Annulment Counter-Memorial | Eiser Infrastructure Limited and Energía Solar Luxembourg S.à r.l.'s Counter-Memorial on Annulment dated June 11, 2018 |
Annulment Hearing | Hearing on Annulment held on March 14 and 15, 2019 in Paris |
Annulment Memorial | Spain's Memorial on Annulment dated March 8, 2018 |
Annulment Rejoinder | Eiser Infrastructure Limited and Energía Solar Luxembourg S.à r.l.'s Rejoinder on Annulment dated November 6, 2018 |
Annulment Reply | Spain's Reply on Annulment dated August 24, 2018 |
Application for Annulment | Spain's Application for Annulment of the Award dated July 21, 2017 |
Arbitration Rules | ICSID Rules of Procedure for Arbitration Proceedings |
Award | Award rendered by the Arbitral Tribunal on May 4, 2017 |
Brattle Group/ Brattle | The Brattle Group, the Eiser Parties' quantum and regulatory experts in the Underlying Arbitration |
Committee | The ad hoc Committee composed of Prof. Ricardo Ramírez Hernández (President), Mr. Makhdoom Ali Khan, and Judge Dominique Hascher |
CSP Plant | Concentrated Solar Power Plant |
Dr. Alexandrov | Dr. Stanimir A. Alexandrov, member of the Arbitral Tribunal in the Underlying Arbitration |
EC | European Commission |
ECT | Energy Charter Treaty, which entered into force on April 16, 1998 for Luxembourg, the United Kingdom and the Kingdom of Spain |
Eiser Parties/ Claimants | Eiser Infrastructure Limited and Energía Solar Luxembourg S.à r.l. |
Ex. C-[#] | Eiser Parties' Exhibit |
Ex. CL-[#] | Eiser Parties' Legal Authority |
Ex. R-[#] | Spain's Exhibit |
Ex. RL-[#] | Spain's Legal Authority |
First Brattle Quantum Report | Expert Report of The Brattle Group – Financial Damages to EISER, dated October 30, 2014 submitted in the Underlying Arbitration |
First Brattle Regulatory Report | Expert Report of The Brattle Group – Changes to the Regulation of Concentrated Solar Power Installations in Spain, dated October 29, 2014 submitted in the Underlying Arbitration |
ICSID Convention | Convention on the Settlement of Investment Disputes between States and Nationals of Other States, which entered into force on October 14, 1966 |
ICSID or Centre | International Centre for Settlement of Investment Disputes |
Mr. Lapuerta | Mr. Carlos Lapuerta (Principal of The Brattle Group), expert on economic analysis and financial valuation in the Underlying Arbitration |
Second Brattle Quantum Report | Second Expert Report of The Brattle Group – Rebuttal Report: Financial Damages to EISER, dated September 17, 2015 submitted in the Underlying Arbitration |
Second Brattle Regulatory Report | Second Expert Report of The Brattle Group – Rebuttal Report: Changes to the Regulation of Concentrated Solar Power Installations in Spain, dated September 17, 2015 submitted in the Underlying Arbitration |
Sidley Austin | Sidley Austin LLP |
Spain/ Applicant/ Respondent | the Kingdom of Spain |
Tr. Day [#] [speaker], [page:line] | English transcript of the Annulment Hearing (as revised by the Parties on May 9, 2019) |
Tribunal | Arbitral Tribunal composed of Prof. John R. Crook (President), Dr. Stanimir A. Alexandrov, and Prof. Campbell McLachlan |
Underlying Arbitration | Arbitration proceedings between Eiser Infrastructure Limited and Energía Solar Luxembourg S.à r.l. and the Kingdom of Spain, ICSID Case No. ARB/13/36 |
Vienna Convention | Vienna Convention on the Law of Treaties. United Nations Treaty Series, Vol. 1155, p. 331 (May 23, 1969) |
For the Applicant :
Counsel
Mr. José Manuel Gutiérrez Delgado Abogacía del Estado, Ministerio de Justicia
Ms. María José Ruiz Sánchez Abogacía del Estado, Ministerio de Justicia
Mr. Pablo Elena Abad Abogacía del Estado, Ministerio de Justicia
Ms. Patricia Elena Froehlingsdorf Nicolás Abogacía del Estado, Ministerio de Justicia
Ms. Gabriela Álvarez Ávila Curtis, Mallet-Prevost, Colt & Mosle LLP Mr. Benard Preziosi Curtis, Mallet-Prevost, Colt & Mosle LLP
Ms. Arianna Sanchez (by Curtis, Mallet-Prevost, Colt & Mosle LLP videoconference)
Mr. Ricardo Mier y Terán Curtis, Mallet-Prevost, Colt & Mosle LLP Ms. Mariana Gómez Vallin Curtis, Mallet-Prevost, Colt & Mosle LLP
For the Eiser Parties :
Counsel
Mr. Jeffrey Sullivan Gibson, Dunn & Crutcher LLP
Mr. Rahim Moloo Gibson, Dunn & Crutcher LLP
Ms. Ceyda Knoebel Gibson, Dunn & Crutcher LLP
Ms. Ankita Ritwik Gibson, Dunn & Crutcher LLP
Mr. Theo Tyrrell Gibson, Dunn & Crutcher LLP
Court Reporters:
Mr. Dante Rinaldi D-R Esteno
Ms. Dawn Larson Worldwide Reporting
Interpreters:
Ms. Amalia Thaler - de Klemm English/Spanish Interpreter
Ms. Gertrudis Durkop English/Spanish Interpreter
Mr. Daniel Giglio English/Spanish Interpreter
Under Article 52(1)(a) of the ICSID Convention, a party may seek the annulment of an award if the tribunal "was not properly constituted." According to the Applicant, this provision has to be read together with Chapter IV, Section 2 of the ICSID Convention titled "Constitution of the Tribunal", which includes Article 40(2). Article 40(2) states that the arbitrators must possess the qualities listed in Article 14(1), which include impartiality and independence. Thus, under Article 52(1)(a) of the ICSID Convention, an award can be annulled for improper constitution of the tribunal if an arbitrator did not possess the qualities of impartiality and independence.7
The Applicant rejects the Eiser Parties' argument that Article 52(1)(a) of the ICSID Convention only applies to procedural deficiencies regarding the constitution of the tribunal at the outset of an arbitration. The Applicant's position is based on the following reasons: (i) the Eiser Parties have not provided a single authority that supports such interpretation;9(ii) issues related to the independence and impartiality of the arbitrators can arise throughout the entire proceeding, as supported by Rule 6 of the Arbitration Rules;10 and, (iii) previous committees and commentators have recognized that the tribunal was not properly constituted if an arbitrator did not possess the qualities of independence and impartiality.11
The Applicant recognizes that, as a general rule, a party must challenge the arbitrator promptly, when the relevant facts are known and, in any event, before the proceeding is declared closed. However, it has been recognized that a party can still challenge the independence and impartiality of an arbitrator in annulment proceedings if the relevant facts only became known once the arbitration proceedings were closed.12
According to the Applicant, the facts surrounding the close relationship between Dr. Alexandrov and Brattle only came to light after the Award was rendered, when public reports of such relationship emerged in July 2017, as a consequence of a challenge filed in an unrelated arbitration involving Pakistan.13 Therefore, it can still raise the challenge to Dr. Alexandrov's independence and impartiality at the annulment stage.
According to the Applicant, to demonstrate the lack of independence and impartiality of an arbitrator, it must prove that a reasonable third party would consider that there were reasonable grounds for an appearance of dependence or bias.14 It is not required, however, to prove actual bias.15 Further, pursuant to Article 57 of the ICSID Convention, the lack of the required qualities must be "evident" or "obvious" but does not need to be "self-evident."16 When the challenge to the independence and impartiality of an arbitrator is raised for the first time in annulment, the committee must approach the question de novo.17
First, according to the Applicant, during the course of his 15 years at Sidley Austin's Washington, D.C. office, where Dr. Alexandrov was a partner and co-head of the firm's international arbitration practice, Dr. Alexandrov and his team appointed the Brattle Group in numerous cases where he served as counsel, including, but not limited to, nine investor-State arbitrations, including eight at ICSID alone, and numerous commercial arbitrations.21 In four of these cases Mr. Lapuerta was the testifying expert.22
In Spain's view, the fact that this took place while Dr. Alexandrov was at Sidley Austin is of particular relevance for two reasons. First, the identity of an arbitrator and his law firm must be considered as one for the purpose of identifying and revealing conflicts of interest. Similarly, individual experts cannot simply be detached from the company for which they work, as the Eiser Parties assert.23 Second, it has been recognized that the fact that an arbitrator is co-head of his firm's worldwide international arbitration practice implies a degree of connection and coordination that creates conflicts even if the arbitrator himself was not involved in the representation.24
Moreover, in two of these cases, Dr. Alexandrov was working with Brattle at the same time that the Underlying Arbitration was taking place. In Pluspetrol and Bear Creek, Dr. Alexandrov and/or his client appointed Mr. Lapuerta and the Brattle Group as the experts, and worked together while the Underlying Arbitration was still pending.25
Although a failure to disclose does not automatically demonstrate the arbitrator's lack of impartiality and independence, it does so, according to the Applicant, when it is a "part of a pattern of circumstances raising doubts as to impartiality."37 For the Applicant, Dr. Alexandrov's failure to disclose his relationship with Brattle Group is not an isolated occurrence and has also occurred in the Raiffeisen Bank, SolEs Badajoz, and Tethyan Copper cases.38 A reasonable third party would therefore conclude that Dr. Alexandrov was unable to objectively and impartially assess the opinions of Brattle and that the Award should be annulled.39
If the Committee were to accept a more expansive interpretation of Article 52(1)(a) of the ICSID Convention and allowed the application of Article 57 of the ICSID Convention "under the guise of annulment",43 a view which the Eiser Parties do not support, the Committee would have to do so "with the safeguards imposed by the Convention on the standards of review for annulment",44 especially because the challenged arbitrator cannot furnish any explanations.45
Second, the cases in which experts from Brattle, other than Mr. Lapuerta, worked together with lawyers from Sidley Austin do not support Dr. Alexandrov's close personal relationship with Mr. Lapuerta. These include:58
- Five ICSID cases where Mr. Lapuerta was not involved and that were handled by Sidley Austin's arbitration team in Washington D.C.;59
- Four commercial arbitration cases handled in whole or in part by Sidley Austin's arbitration team in Washington D.C.;60 and
- One investment arbitration case at the initial stages.61
Out of these four cases, there is only one in which Dr. Alexandrov worked with Mr. Lapuerta while the Underlying Arbitration was taking place, namely Pluspetrol v. Perupetro. As recognized by the Secretary-General of the PCA, "concurrent service as an arbitrator and as counsel in an unrelated matter in which the same expert has been engaged does not automatically result in a conflict of interest warranting disqualification under the ICSID Convention."64
For the Eiser Parties, the SolEs Badajoz and Tethyan Copper cases are irrelevant for establishing the basis of any conflict because, in these cases, Dr. Alexandrov was acting as an arbitrator and not as counsel.65 Further, the Eiser Parties argue that the Applicant's description of the SolEs Badajoz case is misleading. While the unchallenged co-arbitrators were equally divided on the matter, the Applicant cannot know without being privy to the deliberations that one of the co-arbitrators believed that there were justifiable doubts regarding Dr. Alexandrov's impartiality.66
In any event, even if the Committee concludes that Dr. Alexandrov's engagements with Mr. Lapuerta constituted a close professional relationship, such relationship does not necessarily create a conflict.67 Dr. Alexandrov has further confirmed that his relationship with the Brattle Group did not go beyond engaging them as experts and that he has not had any other joint activities with Mr. Lapuerta or any other expert from Brattle.68
Fourth, the Eiser Parties draw the Committee's attention to the fact that in three different instances, it has already been decided that Dr. Alexandrov's relationship with Brattle does not constitute a ground for disqualification. In fact, the very same issue that the Applicant is presenting to the Committee was already decided in Tethyan Copper v. Pakistan. In that case, it was decided that there was no manifest lack of impartiality on the part of Dr. Alexandrov.69
For the Eiser Parties, a lack of disclosure does not automatically imply the existence of a lack of independence and impartiality.72 The obligation to disclose under ICSID Arbitration Rule 6(2)(b) is a subjective standard. As such, it is for the arbitrator to exercise his or her discretion whether to disclose a fact or circumstance. An arbitrator cannot be criticized for honestly exercising that discretion.73
According to the Eiser Parties, even if the Committee decides to review de novo the request to disqualify Dr. Alexandrov, it must reject Spain's case because there is no manifest appearance of bias or dependence. Spain has the burden to point to specific facts that demonstrate bias, which it fails to do because its arguments are based on inferences and speculation and not on objective evidence.76
According to the Applicant, under Article 52(1)(d) of the ICSID Convention, an award may be annulled if "there has been a serious departure from a fundamental rule of procedure." This requires that the departure be: (a) "serious"; and, (b) from a "fundamental" rule of procedure.123 For the Applicant, this test is the same as the "three-limb test" proposed by the Eiser Parties since the additional requirement the existence of a departure is implied in this two-tier test.124
On the one hand, for a departure to be "serious", it must have had or may have had a material effect on the tribunal's decision.125 According to the Applicant, contrary to the Eiser Parties' contention, evidence of an "actual material prejudice" and the showing that the violation created a substantially different result are not required.126 On the other hand, the term "fundamental rule of procedure" refers to a set of minimal standards of procedure that must be respected and includes the right to an independent and impartial tribunal, and the right for the parties to be heard and to be treated equally.127
According to the Applicant, the right to be heard encompasses different protections including: (i) the right to submit arguments and evidence that it deems relevant to support its case, and to do so with a comparatively equal opportunity to that given to the other party;131(ii) the right to respond to the arguments and evidence submitted by the other party, including the right to make submissions when new evidence is received and considered by the tribunal;132 and (iii) not being unjustifiably denied a request for document production, especially when the tribunal, after denying such request, concludes that there was an absence of evidence on the matter.133
The Tribunal allowed the Eiser Parties, during the Hearing, to submit new documents into the record, one of which was used by Brattle as a basis for its new damages calculations presented for the first time at the Hearing. Despite the Applicant's objections, the Tribunal allowed this, failed to give a reasonable opportunity to the Applicant to rebut this new material, and relied on such calculations in its determination of damages in the Award.135
The Eiser Parties do not contest that the right to be heard has been recognized as a fundamental rule of procedure. However, for the annulment to proceed, it must be unequivocally and objectively established that a tribunal has violated this right. As such, this right is not violated when a party does not avail itself of the opportunity to be heard that was granted to it and does not preclude the Tribunal's discretion to admit and evaluate evidence. Similarly, the right to be treated equally is not violated when a request for document production is denied and does not require the parties to have been granted an equal number of requests.146
In Spain's view, this is confirmed by: (a) the Updated Background Paper on Annulment, which explains that under this provision "[t]he parties may raise an objection concerning compliance with [the provisions of Chapter I of the ICSID Arbitration Rules, entitled 'Establishment of the Tribunal']";185 and (b) the committee in EDF v. Argentina, which stated that Article 52(1)(a) must be understood as referring to the requirements of Chapter IV, Section 2 of the ICSID Convention ("Constitution of the Tribunal"). These provisions regarding the "constitution of tribunal", in turn, include all those qualities that an arbitrator must possess.186
Article 40 of the ICSID Convention, which is also part of Chapter IV, Section 2 of the same instrument, establishes that arbitrators "shall possess the qualities stated in paragraph (1) of Article 14." According to the Applicant, it is well stablished that Article 14 of the ICSID Convention includes the qualities of impartiality and independence.187 Therefore, if an arbitrator did not possess the qualities of Article 14, including those of independence and impartiality, the tribunal was not properly constituted and, therefore, the award might be annulled under Article 52(1)(a) of the ICSID Convention.188
For the Eiser Parties, when the facts on which a challenge is based became known after the award was rendered, the appropriate remedy is the revision of the award in accordance with Article 51 of the ICSID Convention. Thus, the Applicant should seek the revision of the Award and not its annulment, which will also allow Dr. Alexandrov to furnish explanations.199
The Eiser Parties criticize the decision of the EDF committee, relied upon by Spain, for erring in the interpretation of Article 52(1)(a) of the ICSID Convention. According to them, the EDF decision failed to address the drafting history of the ICSID Convention.200 It is also inconsistent since, one the one hand, it concluded that challenges to the independence and impartiality of an arbitrator should be heard by the remaining members of the tribunal and, on the other hand, still rejected that the revision is the appropriate remedy.201 In addition, the EDF decision is inconsistent with the object and purpose of the Convention and with the role of the annulment committee, which should not undertake a de novo review as if it were an arbitral tribunal assessing the merits of a disqualification proposal.202
The Parties are in disagreement as to the correct interpretation of Article 52(1)(a) of the ICSID Convention. The Committee will interpret this provision in accordance with the customary rules of interpretation, as reflected in Article 31 of the Vienna Convention. Accordingly, the Committee will interpret Article 52(1)(a) in light of its (1) text; (2) context; (3) object and purpose; and, (4) in light of any relevant rules of international law applicable in the relations between the Parties.203
(1) Either party may request annulment of the award by an application in writing addressed to the Secretary-General on one or more of the following grounds:
(a) that the Tribunal was not properly constituted;
[…]
(1) Persons designated to serve on the Panels shall be persons of high moral character and recognized competence in the fields of law, commerce, industry or finance, who may be relied upon to exercise independent judgment. Competence in the field of law shall be of particular importance in the case of persons on the Panel of Arbitrators.
The Committee notes the difference between the Spanish and English texts of paragraph (1) of Article 14. Whilst the English text reads, "may be relied upon to exercise independent judgment", the Spanish version uses the words "inspirar plena confianza en su imparcialidad de juicio" which may be translated into English as "to inspire full confidence in their impartiality of judgment."210 Earlier, other committees have observed that this requirement encompasses two qualities: independence and impartiality. This Committee cites with approval the observations of the EDF committee:211
[…] the general practice has been to require that arbitrators may be relied upon to exercise independent judgment and inspire full confidence in their impartiality.212
Art. 14(1) describes the qualifications of individuals who may be designated to serve on the Panel of Arbitrators […] the individuals must be persons of high moral character who may be relied upon to exercise their independent judgment. Under Art. 40(2) even arbitrators appointed from outside the Panel of Arbitrators must possess these qualities. Appointment of an arbitrator who manifestly does not possess these qualities may be put forward as a ground for annulment […].213
With respect to object and purpose of the text, features such as the finality of awards, exclusion of appeals, and the exceptional nature of the annulment remedy may be among those that inform the role of annulment committees.220 As other committees have observed, the role of an annulment committee relates to "procedural legitimacy",221 "the legitimacy of the award,"222 and "safeguard[ing] the integrity" of the proceedings and the award.223 Thus, while agreeing with the Eiser Parties about the "limited scope" of the annulment procedure,224 this Committee holds that there can be no greater threat to the legitimacy and integrity of the proceedings or of the award than the lack of impartiality or independence of one or more of the arbitrators. As the Suez committee stated:
In this regard, the Committee agrees with Respondent that the parties' confidence in the independence and impartiality of the arbitrators deciding their case is essential for ensuring the integrity of the proceedings and the dispute resolution mechanism as such; thus, in principle, a lack of the qualities in Article 14(1) may serve as ground for annulment under Article 52(1)(a).225
a) was the right to raise this matter waived because the party concerned had not raised it sufficiently promptly?
b) if not, has the party seeking annulment established that a third party would find an evident or obvious appearance of lack of impartiality or independence on the part of an arbitrator on a reasonable evaluation of the facts of the case (the Blue Bank standard)? and
c) if so, could the manifestly apparent lack of impartiality or independence on the part of that arbitrator have had a material effect on the award?
According to the Applicant, as a general rule, a party challenging an arbitrator for lack of independence and impartiality is required to do so promptly and, in any event, before the proceeding is closed. However, it has been recognized that this general rule cannot prevent a party from challenging that arbitrator for the first time in the annulment phase if the relevant facts only became known after the arbitration proceedings were closed.230 In this case, the Applicant argues that it became aware of the facts on which it bases its challenge to Dr. Alexandrov only after the Eiser Award was rendered. According to the Applicant, in these circumstances, it must be allowed to raise the issue in this annulment proceeding.
The Applicant argues that the relationship between Dr. Alexandrov and the Brattle Group, in particular Mr. Lapuerta, came to the Applicant's attention after the Eiser Award was issued in May 2017. It is only in July 2017 that public reports of this relationship emerged, in the context of a disqualification proposal filed in an unrelated arbitration involving Pakistan.231 As a consequence, Spain was deprived of the opportunity to challenge Dr. Alexandrov in the course of the Underlying Arbitration proceeding.232
The Eiser Parties note that Spain relies on a series of press reports published in GAR and Investment Arbitration Reporter in July 2017, which refer to a challenge filed in the Tethyan Copper v. Pakistan case.235 However, in their view, the fact that Dr. Alexandrov had previously worked on the same cases alongside Mr. Lapuerta was public knowledge years before the Award was issued.236 The Eiser Parties point to the following factors:
a) The decision and awards in PSEG v. Turkey and Pluspetrol v. Perupetro, cases in which Dr. Alexandrov and Mr. Lapuerta worked together, were issued in June 2004,237 January 2007,238 and May 2015,239 years before the Eiser Award was issued in May 2017;240
b) GAR published an article in May 2015 where it was stated that both Dr. Alexandrov and Mr. Lapuerta were retained by the respondent in Pluspetrol v. Perupetro ;241
c) Spain itself relies on information that was publicly available, including awards issued and made public in November 2007 and August 2009, and in a GAR article of September 2016;242
d) Dr. Alexandrov's curriculum vitae, which was provided to the Parties when he was appointed as arbitrator in the Eiser case, listed his representations of Bulgaria, Costa Rica, Peru and Turkey. For the Eiser Parties, this covers the cases of PSEG v. Turkey, Pluspetrol v. Perupetro, and Bear Creek v. Peru.243
For the Applicant, the standards for the disqualification of arbitrators under Article 57 of the ICSID Convention are directly applicable to the annulment under Article 52(1)(a). Accordingly, pursuant to the decision in Blue Bank and many others that have followed it, there has to be an objective "appearance of dependence or bias" and the Applicant is not required to demonstrate "proof of actual dependence or bias."247 Thus, the standard is "whether, based on a reasonable evaluation of the facts […] a third party would find" an "evident or obvious appearance of lack of impartiality."248
First, the Applicant argues that proof of the relationship between Dr. Alexandrov and the Brattle Group, in particular with Mr. Lapuerta, is based on the following facts:252
a) During his time at Sidley Austin, where he was a partner and co-head of international arbitration, Dr. Alexandrov and his team appointed Brattle in numerous cases, four of which involved Mr. Lapuerta as the testifying expert.253 According to Spain, this is particularly relevant because the arbitrator bears the identity of his firm, which is reinforced by his role as co-head of the firm's worldwide international arbitration practice;254
b) At the same time he was serving as arbitrator in Eiser, Dr. Alexandrov was working with the Brattle Group in Pluspetrol and Bear Creek. In Pluspetrol, the testifying expert was Mr. Lapuerta;255
c) In four cases, Blusun v. Italy, Ioan Micula v. Romania, Tethyan v. Pakistan, and SolEs Badajoz v. Spain, Dr. Alexandrov was appointed as an arbitrator by the same party that engaged the Brattle Group as its expert. In Blusun and SolEs Badajoz, the testifying expert was Mr. Lapuerta.256
In the eyes of the Eiser Parties, Spain's case is based on speculations. Spain has resorted to misrepresenting the facts in an attempt to amplify the magnitude of the professional relationship between Dr. Alexandrov and Mr. Lapuerta.269 Specifically, the Eiser Parties argue that:
a) In the 15-year period at issue, there are only three ICSID cases in which Dr. Alexandrov and Mr. Lapuerta were respectively engaged by the same party as counsel and expert; these are PSEG v. Turkey, Alapli v. Turkey, and Pluspetrol v. Perupetro ;270
b) Pluspetrol is the only case in which Mr. Lapuerta and Dr. Alexandrov were engaged by the same party at the same time Dr. Alexandrov was sitting as arbitrator in the Underlying Arbitration;271
c) Mr. Lapuerta was not the testifying expert in Bear Creek ;272
d) There is an undisclosed commercial arbitration in which the same party engaged Sidley Austin and Mr. Lapuerta; as of October 12, 2017, this arbitration was suspended and Dr. Alexandrov was asked by the party to remain involved only if the proceeding resumed;273
e) The SolEs Badajoz and Tethyan Copper cases are irrelevant for the purpose of establishing the basis of any conflict because Dr. Alexandrov was acting as arbitrator and not counsel;274 and
f) Overall, there are only four cases in which Dr. Alexandrov and Mr. Lapuerta worked, respectively, as counsel and expert witness for the same party (PSEG v. Turkey, Alapli v. Turkey, Pluspetrol v. Perupetro, and a commercial arbitration, which was in abeyance).275
The Eiser Parties conclude that Spain has offered no evidence of any "'close relationship'" between Dr. Alexandrov and Mr. Lapuerta or any "'unique reliance'" by the former upon the latter.276 On the contrary, his relationship with any of the experts from the Brattle Group did not go beyond engaging them as experts, which is common practice in international arbitration.277 In any case, even if the Committee were to conclude that Dr. Alexandrov's engagements with Mr. Lapuerta constitute a close professional relationship, the Eiser Parties contend that such a relationship does not create a conflict.278
Based on the submissions of the Parties, the Committee has identified the following relevant uncontested facts:
a) Dr. Alexandrov was appointed as an arbitrator by the Eiser Parties in the Underlying Arbitration;280
b) Mr. Lapuerta, together with other experts from the Brattle Group, was selected as the damages expert by the Claimants in the Underlying Arbitration;281
c) Between May 2002 and August 2017, Dr. Alexandrov worked at Sidley Austin. He served as partner and co-chair of Sidley Austin's international arbitration practice;282
d) The Tribunal in the Underlying Arbitration was constituted in July 2014 and the Award was rendered in May 2017;283
e) There are four cases in which Dr. Alexandrov was appointed as arbitrator and the Brattle Group was engaged by the party that appointed him as arbitrator; these cases are Blusun v. Italy, Ioan Micula v. Romania, Tethyan Copper v. Pakistan, and SolEs Badajoz v. Spain ;284
i. In two of these four cases, the testifying expert was Mr. Lapuerta: Blusun v. Italy and SolEs Badajoz v. Spain ; and
ii. Three of these cases ran in parallel with the Underlying Arbitration: Blusun v. Italy, Tethyan Copper v. Pakistan, and SolEs Badajoz v. Spain.
f) There are at least eight other cases in which Dr. Alexandrov was engaged as counsel by the party that engaged the Brattle Group as its expert;285
i. These eight cases are Bayindir v. Pakistan, PSEG v. Turkey, Archer Daniels v. Mexico, Alapli v. Turkey, Pluspetrol v. Perupetro, LSF-KEB Holdings v. Korea, Bear Creek v. Peru, and Veolia v. Lithuania ;286
ii. At least two of these cases - Pluspetrol v. Perupetro, Bear Creek v. Peru -overlapped with the Underlying Arbitration;
iii. In three of these cases - Pluspetrol v. Perupetro, PSEG v. Turkey, and Alapli v. Turkey - the testifying expert was Mr. Lapuerta; and
iv. In Bear Creek v. Peru, Mr. Lapuerta was not the testifying expert.
g) In addition to the above-mentioned eight cases, there is at least one undisclosed investor-state arbitration and one undisclosed commercial arbitration in which Sidley Austin was engaged as counsel by the party that engaged the Brattle Group as experts;287
i. Both cases overlapped with the Underlying Arbitration; however, as of October 12, 2017, the tribunal in the investor-state arbitration was yet to be constituted;288 and
ii. Mr. Lapuerta was engaged as the testifying expert only in the commercial arbitration.289
Impartiality refers to the absence of bias or predisposition towards a party. Independence is characterized by the absence of external control. Independence and impartiality both "protect parties against arbitrators being influenced by factors other than those related to the merits of the case." Articles 57 and 14(1) of the ICSID Convention do not require proof of actual dependence or bias; rather it is sufficient to establish the appearance of dependence or bias.
The applicable legal standard is an "objective standard based on a reasonable evaluation of the evidence by a third party." As a consequence, the subjective belief of the party requesting the disqualification is not enough to satisfy the requirements of the Convention.
Finally, regarding the meaning of the word "manifest" in Article 57 of the Convention, a number of decisions have concluded that it means "evident" or "obvious," and that it relates to the ease with which the alleged lack of the qualities can be perceived.292
[…] the Chairman concludes that it has been demonstrated that a third party would find an evident or obvious appearance of lack of impartiality on a reasonable evaluation of the facts in this case.293
In Tethyan Copper, Pakistan challenged arbitrator Dr. Alexandrov based on his relationship with the Brattle Group.296 The PCA's Secretary-General Hugo Hans Siblesz found in his Opinion that Pakistan "has not shown that the relationship between Dr. Alexandrov and Brattle goes beyond a normal working relationship as is common between counsel and valuation experts involved in international arbitration cases" and that "such a working relationship would [not] lead to a lack of the required qualities of an arbitrator."297 Having reviewed the Parties' submissions, Dr. Alexandrov's explanations and the PCA Secretary-General's Opinion, the unchallenged arbitrators reached the conclusion that the Proposal for the Disqualification of Dr. Alexandrov did not meet the standard set forth in Article 57 of the ICSID Convention. In the same case, later in the proceeding, Dr. Jim Yong Kim (Chairman of the Administrative Council) dismissed a further challenge against Dr. Alexandrov and his fellow arbitrators.298
The Committee is of the view that the fact pattern in the Underlying Arbitration is not the same.301 First, an important difference between Tethyan Copper and the case at hand is that in Tethyan Copper the Members of the Tribunal were aware of Dr. Alexandrov's relationship with Brattle and Prof. Davis. Moreover, the unchallenged arbitrators (Lord Hoffmann and Prof. Sachs) issued a decision on the disqualification proposal regarding Dr. Alexandrov after receiving the PCA Secretary-General's Opinion, on September 5, 2017.302 It was clear, therefore, that the other two arbitrators did not believe that his involvement would affect their deliberations.
Moreover, in Tethyan Copper, the Brattle Group expert involved was Prof. Davis. When asked, Dr. Alexandrov stated that he had only interacted, as counsel, with this expert in a single case. Furthermore, it was Prof. Davis' disclosure regarding the Bear Creek case which triggered the challenge against Dr. Alexandrov.303 Even though it could be said that the Bear Creek case where Prof. Davis acted as damages expert, with Dr. Alexandrov acting as counsel, was concurrent with the Tethyan Copper case where Dr. Alexandrov acted as arbitrator, the fact is that as Prof. Davis stated, his "[…] engagement [in the Bear Creek case] ha[d] concluded."304 This is confirmed by the fact that the Bear Creek case was almost over, with no filings pending, when the challenge was brought by Pakistan.305 It seems that the PCA's Secretary-General based his ruling on the same assumption, i.e. that in Tethyan Copper there was no "concurrent service" with Dr. Alexandrov acting as arbitrator in Tethyan Copper and Dr. Alexandrov working as counsel with the damages expert in Bear Creek :
Against this background, I conclude that the present procedural situation may, in principle, give rise to an issue conflict. As a general matter, it cannot be ruled out that the concurrent service of an arbitrator as counsel in another pending arbitration, in which the damages expert of the party that he represents has submitted a similar and "innovative" damage valuation method, may prevent that arbitrator from evaluating this method with an open mind. Whether an issue conflict that warrants the disqualification of the arbitrator arises will however depend on the specific facts of a case and the applicable legal standard.306 (emphasis added)
Two relevant and connected responsibilities flow from an arbitrator's duty of disclosure, one substantive and the other temporal. Substantive is the obligation to disclose "any other circumstance that might cause [his/her] reliability for independent judgment to be questioned by a party."313 Temporal is the connected and ongoing nature of this substantive obligation, whereby the arbitrator "assume[s] a continuing obligation promptly to notify the Secretary-General of the Centre of any such relationship or circumstance that subsequently arises during this proceeding."314
The ongoing obligation to disclose cannot be construed narrowly in favor of the arbitrator. It must be approached from the point of view of a party.315 Disclosure inoculates arbitrators from the possibility of any, real or perceived, conflict of interest. As the IBA Guidelines state, "[a]ny doubt as to whether an arbitrator should disclose certain facts or circumstances should be resolved in favour of disclosure."316 There are multiple ways in which a conflict of interest may arise when an arbitrator also acts or has acted as counsel, in another dispute, albeit between different parties. The risks and possibilities of conflict of interest, inherent in double-hatting, dictate caution.
It is the view of this Committee that these facts318 demonstrated enough past and present professional connections and interaction between Dr. Alexandrov, as counsel and as member of the law firm Sidley Austin,319 on the one hand, and the Brattle Group and Mr. Lapuerta, on the other, to require that this relationship be disclosed to the Parties and to the other arbitrators. These past and present connections and interactions should have alerted Dr. Alexandrov to the possibility that his independence and impartiality may be questioned, by one of the Parties to the case before him. As the House of Lords observed in the Pinochet case: "impartiality may be compromised not only through a specific act but also where the appearance of impartiality has not been strongly guaranteed."320
The Eiser Parties argue that the IBA Guidelines do not expressly list this particular relationship i.e., of counsel and expert as subject to mandatory disclosure.321 It could not, therefore, according to them have led to his disqualification, as a member of the Tribunal. Similarly, according to them, this relationship cannot provide a ground for annulment under Article 52. The Committee has difficulties accepting this submission as correct. First, the Committee understands that the IBA Guidelines' list is not exhaustive.322 Second, these are "guidelines" and cannot be treated as a set of binding and exhaustive rules with respect to conflicts. Third, the Committee notes that the Guidelines do not include this type of relationship in the "Green List", either. The Green List identifies, "specific situations where no appearance and no actual conflict of interest exists from an objective point of view."323
In the Committee's view, in this case, the duty to disclose was warranted due to the respective roles of a damages expert and counsel in an arbitration. It was warranted not only because of the existence of such a relationship but also by the extent of the past and present interactions, at issue. These taken together triggered Dr. Alexandrov's obligation to disclose. The Committee is, therefore, of the view that Dr. Alexandrov should have disclosed his relationship with Mr. Lapuerta. Spain submits that there was also a duty on the part of Mr. Lapuerta, as an expert, to disclose his relationship with Sidley Austin and Dr. Alexandrov according to the IBA Rules on the Taking of Evidence in International Arbitration.326 The Committee is not inclined to express any opinion on this submission, as even a disclosure by Mr. Lapuerta would not have absolved Dr. Alexandrov from his disclosure obligations as an arbitrator.
According to the Applicant, for an award to be annulled under Article 52(1)(d) of the ICSID Convention, two elements are required: (a) the departure has to be "serious"; and (b) it must be from a "fundamental" rule of procedure.328 For Spain, there is no doubt that the right to an independent and impartial tribunal is a fundamental rule of procedure.329
They argue that committees have adopted two positions to consider that a departure is "serious." The first approach, preferred by the Eiser Parties, requires the existence of an actual material prejudice and the showing that the violation of the rule caused a "substantially different result."337 The second approach, presented by the Applicant, requires only the showing of a "potential effect" of the departure on the award.338 Under either approach, the departure has to be "outcome-determinative."339
Turning to the Award itself, unanimity does not impede annulment. This is axiomatic because it is impossible for an annulment committee to pierce the veil of a tribunal's deliberations or poll arbitrators.343 Irrespective of the independence and impartiality of the two other arbitrators on the Tribunal,344 each member of the Tribunal, including Dr. Alexandrov, is expected to have influenced the other two with his views and analysis, during the course of deliberations. It is in the very nature of deliberations that arbitrators exchange opinions and are persuaded or influenced by the opinions of their colleagues. That makes us conclude that it would be unsafe to hold that Dr. Alexandrov's views and analysis could not have had any material bearing on the opinions of his fellow arbitrators. It is not improbable that they had such effect and, therefore, excluding this possibility from consideration would go against the nature of deliberations.
A departure is serious if the violation of the fundamental rule of procedure produced a material impact on the award. The applicant however is not required to prove that the violation of the rule of procedure was decisive for the outcome, or that the applicant would have won the case if the rule had been applied. As the Wena committee stated, what the applicant must simply demonstrate is "the impact that the issue may have had on the Award."352
CATEGORY | AMOUNT |
ICSID fees and advance payments | US$525,000 |
Legal fees directly incurred by the Kingdom of Spain | US$1,100,000 |
Legal fees Curtis, Mallet-Prevost, Colt & Mosle LLP | US$2,200,000 |
Expenses directly incurred by the Kingdom of Spain | €275,467 |
Expenses Curtis, Mallet-Prevost, Colt & Mosle LLP | US$62,315.38 |
CATEGORY | AMOUNT |
Legal fees | €2,392,729.45 |
Disbursements | €195,036.35 |
In the case of arbitration proceedings the Tribunal shall, except as the parties otherwise agree, assess the expenses incurred by the parties in connection with the proceedings, and shall decide how and by whom those expenses, the fees and expenses of the members of the Tribunal and the charges for the use of the facilities of the Centre shall be paid. Such decision shall form part of the award.
[I]n the event that an application for annulment of an award is registered, the above provisions of this Rule shall apply mutatis mutandis, except that the applicant shall be solely responsible for making the advance payments requested by the Secretary-General to cover expenses following the constitution of the Committee, and without prejudice to the right of the Committee in accordance with Article 52(4) of the Convention to decide how and by whom expenses incurred in connection with the annulment proceeding shall be paid.
Absent additional guidance in the Convention, the Arbitration Rules, and the Administrative and Financial Regulations, the Committee has the discretion either to apply the "costs follow the event" principle (i.e., the "loser pays" principle)361 or to apportion fees and expenses of the parties, fees and expenses of the members of the Committee and charges for the use of the facilities of the Centre differently between the parties.362 In light of the circumstances of this case, the Committee will apply the "costs follow the event" principle. As explained below, these "circumstances" are: (1) that the Parties agreed to the "loser pays" approach; (2) that other committees have adopted this approach, as pointed out by the Eiser Parties; and (3) the Award was annulled in its entirety for improper constitution of the Tribunal and serious departure from a fundamental rule of procedure.
Committee's fees and expenses | US$329,753.68 |
ICSID's administrative fees | US$126,000.00 |
Direct expenses | US$110,774.50 |
Total | US$566,528.18 |
a) the Award of May 4, 2017 rendered in Eiser Infrastructure Limited and Energía Solar Luxembourg S.à r.l. v. Kingdom of Spain (ICSID Case No. ARB/13/36) is annulled in its entirety; and
b) the Eiser Parties shall bear the full costs of the proceedings, which amount to US$566,528.18, and shall pay the totality of the Applicant's legal fees and expenses, which amount to US$3,362,315.38 and €275,467.
Already registered ?