the parties based on their business interests."168 The conclusion of the contract cannot be guaranteed when it is expressly subject to a negotiation.
(iv) The similarity in the renewable energy regime of Spain with that of the Dominican Republic is in the regulation of the connection contract to the electricity grid, not in the signing of the Concession Agreement. Furthermore, the Spanish regulation does not subject the execution of Concession Agreements to a negotiation process, as is established in Paragraph I of Article 65 of the Regulation.
(i) Dominicana Renovables has a maximum authorized installed capacity of 50 MW and not 100MW.
(ii) The Claimant has not provided evidence to support that the wholesale market did not have the capacity to absorb the 100 MW (which were not such).
(iii) If Dominicana Renovables believed that the other energy sales alternatives were not economically viable, it should not have accepted them in the negotiation of the Final Concession Agreement.
(iv) It is not true that the CDEEE pays the rates established in the Regulations. On the contrary, it paid lower prices. For example, in 2016, it paid 11.50/100 USD per kWh and in 2018, it paid 10.00 - 10.50/100 USD per kWh). The Respondent adds that Dominicana Renovables has not demonstrated that a remuneration lower than the benchmark rates of the Regulations will generate the economic unviability of the Project.
(v) In the Dominican energy sector, there are concessionaires that sell their energy by means other than the PPA with the CDEEE.
(i) Dominicana Renovables fails to refer in its Reply to the attribution of risks established in the Concession Agreement; Claimant's silence confirms its inability to rebut this argument.
(ii) Contrary to what is stipulated in the Concession Agreement, the Claimant intends to transfer the risks by suggesting that the State should guarantee the financing, as well as an exorbitant profitability.
(iii) Dominicana Renovables focuses on arguing that the spot market is not viable without a PPA, but does not comment on the possibility of selling its energy to unregulated users of the market. Profitable deals can be struck in this segment of the market.
(iv) Regarding the financial unviability of the spot market, the State declares: (1) it is not true that the price of energy in that market is determined by the SIE. This entity sets a ceiling price that is different from the market price; (2) it is incorrect to state that the spot market price is characterized by being volatile - from August 2015 to November 2017, the sale prices were profitable for generators; (3) the fact that renewable energy does not receive remuneration for firm capacity does not make the spot market unviable, since on the one hand, the sale prices are higher than the generation costs and, on the other, Law 57-07 has incentives to compensate for the effect of not receiving that remuneration; (4) the Claimant has not been able to dispute that there are two wind farms that are financially viable operating only in the spot market. On the one hand, it did not rule on the Quilvio Cabrera farm and, on the other, the distinctions it has made on the Los Cocos farm are irrelevant; (5) the Respondent's expert has demonstrated that La Isabela Wind Farm could have generated reasonable profitability by selling its energy on the spot market - the Project would have a value of US$147 million if it had been financed, or US$199.2 million if it had been built with own funds.
(v) It is not true that the Concession Agreement or the legal framework granted Dominicana Renovables a guarantee of access to financing. The purpose of Article 65 of the Regulation was not such. The purpose of the aforementioned provision was to allow the CDEEE to purchase energy as a priority to resolve the energy deficit.
(vi) Claimant's position according to which without the formalization of a PPA there is no financing, and therefore there is no wind farm, is exaggerated for the following reasons: (1) to claim that without the PPA there is no financing is to implicitly admit that the Company had not yet secured the financing; (2) it is not “impossible” to obtain financing without the PPA - there are agreements in the Dominican Republic to finance this class of companies; (3) the Project can also be financed with own resources; (4) it is not true that a PPA immediately guarantees financing.
(i) For the CDEEE, the purchase price is an essential component of the authority's commercial interests.
(ii) Article 66 of the Regulations sets forth that developers will have the right to receive the remuneration provided for in the PPA. Therefore, one of the points that were not determined in the draft PPAs circulated by the CDEEE was Article 4.1 that regulated the sale price of the energy.
(iii) Article 5 of the Final Concession Agreement only sets forth the right that developers have to receive as remuneration "the wholesale market price."202 Similarly, Article 11 of the Concession Agreement sets forth that the concessionaire has the right to collect the price of the rate "according to what is set forth in the current regulations that are applicable to it."203
(i) Dominicana Renovables itself acknowledges that Article 110 sets forth a “recommended” level of remuneration: "A recommendation differs substantially from an obligation;"206
(ii) Although the premium of Article 108 of the Regulations is variable, this does not imply that the remuneration value "R" is fixed. Article 110 of the Regulations refers to an annual benchmark, but not mandatory, remuneration. The benchmark remuneration "R" is adjusted taking into account the variations in CAPEX and the efficiencies in technology.
(iii) The standards that the Claimant cites to argue the existence of a financial guarantee establish that any incentive depends on “the situation of the fossil market and its determination in the average and marginal costs of the local market.”207 Both the prices of hydrocarbons and the CAPEX to build a wind farm that existed in 2007 have decreased significantly.
(iv) Maintaining the benchmark price of the Regulations, as claimed by the Claimant, means ignoring the efficiency and savings in CAPEX that are being achieved over time. Precisely, the CNE in the National Energy Plan for 2010-2025 set forth that one of the most important aspects of the price incentive strategy was "the gradual adjustment of the purchase price of energy to the conditions of a competitive market."208
(i) The recording was obtained at a public institution, it concerned issues of public relevance and at no time has it been used to violate the right to privacy of Mr. Fernández;
(ii) The reasons presented by the Claimant to maintain that the recording is not reliable are irrelevant. The third person who is not mentioned in the transcript is the assistant to the Deputy Minister whose job it was to draw up the minutes.
(iii) It is not true that Mr. Fernández's statements have been taken out of context. In said conversation, Dominicana Renovables admitted that the PPA was not entered into due to its lack of insistence and diligence, and it is not acceptable that the Claimant now intends to justify said assertion by arguing that the legal representative was referring to the payment of bribes.
(i) The CDEEE prepared a draft or standard format of the PPA.
(ii) The CDEEE decided to issue the Protocol in order to facilitate the negotiation process and reaffirm that it was granting equal conditions to all interested parties. The Protocol established, on the one hand, that the price that the CDEEE was willing to pay would be 12.50/100 USD per kWh. On the other hand, it reaffirmed the obligation of the developer to submit reliable documentation that would demonstrate that it had the solvency or access to financing to develop the project.
Specifically, the Respondent indicates that, according to the Protocol, the developers “had to submit not only a letter of intent from the institution that would be in charge of financing the project (the “Letter of Intent), but also a term sheet. and conditions, indicating the amount of the credit, the term and the payment conditions.”216
(iii) In mid-2015, the CDEEE decided to reduce energy sale prices even further. Similarly, the CDEEE realized that some concessionaires were “using the concession as a basis of financial speculation."217 Consequently, the authority established three points for the negotiation of the PPAs. First, it reduced the base price for the purchase of energy from 12.50/100 to 11.50/100 USD/kWh. Second, it regulated the scenarios in which the developer could assign its rights and obligations under the PPA. Third, it limited the validity of the PPAs to a term of 20 years from the start date of the energy supply.
On October 6, 2015, the CDEEE requested authorization from the President of the Republic to implement these three new points.
According to the Respondent, these conditions were not reflected in any document and were reported directly by the CDEEE to the developers during the negotiation process.
(i) The Company only submitted the financial statements for the years 2011 and 2012 on May 1, 2014. The Claimant did not provide the financial statements for 2013 as required by the draft PPA.
(ii) Banesto's letter of January 2013 did not confirm the financing of the Project. According to the Respondent, the letter indicated that it was the Spanish Export Credit Insurance Company (“CESCE”) that would cover the credit risk, the financing terms of which were subject to its approval. In other words, the possible financing required not only the approval of Banesto but also the CESCE. Finally, by the time the CDEEE became aware of Banesto's communication, that is in January 2017, the letter was no longer in force.
(i) The Claimant has not refuted that it did not submit the financial statements for the 2013 fiscal year, despite knowing the mandatory nature of this requirement;
(ii) the letter from the Banesto bank was not submitted directly and in a timely manner to the CDEEE, but only alluded to in a chronological summary of the project's actions presented by Dominicana Renovables to the CDEEE on January 13, 2017;
(iii) the fact that at that time the CDEEE did not have a specific file on Dominicana Renovables is not enough to infer that the CDEEE received the letter but did not review it (intentionally or unintentionally), since in any case there is a system for the receipt and cataloging of communications.