2% Tranche | Portion of Daily Shortfall Gas which is exempted from accruing Shortfall Compensation |
2012 PUA Decision | Decision issued by PUA on 14 June 2012 |
7% Tranche | Threshold of the Monthly Shorfall Gas which triggers the right for Monthly Shortfall Compensation |
ACQ | Annual Contract Quantity |
Additional Costs/Additional Fuel Costs | Costs of alternative fuels incurred by IEC as a consequence of EGAS' breaches of the Tripartite Agreement |
Admissibility Objections | EGAS' admissibility objections as to lEC's claims against EGAS |
AGP | Arab Gas Pipeline in the Middle East for export of Egyptian natural gas to Jordan, Syria, Lebanon and Israel |
Al Sakka FWS | First witness statement from Mr. Maamoun Al-Sakka, Managing Director for Operations at EMG |
Al Sakka SWS | Second witness statement from Mr. Maamoun Al-Sakka, Managing Director for Operations at EMG |
Amit WS | Witness statement from Mr. Moshe Amit, Manager of Economics, Financial Planning and Tariffs at IEC |
Andrews | Legal Opinion prepared by Ms. Geraldine Andrews Q.C. of Essex Court Chambers |
Aronovich WS | Witness statement from Mr. Igor Aronovich, Senior Deputy Operations Manager at IEC |
Art. | Article |
Art. 1 | Article 1 of the Tripartite Agreement |
Art. 14.9 | Art. 14.9 of Annex 1 to the GSPA |
Art. 16 | Art. 16 of Annex 1 to the GSPA |
Authorisation | Decree No. 100 of 2004 issued by the Ministry of Petroleum |
Avoidance Requirement | Condition for the availability of the force majeure defence |
A-XXX | Communications from the Tribunal |
B&O’B-Freeny FR | First report on repairs of the Pipeline prepared by Mr. Charles C. Freeny, Mr. Gerald B. Gump and Mr. Timothy D. Rooney from Baker & O’Brien, expert witnesses presented by Claimant |
B&O’B-Freeny SR | Second report on repairs of the Pipeline prepared by Mr. Charles C. Freeny, Mr. Gerald B. Gump and Mr. Timothy D. Rooney from Baker & O’Brien, expert witnesses presented by Claimant |
B&O’B-Schrader FR | First report on security of the Pipeline prepared by Mr. Benjamin F. Schrader from Baker & O’Brien, expert witnesses presented by Claimant |
B&O’B-Schrader SR | Second report on security of the Pipeline prepared by Mr. Benjamin F. Schrader from Baker & O’Brien, expert witnesses presented by Claimant |
Balance of Payments | Item of compensation claimed by EMG consisting of the net amounts owed between EGAS and EMG |
BCM | Billion cubic meters of natural gas |
Brokman FWS | First witness statement form Mr. Shimshon Brokman, Head of the Fuel Management Department in the Generation and Transmission Division at IEC |
Brokman SWS | Second witness statement form Mr. Shimshon Brokman, Head of the Fuel Management Department in the Generation and Transmission Division at IEC |
Buyer | EMG |
CFSC | Claimant's First Submission on Costs |
C FS J | Claimant’s First Submission on Jurisdiction |
C FS M | Claimant’s First Submission on the Merits |
C PHB | Claimant’s Post Hearing Brief |
C S RF | Claimant’s submission on reverse flow |
C SS J | Claimant’s Second Submission on Jurisdiction |
C SS M | Claimant’s Second Submission on the Merits |
C SU SC | Claimant’s Second Updated Statement of Costs |
C SupS | Claimant’s Supplemental Submission |
C USC | Claimant’s Updated Statement of Costs |
Cairo Arbitration | Arbitration under the CRCICA Rules initiated by EGPC and EGAS against EMG pursuant to Art. 14.2 of the GSPA |
Claimant | East Mediterranean Gas S.A.E. |
Com. C-XXX | Communications from Claimant addressed to the Tribunal |
Com. R1+2-XXX | Communications from Respondents 1 and 2 addressed to the Tribunal |
Com. R3-XXX | Communications from Respondent 3 addressed to the Tribunal |
Committee of Five | Committee instructed to issue a Technical Report by the Cairo criminal court in the case felony no. 3642 of 2011 |
common law right | EMG's right to accept EGAS' termination of the GSPA and the Tripartite Agreement at common law |
Conciliatory Letter | Letter sent by EMG to EGAS of 21 September 2011 |
Contracts | The GSPA, the On-Sale Agreement and the Tripartite Agreement |
Cook | Report on the security of the Pipeline prepared by Dr. Steven Cook, expert witness presented by Respondent 3 |
Court | The International Court of Arbitration of the ICC |
CRCICA | Cairo Regional Centre for International Commercial Arbitration |
CY | Contract Year |
DCF | Discounted Cash Flow |
DCQ | Daily Contract Quantity |
Doc. CLA-XXX | Legal authorities presented by Claimant |
Doc. C-XXX | Documentary evidence presented by Claimant |
Doc. H-XXX | Documents submitted by the Parties during the First and Second Hearing |
Doc. R1+2-XXX | Documentary evidence presented by Respondents 1 and 2 |
Doc. R3-XXX | Documentary evidence presented by Respondent 3 |
Doc. RL1+2-XXX | Legal authorities presented by Respondents 1 and 2 |
Dolphinus | Dolphinus Holding Limited |
EBT | Earnings before taxes |
EGAS | Egyptian Natural Gas Holding Company |
EG PC | Egyptian General Petroleum Corporation |
Eiland | Report on the security of the Pipeline prepared by Major General Giora Eiland, expert witness presented by Respondent 3 |
EMG | East Mediterranean Gas S.A.E. |
EMG Pipeline | Ramification of the Peace Pipeline constructed and operated by EMG |
Enforceability Objections | EGAS' enforceability objection as to the unenforceability of the GSPA |
EUR | Euros |
Facilities | Valve stations, railway valves, traps and off-take rooms of the Pipeline |
FHT | First Hearing Transcript |
Fifth Amendment | Fifth amendment of the On-Sale Agreement on 17 September 2009 |
First Amendment | First amendment of the GSPA on 31 May 2009 |
First Hearing | Hearing held at the ICC Hearing Center located at 112 avenue Kléber, 75016 Paris, between 13 and 24 January, 2014 |
First Proposal | First proposal by EGAS for the calculation of the daily maximum |
fn. | Footnote |
Framework Resolution | Resolution issued by the Egyptian Council of Ministers on 18 September 2000 |
FSPL | Swiss Federal Statute on Private International Law |
FTI 1 | First expert report on damages produced by FTI Consulting on behalf of Claimant |
FTI II | Second expert report on damages produced by FTI Consulting on behalf of Claimant |
FTI/JWC | Joint expert report from Messrs. Moselle and Nicholson (Claimant’s experts) and Messrs. Wood-Collins and Giles (Respondents 1 and 2’s experts) on calculation of EMG’s losses |
GASCO | EGAS’ subsidiary entrusted with the operation of the AGP |
GBP | British pound sterling |
GSPA | Long-term gas purchase and sale agreement between EMG and EGPC/EGAS entered into on 13 June 2005 |
GSPA Claims | EMG’s claims under the GSPA |
Gurevich WS | Witness statement from Mr. Vladimir Gurevich, Manager in the Generation System Planning Department at IEC |
Hoffman 1 | First legal opinion of Lord Hoffman on behalf of Respondents 1 and 2 |
Hoffman II | Second legal opinion of Lord Hoffman on behalf of Respondents 1 and 2 |
ICC | The International Court of Arbitration of the ICC |
ICC Costs | Advance on costs fixed by the ICC |
ICC Rules | Rules of Arbitration of the ICC in force as from 1 January 1998 |
Jurisdictional Objections | EGAS' jurisdictional objections as to EMG's claims against EGAS |
JWC | EGAS experts Mr. John Wood Collins and Mr. Timothy Giles |
JWC I to VIII | Expert reports on damages prepared by Mr. John Wood Collins and Mr. Timothy Giles, expert witnesses presented by Respondents 1 and 2 |
KTISTAR | Operator of the EMG Pipeline |
Legal Fees | Reasonable legal and other costs incurred by the parties for the arbitration |
Letter of Intent | Letter of Intent signed by Dolphinus and the Delek Group on 19 October 2014 |
Ling FR | First report on the security of the Pipeline prepared by Brigadier Tony Ling CBE, expert witness presented by Respondent 3 |
Ling SR | Second report on the security of the Pipeline prepared by Brigadier Tony Ling CBE, expert witness presented by Respondent 3 |
LNG | Liquidified natural gas |
Long FAC | Long Term Future Additional Costs |
Long FAC | Long Term Future Additional Costs in Nera's calculation of lEC's damages |
MFO | Multinational Force and Observers |
MIDOR | Middle East Oil Refinery |
MMBTU | Million British thermal unit |
MoU | Memorandum of Understanding signed by the States of Egypt and Israel on 30 June 2005 |
Near FAC | Near Term Future Additional Costs |
Near FAC | Near Term Future Additional Costs in Nera's calculation of lEC's damages |
Nera | Nera Economic Consulting |
Nera I to III | Three expert reports on damages prepared by Nera Economic Consulting, on behalf of Respondent 3 |
NIS | Israeli new Shekel |
Nudelman FWS | First witness statement form Ms. Lena Nudelman, Head of Maintenance Planning at IEC |
Nudelman SWS | Second witness statement form Ms. Lena Nudelman, Head of Maintenance Planning at IEC |
On-Sale Agreement | Long-term gas purchase and sale agreement between EMG and IEC entered into on 8 August 2005 |
Other Costs | Other costs incurred by IEC as a consequence of EGAS' breaches of the Tripartite Agreement |
Other ICC Arbitration | ICC Arbitration initiated on 21 September 2011 by Claimant versus Respondent 3 but suspended by agreement of the parties |
p. | Page |
PAC | Past Additional Costs |
para. | Paragraph |
Partial Award in the Cairo Arbitration | Partial Award in the Cairo Arbitration issued on 11 November 2013 |
Parties | EMG, IEC and EGAS and EGPC |
Pelham FR | First report on the security of the Pipeline prepared by Mr. Nicolas Pelham, expert witness presented by Respondents 1 and 2 |
Pelham SR | Second report on the security of the Pipeline prepared by Mr. Nicolas Pelham, expert witness presented by Respondents 1 and 2 |
Pipeline | First section of 192 km of the AGP between Damietta and Al-Arish |
PNQs | Properly Nominated Quantities |
PO | Procedural Order |
Post-Tamar AC | Period selected by the Tribunal to assess Respondent 3's damages |
Press Release | Press release issued on 18 March 2015 by the Delek Group |
Pre-Tamar AC | Period selected by the Tribunal to assess Respondent 3's damages |
PUA | Public Utilities Authority of Israel |
PUA Decisions | Decisions issued by the Public Utilities Authority of Israel |
PUA Letter | Letter of PUA dated 14 May 2014 |
R1+2 FS C | Respondents 1 and 2's First Submission on Costs |
R1+2 FS J | Respondents 1 and 2's First Submission on Jurisdiction |
R1+2 FS M | Respondents 1 and 2's First Submission on the Merits |
R1+2PHB | Respondents 1 and 2's Post Hearing Brief |
r1+2s rf | Respondents 1 and 2's Submission on Reverse Flow |
R1+2 SC | Respondents 1 and 2's Statement of Costs |
R1+2SI | Respondents 1 and 2's Submission on Interest |
R1+2 SS J | Respondents 1 and 2's Second Submission on Jurisdiction |
R1+2SS M | Respondents 1 and 2's Second Submission on the Merits |
R1+2SupS | Respondents 1 and 2's Supplemental Submission |
R1+2USC | Respondents 1 and 2's Updated Statement of Costs |
R3 FS C | Respondent 3's First Submission on Costs |
R3 FS J | Respondent 3's First Submission on Jurisdiction |
r3 fs m | Respondent 3's First Submission on the Merits |
r3 phb | Respondent 3's Post Hearing Brief |
R3 S RF | Respondent 3's Submission on Reverse Flow |
R3 SS J | Respondent 3's Second Submission on Jurisdiction |
R3 SS M | Respondent 3's Second Submission on the Merits |
R3 SupS | Respondent 3's Supplemental Submission |
r3 USC | Respondent 3's Updated Statement of Costs |
Release of Claims | Letter signed by EMG and EGPC/EGAS dated 31 May 2009 agreeing reciprocal release of claims for liability for breaches of the GSPA prior to the First Amendment |
Respondent 1 or EGPC | Egyptian General Petroleum Corporation |
Respondent 2 or EGAS | Egyptian Natural Gas Holding Company |
Respondent 3 or IEC | Israeli Electric Corporation LTD. |
Respondents 1 and 2 | EGAS and EGPC |
Reverse Flow | Hypothesis raised by Respondents 1 and 2 in relation to the quantification of EMG's claim, consisting of the possibility of gas being imported from Israel to Egypt through EMG’s pipeline |
Ronai WS | Witness statement from Mr. Yaron Ronai, Head of the Haifa office at IEC |
RPPO | Reasonable and Prudent Pipeline Operator |
RPPO Requirement | Condition for the availability of the force majeure |
defence | |
Rules | Rules of Arbitration of the ICC in force as from 1 January 1998 |
Second Hearing | Hearing held at the ICC Hearing Center located at 112 avenue Kléber, 75016 Paris, on 15 and 16 May, 2014 |
Second Proposal | Second proposal by EGAS for the calculation of the daily maximum |
Seller | EGPC/EGAS |
SHT | Second Hearing Transcript |
Simulated Actual Scenario | Item used by Respondent 3's expert in the damages calculation |
Simulated What If Scenario | Item used by Respondent 3's expert in the damages calculation |
Source Contract | Long-term gas purchase and sale agreement between EMG and EGPC/EGAS entered into on 13 June 2005 |
Tamar Contract | Contract entered into by IEC on 14 March 2012 for the supply of gas from the Tamar field |
Technical Report | Report issued in February 2014 by the Committee of Five before the Cairo criminal court in the case felony no. 3642 of 2011 |
Terms of Reference | Terms of Reference governing this arbitration approved by the Court on 26 July 2012 |
The April Ruling | Tribunal's communication A 68 |
Third Proposal | Third proposal by EGAS for the calculation of the daily maximum |
Tripartite Agreement | Agreement concluded between EMG, EGPC and EGAS and IEC on 13 June 2005 |
Tripartite Agreement Claims | EMG’s claims under the Tripartite Agreement |
Tripartite Delivery Breaches | EGAS’ breach of its delivery obligations under the Tripartite Agreement |
Tripartite Repudiatory Breach | EGAS' breach of the Tripartite Agreement for repudiation of the GSPA and Tripartite Agreement |
UK Base Rate | UK Clearing Banks’ Base Lending Rate |
USD | United States dollar |
Valuation Date | Valuation date used by the Tribunal to calculate compensation owed by EGAS to IEC |
WACC | Weighted Average Cost of Capital |
Weiss WS | Witness statement from Moshe Weiss, Contract Manager at the Mechanical Department at IEC |
24 Roushdy St.
Heliopolis 11361
Cairo
Egypt
Ms. Lucy Reed
Freshfields Bruckhaus Deringer LLP
11th Floor
Two Exchange Square
Hong Kong
Tel: +852 2846 3400
Fax: +852 2810 6192
Email: lucy.reed@freshfields.com
Messrs. Noah Rubins, Ben Juratowitch and Ben Love
Freshfields Bruckhaus Deringer LLP
2, rue Paul Cézanne
75008 Paris
France
Tel: +33 (0) 1 44564456
Fax: +33 (0) 1 44564400
Email: noah.rubins@freshfields.com
ben.juratowitch@freshfields.com
ben.love@freshfields.com
Mr. Niv Sever
M. Firon & Co. Advocates
16 Abba Hillel Silver St.
Ramet Gan 52506
Israel
Tel: +972 375 40000
Fax: +972 375 40011
Email: niv_firon.co.il
Mr. Sarwat Abd El-Shahid
Sarwat A. Shahid Law Firm
20 B Adly Street
Cairo
Egyt
Email: sarwat@shahidlaw.com
4 Palestine Street
4th Division
New Maadi 11742
Cairo
Egypt
85, El Nasr Road
1st District, Nasr City 11371
P.O. Box 8064
Cairo
Egypt
Prof. Emmanuel Gaillard
Dr. Yas Banifatemi
Mr. Alexander Uff
Mr. Mohamed Shelbaya
Shearman & Sterling LLP
114 Avenue des Champs-Elysées
75008 Paris
Prance
Tel. +33 1 53 89 70 00
Pax: +33 1 53 89 70 70
E-mail: egaillard@shearman.com
ybanifatemi@shearman.com
alexander.uff@shearman.com
mohamed.shelbaya@shearman.com
1 Netiv Haor Str.
Haifa
Israel
Mr. Neil Q. Miller
Ms. Emma Rooney
Norton Rose Fulbright LLP
3 More London Riverside
London SE1 2AQ
United Kingdom
Tel: +44 20 7283 6000
Fax: +44 20 7283 6500
E-mail: neil.q.miller@nortonrosefulbright.com emma.rooney@nortonrosefulbright.com
Mr. John Marrin QC
Keating Chambers
15 Essex Street
London WC2R 3AA
United Kingdom
Tel: +44 20 7544 2600
Fax: +44 20 7544 2700
E-mail: j marrin@keatingchambers.com
Mr. Osman Berat Gürzumar
Bilkent Universitesi Hukuk Fakultesi
06800 Bilkent-Ankara
Turkey
Tel: +90 312 290 34 90
Fax: +90 312 266 22 80
E-mail: berat@bilkent.edu.tr
Mr. Juan Fernández-Armesto (Chairman)
Armesto & Asociados
General Pardiñas 102
28006 Madrid
Spain
Tel: +34-91,562.16.25
Fax: +34-91,515.91.45
E-mail: jfa@jfarmesto.com
33-43 avenue du President Wilson,
75116 Paris
France
Tel: +33-1 49 53 29 05
Fax: +33 1 49 53 29 33
E-mail: ica7@iccwbo.org
- the GSPA is a long-term gas purchase and sale agreement between EMG (Buyer) and EGPC/EGAS (Seller), which are jointly and severally liable pursuant to Art. 13.3 of the GSPA (for convenience EGPC/EGAS will frequently be referred to simply as "EGAS" or as the "Seller"), entered into on 13 June 2005. EGAS agreed to make a specific volume of natural gas available to EMG on a take or pay basis at the delivery point located at Al-Arish, Egypt. This contract enables EMG to satisfy its obligations as seller towards its customers under the on-sale agreements.
- the On-Sale Agreement is another long-term gas purchase and sale agreement between EMG (Seller) and IEC (Buyer) entered into on 8 August 2005. EMG undertook to deliver to IEC a specific amount of natural gas on a take or pay basis at the delivery point located at Ashkelon, Israel.
- the Tripartite Agreement was concluded between all Parties (EGAS and EGPC, EMG and IEC). The purpose of this agreement was for EGAS to guarantee the supply of gas to IEC through fulfilling their obligations towards EMG under the GSPA.
"Dispute Resolution. All Disputes or disagreements arising under this Agreement and in connection hereto will be conducted in the English language and as per the applicable procedures in Article 14 of Annex 1 and Annex 4 (Expert Provisions), respectively".
"Art. 14.2 -Disputes and Arbitration
Except as set forth in Section 14.9 and 14.11[4] and Paragraph 17 of Annex 4[5], if any dispute between the Parties arising out of or in connection with this Agreement ("Dispute") has not been settled within thirty (30) days of a Party notifying the other Party of the Dispute, then a Party wishing to arbitrate such Dispute may submit such Dispute to arbitration in accordance with and pursuant to the Rules of Arbitration of the Cairo Regional Centre for International Commercial Arbitration ("CRCICA"). All Disputes submitted for arbitration shall be heard and resolved by a panel of three (3) arbitrators, appointed according to the rules of the CRCICA; provided that no member of such panel of arbitrators shall be connected and/or associated with any of the Parties and/or their legal and other advisors. The seat of arbitration shall be in Cairo, Egypt. The arbitration proceedings shall be conducted in the English language, and all documentation submitted for the consideration of the panel shall be translated into English at the expense of the submitting Party".
"Art. 14.9 - Arbitration under On-Sale Agreement
Notwithstanding the foregoing provision of this Article 14, if Buyer and Seller have a Dispute under this Agreement, and if a dispute arising from or related to the same or similar factual circumstances at issue in the Parties’ disagreement is subject to dispute resolution under any On-Sale Agreement, Buyer may choose to resolve the Dispute between Buyer and Seller pursuant to the dispute resolution procedures of the relevant On-Sale Agreement; provided that (a) Buyer provides Seller with notice of the dispute under the relevant On-Sale Agreement, and Buyer’s election to resolve such Dispute pursuant to the dispute resolution procedures under the relevant On-Sale Agreement ("Dispute Resolution Notice"), on or before fifteen (15) days following initiation of the applicable dispute resolution procedure under the On-Sale Agreement; and (b) Buyer shall consult with Seller in respect of such dispute resolution procedure. If Buyer delivers such Dispute Resolution Notice and Seller gave his written consent, neither Party may seek arbitration or an Expert determination regarding such Dispute under this Agreement, and the outcome of such dispute resolution under the On-Sale Agreement shall be binding on the Parties hereunder".
"Art. 14.10 - Disputes under the Tripartite Agreement
Notwithstanding the provisions of the Tripartite Agreement to the contrary, if any dispute under the Tripartite Agreement arises between EGPC and EGAS on the one hand, and EMG on the other hand, and if the Initial On-Sale Customer is not a party to such dispute, such dispute shall be resolved pursuant to the dispute resolution provisions provided for in this Article 14".
"9. This Tripartite Agreement shall be governed by, and construed in accordance with, the Laws of England, but excluding (to the fullest extent) any rules or principles of English Law that would prevent adjudication upon (or accord presumptive validity to) the transactions of sovereign states, and without regard to such principles or requirements of conflicts of Laws that would require the application of Laws of any other jurisdiction to govern this Agreement or any matter arising hereunder. If any dispute between the Parties arising out of or in connection with this Agreement ("Dispute"), has not been settled within (30) Days of a Party of the Dispute, then a Party wishing to arbitrate such Dispute may submit such Dispute to arbitration in accordance with and pursuant to the Rules of Arbitration of the International Chamber of Commerce ("ICC"). All Disputes submitted for arbitration shall be heard and resolved by a panel of three (3) arbitrators, appointed according to the ICC rules; provided that no member in such panel of arbitrators shall be a citizen or national of either Egypt or Israel or a citizen or national of a country which does not have diplomatic relations with either Egypt or Israel, nor will any member of such panel of arbitrators be connected and/or associated with any of the Parties and/or their legal and other advisors. The seat of arbitration shall be in Geneva, Switzerland. The arbitration proceedings shall be conducted in the English language, and all documentation submitted for the consideration of the panel shall be translated into English at the expense of the submitting Party. For the purposes of enforcement in Egypt of any decision or award rendered pursuant to this Tripartite Agreement, the Egyptian Arbitration Law No. 27 of 1994, as amended from time to time, shall apply".
"10.2 Disputes and Arbitration. Except as set forth in Section 10.9, if any dispute between the Parties arising out of or in connection with this Agreement ("Dispute"), has not been settled within (30) days of a Party notifying the other Party of the Dispute, then a Party wishing to arbitrate such Dispute may submit such Dispute to arbitration in accordance with and pursuant to the Rules of Arbitration of the International Chamber of Commerce ("ICC"). All Disputes submitted for arbitration shall be heard and resolved by a panel of three (3) arbitrators, appointed according to the ICC rules; provided that no member in such panel of arbitrators shall be a citizen or national of either Egypt or Israel or a citizen or national of a country which does not have diplomatic relations with either Egypt or Israel, nor will any member of such panel of arbitrators be connected and/or associated with any of the Parties and/or their legal and other advisors. The seat of arbitration shall be in Geneva, Switzerland. The arbitration proceedings shall be conducted in the English language, and all documentation submitted for the consideration of the panel shall be translated into English at the expense of the submitting Party".
- acknowledged receipt of Claimant’s and Respondent 3’s comments on Art. 6(2) of the Rules and noted that Respondents 1 and 2 had failed to submit comments within the allotted time frame;
- confirmed that Respondents 1 and 2’s right to make comments on Art. 6(2) had expired;
- noted that the Court was to examine whether the arbitration should proceed pursuant to Art. 6(2) of the Rules taking into consideration Claimant’s and Respondent 3’s comments of 6 February 2012 and Respondents 1 and 2’s letter dated 10 November 2011 and the Answer to the Request for Arbitration of 21 December 2011; and
- decided that it was appropriate to grant Respondents 1 and 2 permission to file a submission with comments on Respondent 3’s Answer to the Request for Arbitration and Counterclaim.
- Mr. John Marrin QC as co-arbitrator;
- Mr. Osman Berat Gürzumar as co-arbitrator;
- Mr. Juan Fernández-Armesto as Chairman of the Arbitral Tribunal.
On behalf of Claimant
Witnesses | Experts |
Mr. Maamoun Al Sakka | Mr. James Nicholson (FTI Consulting) |
Mr. Abdel Hamid Ahmed Hamdy | Mr. Boaz Moselle (FTI Consulting) |
Mr. Charles Freenv (Baker & O’Brien) | |
Mr. Benjamin Schrader (Baker & O’Brien) |
On behalf of Respondents 1 and 2
Witnesses64 | Experts |
Mr. John Wood-Collins and Mr. Tim Giles | |
Mr. Nicolas Pelham |
On behalf of Respondent 3
Witnesses | Experts |
Ms. Lena Nudelman | Mr. Steven Cook |
Mr. Yaron Ronai | Mr. Giora Eiland |
Mr. Shimshon Brokman | Mr. Graham Shuttleworth |
Mr. Moshe Amit |
- Annual Reconciliation Simulation according to Claimant’s construction and Respondents 1 and 2’s construction;
- A joint expert report from Messrs. Moselle and Nicholson (Claimant’s experts) and Messrs. Wood-Collins and Giles (Respondents 1 and 2’s experts) on calculation of EMG’s losses65;
- A counter-report of Messrs. Wood-Collins and Giles (Respondents 1 and 2’s experts) on the report prepared by Nera (Respondent 3’s expert) on IEC’s losses; Respondent 3 presented a reply to the Wood-Collins and Giles counter-report prepared by its expert Mr. Graham Shuttleworth (Nera).
Claimant | Position |
Mr. Maamoun Al Sakka107 | Managing Director for Operation, Engineering and Contracts at EMG |
Mr. Abdel Hamid Ahmed Hamdy | Commercial Manager at EMG |
Respondent 3 | |
Mr. Igor Aronovich108 | Senior Deputy Operations Manager at IEC |
Ms. Lena Nudelman109 | Head of Maintenance Planning at IEC |
Mr. Yaron Ronai110 | Head of the Natural Gas and Coal Department, Generation & Transmission Division at IEC |
Mr. Shimshon Brokman111 | Head of the Fuel Management Department in the Generation and Transmission Division at IEC |
Mr. Moshe Amit112 | Manager of the Economics, Financial Planning and Tariffs Department at IEC |
Mr. Alexander Zaid | Company Comptroller at IEC |
Mr. David Elmakis | Senior Vice President and Head of the Planning, Development and Technology Division at IEC |
Mr. Joseph Dvir | Former Senior Vice President and CFO at IEC |
Mr. Moshe Weiss113 | Contract Manager in the Mechanical Department in the Generation Division at IEC |
Mr. Vladimir Gurevich114 | Manager in the Generation System Planning Department in the Planning, Development & Technology Division at IEC |
Mr. Zecharia Kay | Head of Finance Division at IEC |
Claimant | Issue |
Mr. Charles C. Freeny, Mr. Gerald B. Gump and Mr. Timothy D. Rooney from Baker & O’Brien | Two expert reports on repairs of the Pipeline115 |
Mr. Benjamin F. Schrader from Baker & O’Brien | Two expert reports on security116 |
Mr. Boaz Moselle and Mr. James Nicholson from FTI Consulting | Two expert reports on quantification of EMG’s damages117, and an Annual Reconciliation Simulation |
Ms. Zoe Young, Mr. Richard Poole and Mr. Bill Cline form Gaffney, Cline & Associates | Compliance with document production |
Mr. Daniel Muthmann from Global Gas Partners GmbH | A financial report |
Respondents 1 and 2 | |
Mr. Nicolas Pelham (independent consultant) | Two expert reports on security118 |
Mr. Chris Clements form Grant Thornton LLP | Two expert reports on quantification of IEC’s damages |
Ms. Geraldine Andrews Q.C. of Essex Court Chambers | A legal opinion119 |
Leonard, Lord Hoffman | Two legal opinions120 |
Mr. John Wood-Collins (independent consultant) and Tim Giles from Independent Economics & Finance LLP | Eight expert reports on quantification of EMG’s and lEC’s damages121 |
Respondents 3 | |
Major General (ret.) Giora Eiland | An expert report on security122 |
Dr. Steven Cook, Senior Fellow at the Council on Foreign Relations | An expert report on security123 |
Brigadier Tony Ling CBE | Two expert reports on security124 |
Mr. Graham Shuttleworth from Nera Economic Consulting | Three expert reports on lEC’s damages125 |
Joint Expert Reports | |
Calculation of EMG’s losses by Messrs. Boaz Moselle and James Nicholson from FTI Consulting (Claimant) and Messrs. John Wood-Collins and Tim Giles (Respondents 1 and 2) |
"Regardless of the procedure chosen, the arbitral tribunal shall ensure equal treatment of the parties and the right of the parties to be heard in adversarial proceedings".
- EGAS had to respond to two claimants in the same time frame that each of the claimants had to defend one case only; the Tribunal should have ordered EMG and IEC to act as co-claimants in this arbitration and by not doing so, EGAS’ right to equality of arms was breached155 (A.);
- EGAS was granted insufficient time and opportunities during the First Hearing156 (B.); and
- EGAS feels that the decisions made by the Tribunal regarding evidence afforded EGAS an unfair treatment (C.).
- EMG and IEC have been treated in this procedure as de facto co-claimants: they have produced submissions simultaneously and have been given equal time in the arbitration;
- Due to the fact that EGAS had to respond to two claimants - whose claims, significantly overlapped - EGAS was given more time to present its reply submissions157;
- The amount of time to be given to each party was agreed upon by the Parties and the Tribunal in telephone conferences and recorded in Procedural Orders issued in advance;
- Despite the schedules agreed upon and reflected in the Procedural Orders, EGAS was granted significant extensions158; and
- EGAS’ claim that it should have been granted twice as much time as EMG or IEC is totally unfounded, because EGAS was not faced with two distinct claims: in fact, there is significant overlap between the merits claims of EMG and IEC.
"In deciding the proportion of time allocated to each party the Tribunal sides with Respondents 1 and 2 and accepts that their extraordinary position, facing significant claims and counterclaims, requires that they be awarded more time than their counterparties. The Tribunal disagrees however, that the proportion of time be 50% for Respondents 1 and 2 and the remaining 50% to be split between Claimant and Respondent 3. A large part of Respondents 1 and 2’s defence, regarding admissibility and merits, is identical, irrespective of whether it is the Claimant or Respondent 3 who is pressing the claim. Bearing in mind this overlap, the Tribunal finds that a fair solution is that Respondents 1 and 2 are granted 40% of the time while the rest is split equally between Claimant and Respondent 3".
"Subject to the Tribunal’s directions, each party is free to use its allocation of time for opening statements, direct examination, cross-examining and re-examining witnesses or any other intervention".
EMG | IEC | EGAS | |
Mr. Hamdy | 30 | - | 82 |
Mr. Al Saaka | 17 | 5 | 13 |
Mr. Ronai | 1 | 1 | 25 |
Mr. Brokman | 3 | 28 | 131 |
Ms. Nudelman | - | 15 | 52 |
Mr. Amit | - | 1 | 17 |
Mr. Freeny | 59 | 43 | 91 |
Mr. Schrader | 25 | - | 61 |
Mr. Eiland | - | 54 | 75 |
Mr. Cook | 10 | 26 | 36 |
Mr. Pelham | 151 | 181 | 71 |
FTI | 70 | - | 162 |
NERA | - | 99 | 95 |
JWC | 182 | 101 | 123 |
TOTAL | 548 | 554 | 1034 |
% | 25,7% | 25,9% | 48,4% |
- It was not attributed half of the available time for examination : in fact, it was allocated almost 50% of the available time.
- It was forced to examine witnesses it did not call163: each party was free to use the time allocated to it as it deemed appropriate; if EGAS decided to cross-examine witnesses that it had not initially wished to call, that was EGAS’ decision - no party was coerced to conduct examinations.
- IEC could perform a direct examination of its quantum expert in two hours, while EGAS’ quantum experts were restricted to 30 minutes direct presentation : the table reproduced supra shows that actually, IEC’s expert (NERA) was subject to 99 minutes of examination by IEC164, while EGAS’ experts (JWC) were subject to 123 minutes of examination by EGAS165; in any case, it was ultimately EGAS’ decision how to allocate the available time.
- EMG and IEC were able to make a second direct examination on each other’s witnesses to support their common position166: In fact EGAS was granted as many rounds of examination as it wished; the Tribunal did not dismiss any witness unless it was satisfied that none of the Parties wished to put any additional question to the witness.
- EGAS was denied access to information relating to the On-Sale Agreement - especially with respect to the gas flow between IEC and EMG - and to the UCOD and OPED models167: IEC did produce the On-Sale Agreement168 and information on the gas flows169. As regards UCOD and OPED, both are optimisation programs and the former was used by IEC to calculate a part of the damages sought in this arbitration; due to its intrinsic characteristics, EGAS could not be given full access to the programs and the Tribunal has decided in this Award to disregard the calculations made by IEC based on UCOD precisely because EGAS could not verify the underlying assumptions.
- EGAS was ordered to produce documents while preparing its written submissions and seeking to respond to new submissions and expert evidence filed by EMG and IEC170: EMG, IEC and EGAS filed approximately 80, 70 and 110 communications, respectively; it is almost inevitable that some were drafted in parallel to major submissions and this risk has affected all Parties equally. As regards the specific allegation that EGAS was ordered to produce documents while preparing its Second Submission on Merits, the Tribunal redirects to the exchange of communications that took place from 26 July 2013 through 6 January 2014171. According to EGAS, it was unable to meet the originally granted deadline for the production of documents due to the political situation in Egypt at that time - an event outside of the Parties’ control172. The Tribunal encouraged all Parties to cooperate173 and urged EMG and IEC to prioritise the documents that were most essential for the preparation of its Second Submission (which was due by 20 September 2013)174 while the rest of the ordered documents would be produced on a "rolling basis" as the situation in Egypt regained normality175.
- EMG and IEC were allowed to submit new expert evidence at a stage in which it was impossible for EGAS to deal with it176: EGAS is referring to two expert reports attached to the Supplemental Submissions of 15 November 2013177. The Supplemental Submissions were required because EGAS could not meet the deadline for the production of documents and most of the documents were handed to IEC and EMG after the presentation of the Second Submissions; the Supplemental Submission gave IEC and EMG the opportunity to comment and present counterevidence with respect to the documents produced by EGAS after the Second Submission had been presented. All three Parties were extensively heard before the Tribunal adopted a decision on this matter, and the admissibility of the two expert reports is duly motivated in the Tribunal’s decision A-39. The Tribunal notes that it also granted EGAS an extension to produce counter-evidence to respond to these reports178.
- EMG was allowed to call one of its security experts (Mr. Freeny) to the Hearing, despite the fact that no counterparty had called him, but EGAS was not given the opportunity to call his legal expert (Lord Hoffman) who was not called by any counterparty179 : there is no unfair treatment when the two situations compared are different in nature. EMG’s expert was not a legal expert, while EGAS’ was. This distinction is essential to the question whether the legal expert was allowed to be heard in the First Hearing, because, as the Tribunal argued in its decision A-44, it is standard practice in international arbitration that experts on applicable law are not required to support their statement with an oral testimony, and the Tribunal did not find a solid reason to deviate from that standard practice.
- Respondents 1 and 2 aver that the Tribunal prejudged or ignored unresolved issues raised by Respondents 1 and 2, by anticipating the date in which the draft of the award would be sent to the ICC before hearing the Parties on several outstanding issues180 : this allegation became moot in light of the Tribunal’s decision A 73 in which it granted the Parties further opportunities to present their arguments on the remaining issues to be decided by the Tribunal.
- Respondents 1 and 2, the State-owned Egyptian companies entrusted with the production, distribution and sale of petroleum and natural gas - EGPC and EGAS (which, for convenience will frequently be referred to simply as "EGAS" or as the "Seller");
- Claimant, EMG, an Egyptian company with Egyptian, Israeli and American shareholders, that had constructed and was operating an underwater gas pipeline, linking Egypt and Israel, and who was buying the gas from EGAS, transporting it via the EMG Pipeline and reselling it in Israel (which will also be referred to as the "Buyer"); and
- Respondent 3, the principal final buyer of the gas, IEC, the Israeli State-owned electricity company, which used it for producing electricity.
- The gas sellers (EGPC and EGAS) and the intermediary (EMG) are bound by the "GSPA", the upstream supply agreement;
- The intermediary (EMG) and the Israeli customer (IEC) executed an "On-Sale Agreement", for the downstream supply of gas;
- All three are Parties signed an overarching "Tripartite Agreement".
- The MoU, although signed by the States, designated EGPC as the company responsible for exporting the gas.
- Egypt would sell gas to an intermediary exporter, EMG.
- The transmission of gas would take place through a Pipeline between Al Arish and Ashkelon.
- IEC was identified as the anchor customer, but the MoU "welcome[d] contracts between EMG and [other] Israel companies".
- Egypt guaranteed the supply of gas contracted or to be contracted in an amount of up to 7 BCM per year.
- A Tripartite Agreement would be signed between the Egyptian Government (through EGPC and EGAS), EMG and IEC, in which the Egyptian Government would guarantee the gas supply.
- Once other Israeli customers were identified, similar tripartite agreements would be concluded between the Egyptian Government, EMG and the final buyers.
- Mashav Initiating and Development Ltd. ["Mashav"]
- Haifa Chemicals South Limited
- Agan Chemicals Manufactures Ltd.
- Oil Refineries Limited
- Dorad Energy Limited202
- Negev Natural Gas Marketing203 plus
- O.P.C. Rotem Ltd204
- DSW Works Industries205
- DSW Works Limited206
- IC Power Israel207
"VI. REQUEST FOR RELIEF
178. The Claimant respectfully requests that the Tribunal:
(a) With respect to objections to the Tribunal’s jurisdiction and to the admissibility of the Claimant’s claims:
(i) DISMISS the First and Second Respondents’ objections to jurisdiction and admissibility in their entirety;
(ii) DECLARE that the Tribunal has jurisdiction over the Claimant’s Source GSPA claims pursuant to Article 14.9 of Annex 1 to the Source GSPA and Article 9 of the Tripartite Agreement;
(iii) DECLARE that the Tribunal has jurisdiction over the Claimant’s Tripartite Agreement claims under Article 9 of the Tripartite Agreement; and
(iv) DECLARE that the Claimant’s claims under the Source GSPA and the Tripartite Agreement are admissible.
(b) With respect to questions of liability:
(i) DECLARE that the First and Second Respondents breached their obligations under the Source GSPA;
(ii) DECLARE that the First and Second Respondents repudiated the Source GSPA, entitling the Claimant to accept that repudiation, terminate the Source GSPA, and claim full compensation under English law;
(iii) DECLARE that the First and Second Respondents breached the Tripartite Agreement; and
(iv) DECLARE that the First and Second Respondents repudiated the Tripartite Agreement, entitling the Claimant to accept that repudiation, terminate the Tripartite Agreement, and claim full compensation under English law;
(c) ORDER the First and Second Respondents to pay to the Claimant compensation of US$1,500.4 million as the principal sum due for breaches of the Source GSPA and the Tripartite Agreement and their repudiation of the Source GSPA and the Tripartite Agreement;
(d) AWARD the Claimant pre-judgment interest on all amounts payable from the relevant date of injury, as more specifically described in this pleading;
(e) DECLARE that the award of damages and interest is made net of applicable Egyptian taxes;
(f) ORDER the First and Second Respondents to indemnify the Claimant should Egypt impose tax on the Award;
(g) ORDER the First and Second Respondents to pay all of the costs and expenses of this arbitration, including the Claimant’s reasonable legal and expert fees, and the expenses of the Tribunal;
(h) AWARD the Claimant post-judgement interest on all amounts payable, as more specifically described in this pleading, until the award is paid in full; and
(i) AWARD the Claimant any other relief deemed appropriate by the Tribunal.
179. To the extent the Claimant is not fully compensated for its loss, the Claimant expressly reserves the right to seek additional or modified remedies in any other current or future arbitral proceedings, including (but not limited to) indemnification for any additional losses incurred towards third parties due to the First and Second Respondents’ breaches, and claims concerning the First Amendment to the Source GSPA".
"Request for Relief
370. In light of the foregoing, EGAS[225] respectfully reiterates its request that the Arbitral Tribunal:
1. Find and declare that it has no jurisdiction over the claims submitted by EMG or IEC in this arbitration;
2. Alternatively, to the extent the Arbitral Tribunal may find it has jurisdiction to hear any of the claims submitted in this arbitration, find and declare that such claims are inadmissible and/or premature and/or fail to state a cause of action and/or unfounded;
3. Order EMG and IEC to bear the costs of this arbitration in their entirety, including but not limited to compensation for all the arbitrators’ fees and expenses, administrative costs and legal fees, and all expenses incurred by EGAS in connection with the present dispute; and
4. Grant EGAS such further relief as the Arbitral Tribunal deems fit and proper".
"Conclusion
98. By way of summary:
(1) For the reasons given in \IEC’s First Submission, article 9 of the Tripartite Agreement confers jurisdiction on the Tribunal to determine the dispute that has arisen between EGPC/EGAS, EMG and IEC as to whether there has been compliance, in particular, with article 1 of the Tripartite Agreement. EGPC/EGAS raises no arguments of construction of article 9 to the contrary.
(2) On the true construction of article 1 of the Tripartite Agreement, it amounts to a promise to EMG, as well as IEC. Consequently, EMG was entitled to commence this arbitration on the footing of a breach of article 1, enforceable by EMG, on the part of EGPC/EGAS. If it were necessary (which it is not), EMG had a cause of action under English law for breach of contract which arises out of or in connection with the Tripartite Agreement. At the very least, there is an arguable case to that effect which is more than sufficient to found the Tribunal's jurisdiction.
(3) In any event, a cause of action is not a prerequisite for the commencement of an arbitration under article 9. The requirement is that there should be a dispute between the parties to the Tripartite Agreement. There plainly is a dispute about whether EGPC/EGAS have performed their promise to continue the supply of gas to IEC through fulfilment of their obligations under the GSPA, which is a dispute that arises out of or in connection with article 1 of the Tripartite Agreement. It is a dispute between all the parties to the Tripartite Agreement, i.e. EGPC/EGAS, EMG and IEC, regardless of whether each of those parties has a cause of action for breach of contract or not. The dispute was validly raised by EMG's Request for Arbitration and, in any event, by IEC's Counterclaim.
(4) EGPC/EGAS's "condition precedent" argument on admissibility is without substance. There is, in particular, no need to await the outcome of bilateral arbitrations under the GSPA and On-Sale Agreement before a claim for breach of article 1 of the Tripartite Agreement can be heard by this Tribunal. The Tripartite Agreement contains no such precondition which would, in any event, be unworkable and unjust. It will be for this Tribunal to determine whether there has been compliance with article 1 and, if and insofar as this may require the Tribunal to have regard to the content of obligations created by the GSPA or On-Sale Agreement and to make findings about whether they have been performed, this Tribunal will be entitled and duty-bound to do so.
99. Accordingly, the Tribunal should hold that it has jurisdiction under article 9 of the Tripartite Agreement to determine the dispute raised in the Request and the Counterclaim and order EGPC/EGAS to bear all of the costs of and occasioned by the jurisdiction phase of this arbitration, including IEC's legal costs".
"H PRAYER
294. IEC seeks the following relief from the Tribunal
(a) a declaration that EGAS/EGPC are in breach of Articles 1 and/or 2 of the Tripartite Agreement for the shortfalls in supply that IEC has suffered to date;
(b) a declaration that IEC has lawfully terminated the Tripartite Agreement on account of the continuing and repudiatory breaches by EGAS/EGPC of the Tripartite Agreement and/or breaches of the conditions of the Tripartite Agreement;
(c) an award of damages in IEC’s favour in the principal amount of US$3,566,479,895 in respect of additional fuel costs, or such other sum as the Tribunal finds appropriate;
(d) an award of damages in IEC’s favour in the principal amount of US$39,939,320 in respect of additional maintenance and associated costs;
(e) an award of damages in IEC’s favour in the principal amount of US$6,845,727 in respect of additional gasoil storage costs;
(f) an award of damages in IEC’s favour in the principal amount of US$211,225,376 in respect of LNG vessel charter costs;
(g) an award of damages in IEC’s favour for penalties for the cancellation of two LNG cargos in the principal amount of US$24,350,600;
(h) an award of damages in IEC’s favour for ship demurrage charges in the principal amount of US$445,000;
(i) an award in IEC’s favour for compound interest on the principal amount of US$2,601,612,903 (being IEC’s additional fuel costs for the historical period July 2008 through June 2013) in the amount of US$105,897,235;
(j) an award in IEC’s favour for compound interest on all other principal amounts (set out at sub-paragraphs (d) to (h) above, totalling US$282,806,023) in respect of losses already incurred as at 30 June 2013, in the amount of US$2,042,982;
(k) an award in IEC’s favour for compound interest on IEC’s total claim from 30 June 2013 to the date of any award, accruing at a daily rate of [US]$350,038, based on Bank Prime Loan Rate published by the US Federal Reserve Bank, or such other rate or on such other basis as may be fixed by the Tribunal;
(1) an award that EGAS/EGPC and/or EMG be liable in full for IEC’s costs of the arbitration, including the fees and expenses of the Tribunal, the ICC’s costs, IEC’s legal costs and expenses;
(m) an award in IEC’s favour for post-award interest at 8% per annum on any amount awarded to IEC, from the date of the award until payment, or at such rate or for such period as the Tribunal deems appropriate; and/or
(n) such other or further relief (whether against EGAS/EGPC or EMG) as the Tribunal may deem appropriate".
"1. Respondents 1 and 2 breached the Tripartite Agreement;
2. Respondents 1 and 2, and not the Claimant, are liable to Respondent 3 for any damages resulting from their failure to deliver contractual quantities of gas to the Claimant;
3. Respondents 1 and 2, and not the Claimant, are liable to Respondent 3 for any damages resulting from Respondents 1 and 2’s repudiation of the GSPA; and
4. the Claimant is not liable to Respondent 3 for any damages resulting from Respondents 1 and 2’s breaches of GSPA and the Tripartite Agreement".
"In relation to the Claimant, insofar as the Claimant may be found to have breached Art. 5 of the Tripartite Agreement prior to the termination of the GSPA and/or in such a way as to justify Respondents 1 and 2’s purported termination of the GSPA or in any other way, Respondent 3 requests that the Arbitral Tribunal award Respondent 3 compensation and interest on the basis set out above".
- For the breaches affecting the GSPA, EMG invokes jurisdiction derived from the arbitration clause contained in Art. 14.9 of Annex 1 to the GSPA, and alternatively, from Art. 9 of the Tripartite Agreement; and
- For the claims deriving from the Tripartite Agreement, the alleged jurisdictional basis is Art. 9 of that agreement.
- objects to the Tribunal’s jurisdiction over EMG’s claims, submitting two "Jurisdictional Objections" denying that the Tribunal has jurisdiction to adjudicate EMG’s claims against EGAS; and
- avers that the GSPA is void and not enforceable having been procured and executed by corruption [the "Enforceability Objection"].
- three "Admissibility Objections", arguing that these claims are inadmissible and/or premature and/or fail to state a cause of action;
- and alternatively that all claims be dismissed as unfounded; mainly because delivery failures were due to force majeure events, and thus, excused.
- that it lacks jurisdiction under Art. 14.9 of Annex 1 of the GSPA, but that it does benefit from jurisdiction under Art. 9 of the Tripartite Agreement; and
- that EGAS’ Admissibility Objections must be dismissed.
- As regards the relationship between EMG and EGAS, the Tribunal will conclude that EGAS’ obligation to deliver gas to EMG under the GSPA is reititerated, as a repeat obligation in Arts. 1 and 2 of the Tripartite Agreement, and any dispute relating to that obligation can be adjudicated by a tribunal formed under Art. 9 of the Tripartite Agreement (as the present Tribunal is), provided that IEC is also a party to such dispute (as required by Art. 14.10 GSPA), that an annual amount of gas not to exceed 2.2 BCM is delivered to EMG in compliance with the GSPA, for redelivery to IEC under the On-Sale Agreement.
- As regards the relationship between IEC and EGAS, the conclusion will be that Art. 1 of the Tripartite Agreement also affords IEC a freestanding enforceable right for delivery of gas vis-à-vis EGAS up to the same annual maximum quantity, for delivery under the GSPA and re-delivery under the On-Sale Agreement.
- the requirement that EGAS act as a Reasonable and Prudent Piepline Operator ["RPPO"]; and
- the additional consequence that the attacks could have been mitigated or prevented, had EGAS acted as a RPPO [the "Avoidance Requirement"].
- the first is a declaration that EGAS has repudiated the Tripartite Agreement, as a consequence of its wrongful termination of the GSPA [the "Tripartite Repudiatory Breach"]; and
- the second that EGAS breached its delivery obligations under the Tripartite Agreement [the "Tripartite Delivery Breaches"].
the invoices due for the delivery of gas (in an amount of USD 23 Million). It is worth noting that EGAS failed to put IEC on notice of the potential termination of the GSPA.