Achmea Judgement | Judgment rendered by the Court of Justice of the European Union in Slovak Republic v. Achmea BV (Case No. C-284/16) dated 6 March 2018 |
Arbitration Rules | ICSID Rules of Procedure for Arbitration Proceedings 2006 |
C-[#] | Claimants’ Exhibit |
Cl. Mem. | Claimants’ Memorial on the Merits dated 28 July 2016 |
Cl. PHB | Claimants’ Post-Hearing Brief dated 19 September 2019 |
Cl. Rej. | Claimants’ Rejoinder on Jurisdiction dated 23 July 2017 |
Cl. Reply | Claimants’ Reply on the Merits and Counter-Memorial on Jurisdiction dated 26 April 2017 |
CL-[#] | Claimants’ Legal Authority |
CPI | Consumer Price Index |
DSG Claimants | The first 73 Claimants listed at paragraph 2 of this Decision |
DSG claims | The claims of the DSG Claimants |
DSG GmbH | DSG Deutsche Solargesellschaft GmbH |
ECT | Energy Charter Treaty, 17 December 1994 |
EU | European Union |
EU Brief | Amicus curiae brief filed by the European Commission, 27 June 2016 |
First Proposal | Respondent’s Proposal to Disqualify Mr. Gary Born dated 13 February 2018 |
Hearing | Hearing on jurisdiction and merits held on 3 June to 7 June 2019 |
ICSID Convention | Convention on the Settlement of Investment Disputes Between States and Nationals of Other States dated 18 March 1965 |
ICSID or the Centre | International Centre for Settlement of Investment Disputes |
Kruck Beteiligungs GmbH | Later became DSG Spanien Verwaltungs GmbH |
Margarit Complementary Report | Jaume Margarit, Complementary Report on Specific Aspects of the Regulatory Framework for the Promotion of Renewable Energy in Spain, 18 April 2017 |
Margarit Report | Jaume Margarit, Report on the Regulatory Framework to Promote Renewal Energy before RDL 9/2013 and its Determining Factors, 7 July 2016 |
NDP | Non-Disputing Party |
NRR | New regulatory regime |
PV | Photovoltaic energy |
R-[#] | Respondent's Exhibit |
RD | Royal Decree |
RDL | Royal Decree-Law |
REIO | Regional Economic Integration Organization |
Resp. C-Mem. | Respondent's Counter-Memorial on the Merits and Memorial on Jurisdiction dated 31 October 2016 |
Resp. PHB | Respondent's Post-Hearing Brief dated 19 September 2019 |
Resp. Rej. | Respondent's Rejoinder on the Merits and Reply on Jurisdiction dated 27 June 2017 |
RL-[#] | Respondent's Legal Authority |
Second Proposal | Respondent's Request for Disqualification of Presiding Arbitrator Professor Vaughan Lowe submitted on 16 April 2019 |
SPV | Special Purpose Vehicle |
TFEU | Treaty on the Functioning of the European Union published in the Official Journal of the European Union on 26 October 2012 |
Tr. Day [#] [Speaker(s)] [page:line] | Transcript of the Hearing |
Tribunal | Arbitral tribunal constituted on 19 January 2016 |
TS Claimants | The last 43 Claimants listed at paragraph 2 of this Decision |
TS claims | The claims of the TS Claimants |
TVPEE | Tax on the Production Value of Electric Power (created by Law 15/2012 of 27 December 2012, on fiscal measures for energy sustainability) |
VCLT | Vienna Convention on the Law of Treaties, 23 May 1969 |
This case concerns a dispute submitted to the International Centre for Settlement of Investment Disputes ("ICSID" or the "Centre") on the basis of the Energy Charter Treaty, which entered into force on 16 April 1998 (the "ECT") and the Convention on the Settlement of Investment Disputes between States and Nationals of Other States, which entered into force on 14 October 1966 (the "ICSID Convention").
1. Solar Andaluz 1 GmbH & Co. KG
2. Solar Andaluz 2 GmbH & Co. KG
3.Solar Andaluz 3 GmbH & Co. KG
4.Solar Andaluz 4 GmbH & Co. KG
5.Solar Andaluz 5 GmbH & Co. KG
6.Solar Andaluz 6 GmbH & Co. KG
7.Solar Andaluz 7 GmbH & Co. KG
8.Solar Andaluz 8 GmbH & Co. KG
9.Solar Andaluz 9 GmbH & Co. KG
10.Solar Andaluz 10 GmbH & Co. KG
11.Solar Andaluz 11 GmbH & Co. KG
12.Solar Andaluz 12 GmbH & Co. KG
13.Solar Andaluz 13 GmbH & Co. KG
14.Solar Andaluz 14 GmbH & Co. KG
15.Solar Andaluz 15 GmbH & Co. KG
16.Solar Andaluz 16 GmbH & Co. KG
17.Solar Andaluz 17 GmbH & Co. KG
18.Solar Andaluz 18 GmbH & Co. KG
19.Solar Andaluz 19 GmbH & Co. KG
20.Solar Andaluz 20 GmbH & Co. KG
21.Solarpark Calasparra 251 GmbH & Co. KG
22.Solarpark Calasparra 252 GmbH & Co. KG
23.Solarpark Calasparra 253 GmbH & Co. KG
24.Solarpark Calasparra 254 GmbH & Co. KG
25.Solarpark Calasparra 255 GmbH & Co. KG
26.Solarpark Calasparra 256 GmbH & Co. KG
27.Solarpark Calasparra 257 GmbH & Co. KG
28.Solarpark Calasparra 258 GmbH & Co. KG
29.Solarpark Calasparra 259 GmbH & Co. KG
30.Solarpark Calasparra 260 GmbH & Co. KG
31. Solarpark Calasparra 261 GmbH & Co. KG
32. Solarpark Calasparra 262 GmbH & Co. KG
33. Solarpark Calasparra 263 GmbH & Co. KG
34. Solarpark Calasparra 264 GmbH & Co. KG
35. Solarpark Calasparra 265 GmbH & Co. KG
36. Solarpark Tordesillas 401 GmbH & Co. KG
37. Solarpark Tordesillas 402 GmbH & Co. KG
38. Solarpark Tordesillas 403 GmbH & Co. KG
39. Solarpark Tordesillas 404 GmbH & Co. KG
40. Solarpark Tordesillas 405 GmbH & Co. KG
41. Solarpark Tordesillas 406 GmbH & Co. KG
42. Solarpark Tordesillas 407 GmbH & Co. KG
43. Solarpark Tordesillas 408 GmbH & Co. KG
44. Solarpark Tordesillas 409 GmbH & Co. KG
45. Solarpark Tordesillas 410 GmbH & Co. KG
46. Solarpark Tordesillas 411 GmbH & Co. KG
47. Solarpark Tordesillas 412 GmbH & Co. KG
48. Solarpark Tordesillas 413 GmbH & Co. KG
49. Solarpark Tordesillas 414 GmbH & Co. KG
50. Solarpark Tordesillas 415 GmbH & Co. KG
51. Solarpark Tordesillas 416 GmbH & Co. KG
52. Solarpark Tordesillas 417 GmbH & Co. KG
53. Solarpark Tordesillas 418 GmbH & Co. KG
54. Solarpark Tordesillas 419 GmbH & Co. KG
55. Solarpark Tordesillas 420 GmbH & Co. KG
56. Solarpark Tordesillas 421 GmbH & Co. KG
57. Solarpark Tordesillas 422 GmbH & Co. KG
58. Solarpark Tordesillas 423 GmbH & Co. KG
59.Solarpark Tordesillas 424 GmbH & Co. KG
60.Solarpark Tordesillas 425 GmbH & Co. KG
61.Solarpark Tordesillas 426 GmbH & Co. KG
62.Solarpark Tordesillas 427 GmbH & Co. KG
63.Solarpark Tordesillas 428 GmbH & Co. KG
64.Solarpark Tordesillas 429 GmbH & Co. KG
65.Solarpark Tordesillas 430 GmbH & Co. KG
66.DSG Deutsche Solargesellschaft mbH
67.DSG Spanien Verwaltungs GmbH1
68.Mr. Mathias Kruck
69.Mr. Joachim Kruck
70.Mr. Peter Flachsmann
71.Mr. Ralf Hofmann
72.Mr. Rolf Schumm
73.Mr. Frank Schumm
74.TS Abuzaderas 1 GmbH
75.TS Abuzaderas 2 GmbH
76.TS Abuzaderas 3 GmbH
77.TS Abuzaderas 4 GmbH
78.TS Abuzaderas 5 GmbH
79.TS Abuzaderas 6 GmbH
80.TS Abuzaderas 7 GmbH
81.TS Abuzaderas 8 GmbH
82.TS Abuzaderas 9 GmbH
83.TS Abuzaderas 10 GmbH
84.TS Abuzaderas 11 GmbH
85.TS Abuzaderas 12 GmbH
86.TS Abuzaderas 13 GmbH
87.TS Abuzaderas 14 GmbH
88.TS Abuzaderas 15 GmbH
89.TS Abuzaderas 16 GmbH
90.TS Abuzaderas 17 GmbH
91.TS Abuzaderas 18 GmbH
92.TS Abuzaderas 19 GmbH
93.TS Abuzaderas 20 GmbH
94.TS Abuzaderas 21 GmbH
95.TS Abuzaderas 22 GmbH
96.TS Abuzaderas 23 GmbH
97.TS Abuzaderas 24 GmbH
98.TS Abuzaderas 25 GmbH
99.TS Abuzaderas 26 GmbH
100.TS Abuzaderas 27 GmbH
101.TS Abuzaderas 28 GmbH
102.TS Abuzaderas 29 GmbH
103.TS Abuzaderas 30 GmbH
104.TS Avila eins GmbH
105.TRC Energy GmbH
106.TS Cuenca zwei GmbH
107.WBG GmbH
108.Sunburn Verwaltungs GmbH
109.TS Villalba GmbH
110.Tauber-Solar Sierra GmbH
111.ZKS GmbH
112.TS Cuenca 20 GmbH
113.TS Valtou GmbH
114.TS Cuenca 40 GmbH
115.Mr. Karsten Reiss
116.Mr. Jurgen Reiss2
• a declaration that the Tribunal has jurisdiction under the ECT and the ICSID Convention;
• a declaration that Spain has violated Part III of the ECT and international law with respect to Claimants' investments;
• compensation to Claimants for all damages they have suffered as set forth in this Memorial and as will be further developed and quantified in the course of this proceeding;
• all costs of this proceeding, including (but not limited to) Claimants' attorneys' fees and expenses, the fees and expenses of Claimants' experts, and the fees and expenses of the Tribunal and ICSID;
• pre- and post-award compound interest at the highest lawful rate from the Date of Assessment until Spain's full and final satisfaction of the Award; and
• any other relief the Tribunal deems just and proper.4
• a declaration that the Tribunal had jurisdiction under the ECT and the ICSID Convention;
• a declaration that Spain has violated Part III of the ECT and international law with respect to Claimants’ investments;
• compensation to Claimants for all damages they have suffered as set forth in this Reply and Claimants’ Memorial on the Merits and as will be further developed and quantified in the course of this proceeding;
• all costs of this proceeding, including (but not limited to) Claimants’ attorneys’ fees and expenses, the fees and expenses of Claimants’ experts, and the fees and expenses of the Tribunal and ICSID;
• pre- and post-award compound interest at the highest lawful rate from the Date of Assessment until Spain’s full and final satisfaction of the Award; and
• any other relief the Tribunal deems just and proper.5
• a declaration that the Tribunal has jurisdiction under the ECT and the ICSID Convention for all of Claimants’ claims, thereby rejecting Respondent’s jurisdictional objections in full;
• a declaration that Spain has violated Part III of the ECT and international law with respect to Claimants’ investments;
• compensation to Claimants for all damages they have suffered as set forth in their Memorial on the Merits and in their Reply Memorial on the Merits and as may be further developed and quantified during the course of this proceeding;
• all costs of this proceeding, including (but not limited to) Claimants’ attorneys’ fees and expenses, the fees and expenses of Claimants’ experts, and the fees and expenses of the Tribunal and ICSID;
• pre- and post-award compound interest at the highest lawful rate from the Date of Assessment until Spain’s full and final satisfaction of the Award; and
• any other relief the Tribunal deems just and proper.6
• a declaration that the Tribunal had jurisdiction under the ECT and the ICSID Convention;
• a declaration that Spain has violated Part III of the ECT and international law with respect to Claimants' investments;
• compensation to Claimants for all damages they have suffered as set forth in their submissions;
• all costs of this proceeding, including (but not limited to) Claimants' attorneys' fees and expenses, the fees and expenses of Claimants' experts, and the fees and expenses of the Tribunal and ICSID;
• pre- and post-award compound interest at the highest lawful rate from the Date of Assessment until Spain's full and final satisfaction of the Award; and
• any other relief the Tribunal deems just and proper.7
a) To declare its lack of jurisdiction over the claims of the Claimant Party or, if applicable, the inadmissibility of said claims.
b) Subsidiarily, in the event that the Arbitral Tribunal decides that it has jurisdiction to hear this dispute, to dismiss all the claims of the Claimant Party regarding the Merits, as the Kingdom of Spain has not breached the ECT in any way, pursuant to section IV herein, with regard to the Merits.
c) Subsidiarily, to dismiss all the Claimant Party's claims for damages as the Claimant has no right to compensation, in accordance with section V herein; and
d) Order the Claimant Party to pay all costs and expenses derived from this arbitration, including ICSID administrative expenses, arbitrators' fees and the fees of the legal representatives of the Kingdom of Spain, their experts and advisors, as well as any other cost or expense that has been incurred, all of this including a reasonable rate of interest from the date on which these costs are incurred until the date of their actual payment.8
a) Declare its lacks [sic] of jurisdiction to settle the claims of the Claimants, or if the case may be, their inadmissibility, in accordance with what is set forth in section III of this Document, referred to Jurisdictional Objections;
b) Alternatively, in the event that the Arbitral Tribunal decides that it has jurisdiction to hear this dispute, to dismiss all the Claimants' claims regarding the Merits of the case, as the Kingdom of Spain has not breached the ECT in any way, pursuant to sections IV and V herein, referred to the Facts and the Merits, respectively;
c) Alternatively, to dismiss all the Claimants' claims for damages as they are not entitled to compensation, in accordance with section V of this Document; and
d) Sentence the Claimants to pay all costs and expenses derived from this arbitration, including ICSID administrative expenses, arbitrators ‘fees, and the fees of the legal representatives of the Kingdom of Spain, their experts and advisors, as well as any other cost or expense that has been incurred, all of this including a reasonable rate of interest from the date on which these costs are incurred and up to the date of their actual payment.9
a) It declares its lack of jurisdiction to hear the claims of the Claimants, or where appropriate, their the [sic] inadmissibility, in accordance with what is stated in section II of this Respondent's Post-Hearing Brief in reference to Jurisdictional Objections;
b) Secondarily in the event that the Arbitration Tribunal were to decide that it has jurisdiction to hear the present dispute, that it rejects all the claims of the Claimants on the merits, since the Kingdom of Spain has not in any way breached the ECT, in accordance with what is set forth in sections III and IV of the present Brief, regarding the Facts and the Merits of the case.
c) Secondarily, that it dismisses all of the Claimants’ compensatory claims, as the Claimants have no right to compensation, pursuant to that stated in section V herein; and
d) To Order the Claimants' to pay all costs and expenses derived from this arbitration, including ICSID administrative expenses, arbitrators’ fees, and the fees of the legal representatives of the Kingdom of Spain, their experts and advisors, as well as any other cost or expense that has been incurred, all of this including a reasonable rate of interest from the date on which these costs are incurred and the date of their actual payment.10
1. The DSG Deutsche Solargesellschaft Group (the "DSG Group") and the Tauber Solar Investors Group (the "TS Investors Group") as defined herein (collectively, "Claimants") hereby request the initiation of an arbitration proceeding against the Kingdom of Spain ("Spain") under the Convention and Rules of the International Centre for Settlement of Investment Disputes ("ICSID"). Claimants file this Request for Arbitration pursuant to Article 25 of the ICSID Convention, ICSID Institution Rules 1 and 2, and Article 26(4)(c) of the Energy Charter Treaty ("ECT" or "Treaty"). [Emphasis in the original]
On 19 January 2016, the Secretary-General notified the Parties that all three arbitrators had accepted their appointments and that the Tribunal was therefore deemed to have been constituted on that date in accordance with Rule 6(1) of the ICSID Rules of Procedure for Arbitration Proceedings (the "Arbitration Rules"). Ms. Mairée Uran Bidegain, ICSID, was designated to serve as Secretary of the Tribunal.
On 19 February 2016, the Respondent made an application under ICSID Arbitration Rule 41(5), alleging that the claim was "manifestly without legal merit" (the "Respondent’s Rule 41(5) Objection"). On 2 March 2016, the Claimants filed observations on the Respondent’s Rule 41(5) Objection.
On 15 March 2016, the Tribunal held a first session with the Parties by teleconference in accordance with ICSID Arbitration Rule 13(1).
On 18 April 2016, the European Commission filed an Application for leave to intervene as a non-disputing party pursuant to ICSID Arbitration Rule 37(2) (the "European Commission’s Application").
■ Witness Statements of:
- Joachim Kruck, dated 21 July 2016
- Peter Flachsmann, dated 11 July 2016
- Klaus Matuschke, dated 28 July 2016
- Markus Karl, dated 19 July 2016
- Klaus-Bruno Flech, dated 18 July 2016
- Karsten Reiss, dated 19 July 2016
■ Expert Reports by:
- Brattle Group Quantum Report, dated 27 July 2016, with exhibits BQR-001 to BQR-174
- Brattle Group Regulatory Report, dated 27 July 2016, with exhibits BRR-001 to BRR-131
- Manuel Aragon Reyes, dated 7 July 2016
- Jaume Margarit, dated 7 July 2016
■ Exhibits C-001 to C-342
■ Legal Authorities CL-001 to CL-134.
■ Witness Statement of:
- Carlos Montoya, dated 27 October 2016, with exhibits17
■ Expert Reports by:
- Pablo Pérez Tremps and Marcos Vaquer Caballería, dated 25 July 2016
- Grant Geatrex, David Pérez López, Jesús Fernández Salguero and Carlos Montojo González, dated 31 October 2016, with exhibits DOC-001 to DOC-046
■ Exhibits R-016 to R-243
■ Legal Authorities RL-030 to RL-096.
■ Second Witness Statements of:
- Joachim Kruck, dated 25 April 2017
- Markus Karl, dated 25 April 2017
- Karsten Reiss, dated 20 April 2017
■ Rebuttal Expert Reports by:
- Brattle Group Rebuttal Quantum Report, dated 26 April 2017, with exhibits BQR-175 to BQR-188
- Brattle Group Rebuttal Regulatory Report, dated 26 April 2017, with exhibits BRR-132 to BRR-209
- Manuel Aragón Reyes, dated 5 April 2017
- Jaume Margarit, dated 18 April 2017
■ Exhibits C-343 to C-490
■ Legal Authorities CL-135 to CL-179.
■ Second Witness Statement of:
- Carlos Montoya, dated 27 June 2017, with exhibits18
■ Rebuttal Expert Reports by:
- Pablo Pérez Tremps and Marcos Vaquer Caballería, dated 21 June 2017
- Grant Greatrex, David Pérez López, Jesús Fernández Salguero and Carlos Montojo González, dated 27 June 2017, with exhibits DOC-048 to DOC-093
■ Exhibits R-244 to R-361
■ Legal Authorities RL-097 to RL-112.
On 13 February 2018, the Respondent proposed the disqualification of Mr. Gary Born, in accordance with Article 57 of the ICSID Convention and ICSID Arbitration Rule 9 (the "First Proposal"). On that date, the Centre informed the Parties that the proceeding had been suspended until the Proposal was decided, pursuant to ICSID Arbitration Rule 9(6).
The Parties were also informed that the Proposal would be decided by Professors Lowe and Douglas (the "Two Members"), in accordance with Article 58 of the ICSID Convention and ICSID Arbitration Rule 9(4).
On 27 February 2018, Mr. Gary Born furnished his explanations regarding the First Proposal in accordance with ICSID Arbitration Rule 9(3).
On 26 March 2018, the Tribunal invited the Parties to produce the judgment rendered by the Court of Justice of the European Union on 6 March 2018, in Case No. C-284/16, Slovak Republic v. Achmea B.V (the "Achmea Judgement"). The Parties were also invited to make written submissions on the implications for the present case of the Achmea Judgment by 27 April 2018.
On 22 June 2018, Mr. Gary Born submitted his resignation to the Secretary General of ICSID, and to Professors Lowe and Douglas, in accordance with ICSID Arbitration Rule 8(2).
On that same date, the Parties were notified of Mr. Born’s resignation and of the suspension of the proceeding. The Claimants were further invited to appoint an arbitrator in accordance with ICSID Arbitration Rule 11(1).
On 8 August 2018, Dr. Michael Pryles accepted his appointment as co-arbitrator in this case, and the Tribunal was reconstituted. Its members are Prof. Vaughan Lowe, QC, a national of the United Kingdom, President, appointed by agreement of the Parties; Dr. Michael Pryles AO, PBM, a national of Australia, appointed by the Claimant; and Prof. Zachary Douglas, QC, a national of Australia, appointed by the Respondent. The proceeding was resumed in accordance with ICSID Arbitration Rule 12.
The Parties have agreed that they will exchange further requests to add documents to the record in May 2019, prior to the hearing. Further, the Parties have agreed that they waive any objection to the timeliness of such requests under Procedural Order No. 1 on the basis that the opposing Party could have requested to add a document prior to May 2019, in the months after the Tribunal was reconstituted. This waiver of objections to timeliness will apply only to new legal authorities and exhibits regarding Spain's regulatory regime that have been made public after the Parties' original 12 February 2018 requests.
On 16 April 2019, the Respondent proposed the disqualification of Prof. Vaughan Lowe pursuant to Article 57 of the ICSID Convention and ICSID Arbitration Rule 9 (the "Second Proposal"). By letter of the same date, the Secretariat confirmed receipt of the Second Proposal and informed the Parties that (i) the Second Proposal would be decided by the other members of the Tribunal (the "Unchallenged Arbitrators") and (ii) the proceeding would be suspended until a decision had been taken on the Second Proposal.
On 28 April 2019, Prof. Lowe furnished his explanations on regarding the Second Proposal in accordance with ICSID Arbitration Rule 9(3).
Tribunal:
Prof. Vaughan Lowe QC President
Dr. Michael Pryles AO, PBM Arbitrator
Prof. Zachary Douglas QC Arbitrator
ICSID Secretariat:
Mr. Paul-Jean Le Cannu Secretary of the Tribunal
For the Claimants:
Counsel:
Mr. Reginald Smith King & Spalding
Mr. Kevin Mohr King & Spalding
Ms. Amy Frey King & Spalding
Mr. Jan Schafer King & Spalding
Mr. Christopher Smith King & Spalding
Ms. Violeta Valicenti King & Spalding
Mr. Karam Farah King & Spalding
Mr. Cristian Boruzi King & Spalding
Ms. Inés Vazquez García Gómez-Acebo & Pombo
Ms. Inés Puig-Samper Gómez-Acebo & Pombo
Ms. Cristina Matia Garay Gómez-Acebo & Pombo
Parties:
Mr. Andreas Nagel DSG
Ms. Mafalda Soto DSG / Brenes Abogados
Mr. Joachim Kruck (after examination) DSG
Mr. Peter Flachmann (after examination) DSG / KACO
Mr. Klaus Matuschke (after examination) DSG
Mr. Markus Schreck Tauber Solar
Mr. Antonio Jiménez Abraham Monereo Meyer Marinel-lo Abogados; Tauber Solar
Mr. Klaus-Bruno Fleck (after examination) Tauber Solar
For the Respondent:
Counsel:
Ms. María José Ruiz Sánchez Abogacía General del Estado
Mr. Pablo Elena Abad Abogacía General del Estado
Mr. Roberto Fernández Castilla Abogacía General del Estado
Ms. Almudena Pérez-Zurita Gutiérrez Abogacía General del Estado
Mr. Alberto Torró Molés Abogacía General del Estado
Court Reporter(s) :
Mr. Dante Rinaldi D-R Esteno, Spanish Court Reporter
Ms. María Eliana Da Silva D-R Esteno, Spanish Court Reporter
Ms. Luciana Sosa D-R Esteno, Spanish Court Reporter
Mr. Trevor McGowan The Court Reporter Ltd
Interpreters:
Mr. Jesús Getan Bornn English-Spanish
Ms. Amalia Thaler de Klemm English-Spanish
Mr. Marc Viscovi English-Spanish
Mr. Ralph Gerhardt English-German
Ms. Silke Schoenbuchner English-German
Ms. Barbara Weller English-German
On behalf of the Claimant(s):
Witness(es):
Mr. Joachim Kruck DSG
Mr. Peter Flachmann DSG / KACO
Mr. Klaus Matuschke DSG
Mr. Klaus-Bruno Fleck Tauber Solar
Mr. Markus Karl Tauber Solar
Mr. Karsten Reiss hagebau; Tauber Solar
Expert(s):
Mr. Jaume Margarit Independent Consultant, formerly Director of Renewable Energy at the IDAE
Dr. Manuel Aragón Reyes Autonomous University of Madrid (Professor of Constitutional Law) Mr. Carlos Lapuerta Brattle
Mr. Jose Antonio Garcia Brattle
Mr. Richard Caldwell Brattle
Mr. Alejandro Zerain Brattle
Ms. Aurora Velente Brattle
On behalf of the Respondent(s) :
Expert(s):
Dr. Marcos Vaquer Caballería Universidad Carlos III Madrid
Mr. Grant Greatrex Altran MaC Group
Mr. David Pérez López Altran MaC Group
Mr. Jesús Fernández Salguero Altran MaC Group
Mr. Carlos Montojo González Altran MaC Group
Mr. Antonio Sanchis Boscá Altran MaC Group
On 4 December 2019, pursuant to Section 16.3 of Procedural Order No. 1, the Respondent sought leave to file the Stadtwerke Award20 and the BayWa Decision (the "4 December Section 16.3 Request").21 Further to the Tribunal’s invitation, the Claimants submitted comments on the 4 December Section 16.3 Request on 18 December 2019, along with their own request for leave to file additional legal authorities22 and a factual exhibit. The Respondent filed a response to the Claimants’ 18 December 2019 comments, including a request to file an additional legal authority,23 on 9 January 2020.
Stadtwerke München GmbH, RWE Innogy GmbH, and others v. Kingdom of Spain (ICSID Case No. ARB/15/1), Dissenting Opinion Prof. Kaj Hobér, 2 December 2019 (RL-147); BayWa r.e. renewable energy GmbH and BayWa r.e. Asset Holding GmbH v. Kingdom of Spain (ICSID Case No. ARB/15/16), Dissenting Opinion Dr. Horacio Grigera Naón, 2 December 2019 (RL-145); OperaFund Eco-Invest SICAV PLC and Schwab Holding AG v. Kingdom of Spain (ICSID Case No. ARB/15/36), Award and Dissent on Liability and Quantum, 6 September 2019 (CL-221); Cube Infrastructure Fund SICAV and others v. Kingdom of Spain (ICSID Case No. ARB/15/20), Award, 15 July 2019 (CL-222).
The Tribunal notes that the Parties agree that the BayWa Decision and the Stadtwerke, OperaFund and Cube Awards should be admitted into the record by the Tribunal. By contrast, there is no agreement between the Parties as to the admission of the Claimants' proposed new factual exhibits, Royal Decree-Law (RDL) 17/2019 and statements by the Minister of Ecological Transition to the Spanish Parliament regarding RDL 17/2019.
The Tribunal has decided to allow the Parties to enter into the record the above-referred Decisions and Awards, including dissents, to the extent that they are publicly and freely available via the Internet and that either Party considers that the Tribunal should review them. As contemplated in Section 13 of PO1, the Tribunal does not require hard copies: it will be sufficient to send a list of such Decisions and Awards together with an indication of their legal authority number and where on the Internet they are to be found. The Tribunal does not wish to receive comments on these additional legal authorities.
The Tribunal further considers that no exceptional circumstances have been shown that would justify the admission of additional factual exhibits at this late stage. The Claimants' request for admission of further factual exhibits is therefore dismissed.
The Tribunal recalls the Secretariat’s communication of 7 February 2020, which said that the Tribunal ‘will admit into the record any additional published decision or award issued in treaty arbitrations to which Spain is a party, on the conditions set forth in the Secretariat’s email of 24 January 2020. ’ Those conditions are that the Parties are allowed ‘to enter into the record the above-referred Decisions and Awards, including dissents, to the extent that they are publicly and freely available via the Internet and that either Party considers that the Tribunal should review them. As contemplated in Section 13 of PO1, the Tribunal does not require hard copies: it will be sufficient to send a list of such Decisions and Awards together with an indication of their legal authority number and where on the Internet they are to be found.’
The Tribunal confirms that it does not wish to receive comments from either Party on this additional legal authority immediately, and that it will invite a final comment, of limited length, from each Party on this and any other award or decision that has been published since the hearing. Those comments will be invited in the coming weeks, after which the Tribunal will formally close the proceedings.
On 26 October 2020, the Respondent submitted legal authorities RL-152 and 153 (the Decision on Jurisdiction, Liability and Directions on Quantum and the Dissenting Opinion of Mr. David R. Haigh Q.C., both issued on 31 August 2020 in Cavalum SGPS SA v. Kingdom of Spain (ICSID Case No. ARB/15/34)) and the Respondent’s consolidated list of legal authorities. The following day, the Claimants submitted Legal Authority CL-224 (the Decision on Jurisdiction, Liability and Directions on Quantum and the Dissenting Opinion of Prof. Pierre-Marie Dupuy, both issued on 8 October 2020 in STEAG GmbH v. Kingdom of Spain (ICSID Case No. ARB/15/4)) and the Claimants’ Consolidated List of Legal Authorities.
The Tribunal has decided that it would now be helpful to receive these submissions, in the form of a link to an on-line version of the Decision or Award in question and a brief comment (limited to 500 words for each Decision or Award) of its relevance to the case pleaded by the Party adducing the Decision or Award. The Parties should submit their comments simultaneously to the Tribunal secretary, by close of business (Washington DC) on Friday 04 December 2020. [Emphasis in the original]
On 22 March 2021, the Respondent submitted as legal authority RL-154 the Final Award rendered 8 March 2021 in Freif Eurowind Holdings Ltd. (United Kingdom) v. Kingdom of Spain, SCC Case V 2017/060, along with a consolidated List of Legal Authorities (RL). On 25 March 2021, the Respondent submitted an additional legal authority, the Decision on Jurisdiction and Liability issued on 17 March 2021 in Eurus Energy Holdings Corporation v. Kingdom of Spain (ICSID Case No. ARB/16/4) (legal authority RL-0155), and a consolidated List of Legal Authorities (RL). On 26 March 2021, the Tribunal through its Secretary acknowledged receipt of legal authorities RL-0154 and RL-0155, and indicated that it did not wish to receive any comment on them from either Party. The Tribunal also invited the Parties to confirm the accuracy of the lists of Party representatives and June 2019 hearing participants as provided to the Parties. On 29 March 2021, the Claimants confirmed the accuracy of the list of hearing participants with respect to the Claimants’ counsel, party representatives, fact witnesses, and experts, and requested certain modifications to the list of Claimants’ representatives. They also requested that the Respondent be required to submit the Partial Dissent of Arbitrator Oscar Garibaldi in the Eurus v. Spain case, which in their view the Respondent ought to have included with the Decision on Jurisdiction and Liability. By email of 4 April 2021 from the Secretariat, the Respondent was requested on behalf of the Tribunal to submit a copy of Mr. Garibaldi’s Partial Dissent in the interest of having a complete file. The Respondent submitted the Partial Dissent as legal authority RL-156 on 5 April 2021.
To work out the premiums, the voltage level on delivery of the power to the network, the effective contribution to environmental improvement, to primary energy saving and energy efficiency, the generation of economically justifiable useful heat and the investment costs incurred shall all be taken into account so as to achieve reasonable profitability.38
3. The tariffs, premiums, incentives and supplements resulting from any of the revisions provided for in this section shall apply solely to the plants that commence operating subsequent to the date of the entry into force referred to in the paragraph above and shall not have a backdated effect on any previous tariffs and premiums.
The economic framework established in the present Royal Decree develops the principles provided in Law 54/1997, of 27 November, on the Electricity Sector, guaranteeing the owners of facilities under the special regime a reasonable return on their investments, and the consumers of electricity an assignment of the costs attributable to the electricity system which is also reasonable, although incentives are provided to playing a part in this market since it is considered that in this manner lower government intervention will be achieved in the setting of prices, together with better, more efficient, attribution of the costs of the system, particularly in respect of the handling of diversions and the provisions of supplementary services.
To this effect, a system which is analogous to that provided in Royal Decree 436/2004, of 12 March, is maintained, in which the owner of the facility may opt to sell their energy at a regulated tariff, which will be the same for all scheduling periods, or alternatively to sell this energy directly on the daily market, the term market, or through a bilateral contract, in this case receiving the price negotiated in the market plus a premium. In this latter case, an innovation is introduced for certain technologies, namely upper and lower limits for the sum of the hourly price in the daily market, plus a reference premium, such that the premium to be received for each hour may be limited in accordance with these values. This new system protects the promoter when the revenues deriving from the market price falls excessively low, and eliminates the premium when the market price is sufficiently high to guarantee that their costs will be covered, thus eliminating irrationalities in the payment for the technologies the costs of which are not directly related to the prices of petroleum in the international markets.
During the year 2010, on sight of the results of the monitoring reports on the degree of fulfilment of the Renewable Energies Plan (PER) 2005-2010, and of the Energy Efficiency and Savings Strategy in Spain (E4), together with such new targets as may be included in the subsequent Renewable Energies Plan 2011-2020, there shall be a review of the tariffs, premiums, supplements and lower and upper limits defined in this Royal Decree with regard to the costs associated with each of these technologies, the degree of participation of the special regime in covering the demand and its impact upon the technical and economic management of the system, and a reasonable rate of profitability shall always be guaranteed with reference to the cost of money in the capital markets. Subsequently a further review shall be performed every four years, maintaining the same criteria as previously.
The revisions to the regulated tariff and the upper and lower limits indicated in this paragraph shall not affect facilities for which the deed of commissioning shall have been granted prior to 1 January of the second year following the year in which the revision shall have been performed.54
Every 4 years the tariffs will be revised, bearing in mind compliance with the targets set. This will allow an adjustment to the tariffs in line with the new costs and the degree of compliance with the targets. The tariff revisions carried out in the future will not affect those installations already operating. This guarantee affords legal safety to the producer, providing stability to the sector and promoting its development. The new regulations will not be of a retroactive nature. The installations operating before January 1, 2008 may continue to adopt the previous regulations under the fixed tariff option throughout their working life.
The new text, which replaces Royal Decree 436/2004, fits into the energy policy commitment to drive forward the use of clean, native and efficient energies in Spain. The Government commitment to these energy technologies was the reason why the new regulations sought stability over time, which allows businessmen to carry out medium and long-term scheduling as well as a sufficient, fair return that, combined with stability, makes the investment and dedication to this activity attractive.
...
The new regulations will not be of a retroactive nature. The installations that are operational by January 1, 2008 may continue to adopt the previous regulations under the fixed tariff option throughout their operating life. When they take part in the market, they may maintain their prior regulation until December 31, 2012. These installations may voluntarily opt to abide by this new Royal Decree as from its publication.
It will be in 2010 that the tariffs and premiums set out in the proposal will be revised in accordance with the targets set in the Renewable Energies Plan 2005-2010 and in the Energy Efficiency and Savings Strategy and in line with the new targets included in the following Renewable Energies Plan for the period 2011-2020.
The revisions carried out in the future of the tariffs will not affect those Installations already in operation. This guarantee provides legal safety for the producer, affording stability to the sector and fostering its development.57
The incentives under RD 661/2007 offered investors a fixed long-term tariff at rates equal or even higher - for relatively large facilities - than those offered under RD 436/2004. The full tariff would apply for twenty-five years, after which the facility would receive approximately 80% of the fixed tariff rate for the duration of the life of the facility. Further, the tariff would be adjusted annually under the consumer price index (CPI), which was also a clear indication that Spain would not arbitrarily modify the tariff in future years. Notably, the decree ensured that once a facility had been granted rights under the applicable tariff regime, any future revisions to the tariff rates would not impact those facilities. Thus, it was critically important for us to develop and finalize our facilities quickly so that they would receive the RD 661/2007 tariffs.58
The development of this sector in Spain has totally outperformed the forecasts in 2005. To be precise, the target set for 2010 to attain 371 MW of photovoltaic energy was achieved in August 2007 and it is estimated that installed power at year-end 2008 will be fivefold the power target for 2010. Hence, since said goal has been surpassed, it is necessary to determine a new long-term target and a new legal framework which allows the continuity of the success achieved by this sector in Spain at reasonable costs. With this in mind, a Royal Decree has been approved which will allow 3,000 MW to be attained in 2010 and around 10,000 MW in 2020.62
Just as insufficient compensation would make the investments nonviable, excessive compensation could have significant repercussions on the costs of the electric power system and create disincentives for investing in research and development, thereby reducing the excellent medium-term and long-term perspectives for this technology. Therefore, it is felt that it is necessary to rationalize compensation and, therefore, the royal decree that is approved should modify the economic regime downward, following the expected evolution of the technology, with a long-term perspective.63
Fifth additional provision. Modification of the compensation for generation by photovoltaic technology.
During the year 2012, based on the technological evolution of the sector and the market, and the functioning of the compensatory regime, compensation for the generation of electric power by photovoltaic solar technology may be modified.71
The objective of this Act is to harmonize our tax system with a more efficient use which greater respects [sic] the environment and sustainability, values which have inspired this reform of the tax system, and as such in line with the basic principles governing the tax, energy and, of course, environmental policies of the European Union.
In today's society, the increasingly greater effect of energy production and consumption on environmental sustainability requires a legislative and regulatory framework which guarantees for all the agents involved correct operation of the energy model which also contributes to preserving our rich environmental heritage.
The basic foundation of this Act lies in Article 45 of the Constitution, a precept in which the protection of our environment is established as one of [the] guiding principles of social and economic policies. One of the bases of this tax system reform will therefore be the internalization of the environmental costs arising from the production of electrical energy....
For this purpose and also with a view to favouring budgetary balance, Title I of this Act establishes a tax on the value of the production of electrical energy, of a direct and real nature, which is levied on the performance of activities of production and incorporation into the electricity system of electrical energy in the Spanish electricity system.82
The data reported by the National Energy Commission in its report 35/2012 of the 20th of December on the order proposal establishing the access tolls are established from the 1st of January 2013 and tariffs and premiums of special regime facilities, has revealed the appearance of new deviations in estimates of costs and revenues caused by various factors, both for the end of 2012 and 2013, that in the current economic context, would render almost unfeasible their coverage with electric tolls and the items prescribed from the State General Budget.
These deviations are due largely to a higher growth in the cost of the special regime, due to an increase in the operation hours exceeding the projected and an increase in the compensation values after indexing to the Brent price, and a reduction of toll revenues due to a very sharp drop in demand which is consolidated for this exercise.
The proposed alternative would be a further increase in access tolls paid by electricity consumers. This measure would affect directly household economies and corporal [sic] competitiveness, both in a delicate situation, given the current economic situation.
Given this scenario, in order to alleviate this problem the Government has decided to adopt certain cost-reduction urgent measures to avoid the assumption of a new effort by consumers; helping them, through consumption and investment, to collaborate as well for the economic recovery.
Consequently, with the purpose of using a more stable index which is not affected by the volatility of unprocessed foods no[r] those from domestic fuels, all those remuneration updating methodologies that are linked to CPI shall substitute it by the Consumption Price Index to constant taxes with no unprocessed food nor energy products.85
It shall be based on receiving the revenue derived from participation in the market, with an additional return that, if necessary, shall cover those investment costs that an efficient and well-managed company does not recover in the market. In this sense, according to community case law, a company shall be deemed as being efficient and well-managed if it has the necessary means for the development of its field, whose costs are those of an efficient enterprise in that field and considering the corresponding revenue and a reasonable profit for the execution of its functions. The aim is to ensure that the high costs of an inefficient company are not taken as reference.
…
This framework shall articulate a remuneration that shall allow renewable energy, cogeneration, and waste facilities to cover the costs necessary to compete in the market at an equal level with the rest of technologies and get a reasonable rate of return.
…
In this way, the Law carries out a balanced allocation of the costs attributable to the electricity system, electrical consumers and taxpayers, to the extent in which part of these costs are financed under the General State Budget.
Furthermore, Law 54/1997, of 27 November, stipulates the regulation on the concept of reasonable rate of return, setting it, in line with the legal principles on the particular case law developed within the last few years, within project profitability that will be focused, prior to taxes, on the average yield in the secondary market of State Obligations within ten years, by applying the appropriate differential.
In this way, the aim is to consolidate the continuous adaptation that the regulation has experienced, in order to keep this reasonable rate of return through a predictable system, subject to temporary realisation.90
For purposes of the provisions of the penultimate paragraph of Article 30.4 of Law 54/1997, of 27 November, for the facilities that as of date of the entry into force of this Royal Decree law have the right to a feed-in tariff scheme, the reasonable rate of return shall focus, before taxes, on the average yield in the secondary market for ten years prior to the entry into force of this Royal Decree-Law of the Obligations of the State within ten years91 increased by 300 basic points, without prejudice to the revision envisaged in the last paragraph of that article.92
Essentially, the continuous normative changes have entailed an important distortion to the normal operation of the electrical system and which needs to be corrected through action by the legislator which lends the regulatory stability that electrical activity requires. This regulatory safety, combined with the need to undertake the reforms needed to ensure the sustainability of system in the long-term and to resolve the existing shortcomings in system operation would recommend the approval of an overall reform of the sector, based on a new income and expenses regime for the electrical system which tries to return to the system the financial sustainability it lost a long time ago and whose eradication has not been achieved to date through the adoption of partial measures.
…
The present Law essentially sets out to establish the regulation for the Electrical Sector, ensuring electrical supply with the necessary quality levels and at the lowest possible cost, to ensure the economic and financial sustainability of the system and allow an effective competition level in the Electrical Sector, all within the environmental protection principles of a modern society.
…
The widespread awareness of the tariff deficit situation and the consequent threat to the very feasibility of the electrical system has led to the need to make major changes to the remuneration regime for regulated activities. In view of the progressive deterioration in the sustainability of the electrical system, the legal entities in the latter could no longer legitimately trust the maintenance of the parameters which had degenerated into the situation described and any diligent operator could anticipate the need for these changes.
For activities with regulated remuneration, the Law reinforces and clarifies the principles and criteria for establishing the remuneration regimes to which end the necessary costs will be considered to carry out activity by an efficient, well-managed company through the application of homogeneous criteria throughout Spain. These economic regimes will allow appropriate returns to be obtained with regard to the activity risk.
The technical and economic management of the system essentially maintains the other remuneration criteria, incorporating into the system operator’s remuneration incentives for the reduction of system costs deriving from the operation.
The high penetration of production technologies deriving from renewable energy sources, cogeneration and waste, included in the so-called special regime for electrical energy production, has meant that its unique regulation connected with power and its technology lacks any object. By contrast, it makes it necessary for regulation to consider these installations in a similar way to those of other technologies which will be integrated into the market and, in any case, for them to be considered because of their technology and impacts on the system, rather than because of their power which is why the differentiated concepts of ordinary and special regime are abandoned. This is why unified regulation is being carried out without prejudice to any unique considerations which need to be established.
The remuneration regime for renewable energies, cogeneration and waste will be based on the necessary participation in the market of these installations, complemented by market income with specific regulated remuneration which enables these technologies to compete on an equal footing with the other technologies on the market. This specific complementary remuneration will be sufficient to attain the minimum level required to cover any costs which, by contrast to conventional technologies, they cannot recover on the market and will allow them to obtain a suitable return with reference to the installation type applicable in each case.95
Although, considering the circumstances existing at each moment in time, these provisions permitted the achievement of the purposes for which they were introduced, it cannot be overlooked that the forecasts prevailing when they were adopted were soon surpassed as a result of the highly favourable support framework. This circumstance, together with the fact that the costs of technology were gradually falling, made it necessary to make a series of amendments to the regulatory framework in order to guarantee both the principle of reasonable return and the financial sustainability of the system itself.
...
The measures adopted between 2009 and 2011 proved insufficient for fulfilling their intended aims and the regulatory framework was found to be suffering from certain failings—which remained uncorrected despite the huge effort made to adapt the regulation—seriously compromising the system's financial sustainability. This situation led to the adoption of Royal Decree-Act 1/2012, of 27th January, which suspended the remuneration pre-allocation procedures and withdrew financial incentives for new facilities generating electrical energy through cogeneration or from renewable energy sources or waste, and Royal-Decree Law 2/2013, of 1st February, on urgent measures for the electricity system and the financial sector, which, among other measures, amended Royal Decree 661/2007, of 25th May, eliminating the "market price plus premium" option applicable to certain technologies and establishing tariff-based remuneration for all special regime facilities, while at the same time modifying the criteria for updating the remuneration of regulated activities in the electricity system.
In this context—it having become apparent that the financial sustainability of the electricity system had to be guaranteed, that the successive amendments to the regulation required consolidation (among other reasons, to ensure the stringent and correct application of the principle of reasonable return), and that the regulatory framework needed to be reviewed in order to adapt it to the actual circumstances of the industry— Royal Decree-Act 9/2013, of 12th July, on urgent measures to ensure the financial stability of the electricity system, was passed.98
Under this new framework, in addition to the remuneration earned by selling energy at market rates, facilities may also receive specific remuneration throughout their regulatory useful lives. This specific remuneration comprises an amount per unit of installed capacity, intended to cover any investment costs incurred by a standard facility that cannot be recovered through the sale of its energy on the market, known as "compensation for investments and an amount linked to operations, intended to cover any difference between a standard facility’s operating costs and the revenue generated from its participation in the energy production market, known as "compensation for operations".
The compensation for investments and compensation for operations applicable to a standard facility are to be calculated based on standard revenues from the sale of energy valued at market rates, standard operating costs required to perform the activity and the standard value of the initial investment—all three standard values established on the basis of an efficient, well-managed company. A set of compensation benchmarks will be established for each standard facility by order of the Ministry of Industry, Energy and Tourism....
The compensation for investments—and, where applicable, the compensation for operations—aims to cover the higher costs incurred by facilities that produce electricity from renewable energy, high-efficiency cogeneration and waste, so that they may compete on an equal footing with other technologies and obtain a reasonable return by reference to the standard facility applicable in each case.
Moreover, the concept of "reasonable return" on a project is introduced into the regulatory framework. In line with legal scholarship on this matter in recent years, reasonable return is set as a pre-tax return approximately equal to the average yield on ten-year government bonds in the secondary market for the 24-month period leading up to the month of May of the year prior to the commencement of a given regulatory period, increased by a spread.
…
Regulatory periods are to have a six-year duration. The first regulatory period spans from the date of entry into force of Royal Decree-Act 9/2013, of 12th July, to 31st December 2019. Each regulatory period is divided into two half-periods of three years each; the first half-period runs from the date of entry into force of Royal Decree 9/2013, of 12th July, to 31st December 2016.
The compensation benchmarks may be adjusted as part of a review conducted at the end of each regulatory half-period or period, pursuant to Article 14.1 of Act 24/2013, of 26th December.
All compensation benchmarks may be adjusted in the corresponding review, including the value upon which reasonable return is to be based over the remaining regulatory life of standard facilities.
…
Once a facility’s regulatory useful life99 has elapsed, it will no longer receive the compensation for investments or compensation for operations. Such facilities may remain in operation, receiving only the remuneration earned on energy sales on the market.100
a. The Tribunal lacks jurisdiction because the Claimants are not protected investors under Article 25 of the ICSID Convention. Alternatively, the Tribunal lacks jurisdiction due to the Respondent's lack of consent to having the multiple Claimants' claims heard in a single arbitration (the "Multi-Party Objection");112
b. The Tribunal lacks jurisdiction since the Claimants are not protected investors under the ECT. They are not nationals of another Contracting Party because both Germany and Spain are members of the EU, also a party to the ECT, and the ECT does not apply to disputes related to Intra-EU investments (the "Intra-EU Objection");113 and
c. The Tribunal lacks jurisdiction to decide on the alleged breach of Article 10(1) of the ECT arising from the introduction of the TVPEE by Law 15/2012. This is because Article 21 of the ECT enshrines a carve-out for taxation measures and the TVPEE is a taxation measure (the "Taxation Measure Objection").114
Resp. C-Mem., ¶ 74 (emphasis in the original) (citing Giovanni Alemanni (RL-023), ¶ 287); Resp. Opening Statement, slide 251; Tr. Day 1 [Mr. Elena Abad] 298:7-14.
Resp. C-Mem., ¶ 75 (emphasis in the original) (citing Giovanni Alemanni (RL-023), ¶ 292); Resp. Rej., ¶ 95.
a. DSG Spanien Verwaltungs GmbH, DSG Deutsche Solargesellschaft mbH, Matthias Kruck, Joachim Kruck, Ralf Hofmann, Peter Flachsmann, Frank Schumm and Rolf Schumm have not demonstrated that they are investors in the plants;129 and
b. Two of the Claimants, DSG Spanien Verwaltungs GmbH and Matthias Kruck, do not claim anything. Thus, there is no dispute as required by Article 25 of the ICSID Convention.130
Third, the Claimants argue that several tribunals have recognized that multi-party arbitrations are permissible.146 The correct standard for a multi-party arbitration, which has never been contested by the Respondent, is whether there is a common legal dispute, originated from the same facts and measures, and the relief sought is significantly similar.147 There is no requirement that several named claimants in a single arbitration must hold "identical" investments.148
Cl. Reply, ¶¶ 53-55 (citing Ambiente Ufficio S.p.A. and others v. Argentine Republic (ICSID Case No. ARB/08/9), Decision on Jurisdiction and Admissibility, 8 February 2013 (CL-002), ¶¶ 141, 161, 163; Guaracachi America, Inc. and Rurelec PLC v. Plurinational State of Bolivia (PCA Case No. 2011-17), Award, 31 January 2014 (CL-003), ¶ 341; Abaclat and others v. Argentine Republic (ICSID Case No. ARB/07/5), Decision on Jurisdiction and Admissibility, 4 August 2011 (RL-021), ¶¶ 518-519; Noble Energy, Inc. and MachalaPower Cia. Ltd. v. Republic of Ecuador and Consejo Nacional de Electricidad (ICSID Case No. ARB/05/12), Decision on Jurisdiction, 5 March 2008 ("Noble") (RL-025), ¶ 194).
Cl. Reply, ¶ 52; Cl. Rej., ¶¶ 15-17, 30 (citing Giovanni Alemanni (RL-023), ¶¶ 288, 292; Ambiente Ufficio S.p.A. and others v. Argentine Republic (ICSID Case No. ARB/08/9), Decision on Jurisdiction and Admissibility, 8 February 2013 (RL-026), ¶ 161; Noble (RL-025), ¶ 194).
Cl. Reply, ¶ 45.
a. They have not concealed any information and have taken great care to transparently describe their investments, their ownership and the damages claimed;151 as such, they have demonstrated their ownership, directly or indirectly, of all the assets related to their facilities;152
b. DSG Spanien Verwaltungs GmbH and Mathias Kruck have not claimed any specific compensation to avoid double-counting; this does not affect the Respondent’s consent to arbitrate the dispute since these Claimants fulfil the jurisdictional requisites under the ECT and the ICSID Convention;153
c. Deutsche Solar Ibérica Real State, S.L. and Solar Andaluz Grundstücks, S.L. are not Claimants in this proceeding. Some of the DSG Claimants share ownership of these companies and, as such, these two companies are investments in relation to the Projects in Alcolea, Calasparra and Todersillas;154 and
d. DSG Deutsche Solargesellschaft GmbH holds contractual rights in relation to the Alcolea, Calasparra, and Tordesillas projects and these rights have been affected by the Respondent’s conduct;155 in any event, the Claimants’ experts have ensured there will be no double recovery.156
As previously explained, the 116 Claimants fall into two distinct (but informal) groups of investors that own investments related to solar photovoltaic plants in Spain. Those Claimants are listed and numbered in our letter of April 17, 2015.
Claimants numbered 1 through 73 in that list hold investments in three photovoltaic projects in Spain known as the Alcolea, Calasparra, and Tordesillas project (Request ¶¶ 2, 11-13, 33-39). Specifically, Claimants Joachim Kruck, Ralf Hofmann, Frank Schumm, Rolf Schumm, and Peter Flachsmann invested in the Alcolea solar park, which today consists of twenty 100 kW photovoltaic plants (see Request ¶¶ 12, 33). Those Claimants incorporated an engineering, procurement, and construction company in Spain called Solar Andaluz 2006 S.L. (Request ¶ 33), which constructed and financed the Alcolea project. Additionally, they incorporated Claimants Solar Andaluz 1-20 GmbH & Co. KGs in Germany, each of which owns a Spanish special purpose vehicle that in turn owns a 100 kW solar plant comprising the Alcolea project (Request ¶¶ 33, 35).
Claimants Joachim Kruck, Ralf Hofmann, and Peter Flachsmann further invested in two additional photovoltaic projects in Spain, called Calasparra and Tordesillas (Request ¶ 36). To manage construction of these projects, they formed DS Hispano Alemana Fotovoltaica Sociedad Unipersonal S.L. and incorporated Claimants Solarpark Tordesillas 401-430 GmbH & Co. KGs and Claimants Solarpark Calasparra 251-265 GmbH & Co. KGs (Request ¶¶ 36-38). Each of the Claimants Solarpark Tordesillas 401-430 GmbH & Co. KGs and Claimants Solarpark Calasparra 251-265 GmbH & Co. KGs owns a Spanish special purpose vehicle ("SPV") that in turn owns a 100 kW photovoltaic plant comprising the Calasparra and Tordesillas projects, respectively. The Claimants’ ownership interests in those SPVs and their ownership of the photovoltaic facilities are qualifying "investments."
Moreover, the investments of Claimant Kruck Beteiligungs GmbH include its contracts with all of the German limited partnerships named above to serve as their general partner (see Request ¶ 39). The investments of Claimants Peter Flachsmann, Joachim Kruck, and DSG Deutsche Solargesellschaft mbH ("DSG") include contractual rights and rights to money enshrined in operation and management contracts that Claimant DSG entered into with respect to each Spanish SPV (see id.). Further, Claimants Peter Flachsmann, Joachim Kruck, Ralf Hofmann, Frank Schumm, and Rolf Schumm’s investments include contractual rights and rights to money derived from lease agreements that a company they own, Solar Andaluz Grundstucks S.L. (SAG S.L.), entered into with the Alcolea SPVs (id.).
Separate from the investments described above, Claimants numbered 74 through 116 in our letter of April 17, 2015, own investments in and related to ten different solar photovoltaic projects held through a number of different SPVs in Spain. Specifically, Claimants TRC Energy GmbH, Sunburn Verwaltungs GmbH, and TS Villalba GmbH own fifteen 100 kW photovoltaic plants in the Cuenca III project (see Request ¶ 42; see also CEX-13). Claimant Sunburn Verwaltungs GmbH further owns six 100 kW photovoltaic plants comprising the Cabeza Oliva project. Tauber-Solar Sierra GmbH owns two 100 kW mounted photovoltaic plants comprising the Pozoblanco Rooftop project.
Claimants TS Abuzaderas 1-30 GmbHs own thirty 100 kW photovoltaic plants comprising the Abuzaderas project (id.). Claimant TS Avila Eins GmbH owns twenty 100 kW solar plants comprising the Avila project (id.). Claimants Karsten and J ü rgen Reiss, as well as Claimants WBG GmbH, TS Cuenca zwei GmbH, TRC Energy GmbH own seven 100 kW photovoltaic plants comprising the Cuenca I project (id.). Claimant ZKS GmbH owns a 415 kW photovoltaic plant called Henibra and Claimant TS Cuenca 20 GmbH owns a 415 kW photovoltaic plant called Boguar (see Request ¶ 43; see also CEX-13). Claimant TS Valtou GmbH owns a 476 kW photovoltaic plant called Valtou, and Claimant TS Cuenca 40 GmbH owns a 340 kW photovoltaic plant called Juan del Valle (id.). The Claimants’ ownership interests in their respective Spanish SPVs and their ownership of the respective photovoltaic facilities are qualifying "investments."165
The relevant provision of ECT is Article 26, which reads as follows:
ARTICLE 26
SETTLEMENT OF DISPUTES BETWEEN AN INVESTOR AND A CONTRACTING PARTY
(1) Disputes between a Contracting Party and an Investor of another Contracting Party relating to an Investment of the latter in the Area of the former, which concern an alleged breach of an obligation of the former under Part III shall, if possible, be settled amicably.
(2) If such disputes can not be settled according to the provisions of paragraph (1) within a period of three months from the date on which either party to the dispute requested amicable settlement, the Investor party to the dispute may choose to submit it for resolution:
(a) to the courts or administrative tribunals of the Contracting Party party to the dispute;
(b) in accordance with any applicable, previously agreed dispute settlement procedure; or
(c) in accordance with the following paragraphs of this Article.
(3) (a) Subject only to subparagraphs (b) and (c), each Contracting Party hereby gives its unconditional consent to the submission of a dispute to international arbitration or conciliation in accordance with the provisions of this Article.
(b) (i) The Contracting Parties listed in Annex ID do not give such unconditional consent where the Investor has previously submitted the dispute under subparagraph (2)(a) or (b).
(ii) For the sake of transparency, each Contracting Party that is listed in Annex ID shall provide a written statement of its policies, practices and conditions in this regard to the Secretariat no later than the date of the deposit of its instrument of ratification, acceptance or approval in accordance with Article 39 or the deposit of its instrument of accession in accordance with Article 41.
(c) A Contracting Party listed in Annex IA does not give such unconditional consent with respect to a dispute arising under the last sentence of Article 10(1).
(4) In the event that an Investor chooses to submit the dispute for resolution under subparagraph (2)(c), the Investor shall further provide its consent in writing for the dispute to be submitted to:
(a) (i) The International Centre for Settlement of Investment Disputes, established pursuant to the Convention on the Settlement of Investment Disputes between States and Nationals of other States opened for signature at Washington, 18 March 1965 (hereinafter referred to as the "ICSID Convention"), if the Contracting Party of the Investor and the Contracting Party party to the dispute are both parties to the ICSID Convention; or
(ii) The International Centre for Settlement of Investment Disputes, established pursuant to the Convention referred to in subparagraph (a)(i), under the rules governing the Additional Facility for the Administration of Proceedings by the Secretariat of the Centre (hereinafter referred to as the "Additional Facility Rules"), if the Contracting Party of the Investor or the Contracting Party party to the dispute, but not both, is a party to the ICSID Convention;
(b) a sole arbitrator or ad hoc arbitration tribunal established under the Arbitration Rules of the United Nations Commission on International Trade Law (hereinafter referred to as "UNCITRAL"); or
(c) an arbitral proceeding under the Arbitration Institute of the Stockholm Chamber of Commerce.
(5) (a) The consent given in paragraph (3) together with the written consent of the Investor given pursuant to paragraph (4) shall be considered to satisfy the requirement for:
(i) written consent of the parties to a dispute for purposes of Chapter II of the ICSID Convention and for purposes of the Additional Facility Rules;
(ii) an "agreement in writing" for purposes of article II of the United Nations Convention on the Recognition and Enforcement of Foreign Arbitral Awards, done at New York, 10 June 1958 (hereinafter referred to as the "New York Convention"); and
(iii) "the parties to a contract [to] have agreed in writing" for the purposes of article 1 of the UNCITRAL Arbitration Rules.
(b) Any arbitration under this Article shall at the request of any party to the dispute be held in a state that is a party to the New York Convention. Claims submitted to arbitration hereunder shall be considered to arise out of a commercial relationship or transaction for the purposes of article I of that Convention.
(6) A tribunal established under paragraph (4) shall decide the issues in dispute in accordance with this Treaty and applicable rules and principles of international law.
(7) An Investor other than a natural person which has the nationality of a Contracting Party party to the dispute on the date of the consent in writing referred to in paragraph (4) and which, before a dispute between it and that Contracting Party arises, is controlled by Investors of another Contracting Party, shall for the purpose of article 25(2)(b) of the ICSID Convention be treated as a "national of another Contracting State" and shall for the purpose of article 1(6) of the Additional Facility Rules be treated as a "national of another State".
(8) The awards of arbitration, which may include an award of interest, shall be final and binding upon the parties to the dispute. An award of arbitration concerning a measure of a sub-national government or authority of the disputing Contracting Party shall provide that the Contracting Party may pay monetary damages in lieu of any other remedy granted. Each Contracting Party shall carry out without delay any such award and shall make provision for the effective enforcement in its Area of such awards.
The express terms of ECT Article 26 are clear. It makes provision for the arbitration of "a dispute" or "the dispute" between the parties to it, and thus indicates an assumption that it is what might be called a ‘single’ or a ‘unitary’ dispute that will come before an arbitral tribunal. Article 26(3)(a) refers to "consent to the submission of a dispute to international arbitration", and in adding qualifications (not relevant here) to that provision, paragraphs (3)(b) and (c) refer respectively to "the dispute" and "a dispute" in the singular. Similarly, Article 26(4) addresses situations in which an Investor chooses to "submit the dispute" for resolution, referring consistently to "the dispute." Article 26(5), (7), and (8) also refer throughout to "a dispute" or "the dispute", in the singular.
The only elements of the language of Article 26 that might suggest that it is possible to file multiple ‘disputes’ as a single ‘case’ appear in Article 26(1) and (2). Those paragraphs refer to "disputes", and appear to refer to disputes in the plural. Those paragraphs are, however, setting out general provisions applicable to each and every dispute "between a Contracting Party and an Investor of another Contracting Party relating to an Investment of the latter in the Area of the former, which concern an alleged breach of an obligation of the former under Part II." Paragraph (1) says that such disputes (i.e., each and every dispute within the definition in paragraph (1)) "shall, if possible, be settled amicably." Paragraph (2) opens by referring to "such disputes", i.e., the disputes identified by paragraph (1): it provides (with emphasis added) that "[i]f such disputes can not be settled according to the provisions of paragraph (1) within a period of three months from the date on which either party to the dispute requested amicable settlement, the Investor party to the dispute may choose to submit it for resolution..." But its meaning would be more accurately rendered by stating that the words "if any such dispute" cannot be so settled it may be submitted for resolution. It would be completely and obviously nonsensical to say that all disputes falling with Article 26(1) must remain unsettled before any such dispute may be submitted for resolution.169
If confirmation of this interpretation were needed it can be found in the French text of ECT Article 26(2), which states that "Si un différend de ce type n'a pu être réglé́ conformément aux dispositions du paragraphe 1 dans un délai de trois mois à compter du moment où l'une des parties au différend a sollicité́ un règlement à l'amiable, l'investisseur partie au différend peut choisir de le soumettre, en vue de son règlement …." Recourse to other authentic texts (cf., ECT Article 50) is a standard part of well-established principles of treaty interpretation: see Vienna Convention on the Law of Treaties, 23 May 1969 (CL-049), Article 33.
For these reasons, the Tribunal finds that the consent to arbitrate given in ECT Article 26, and specifically in Article 26(3) is a consent to accept the submission of a dispute to a tribunal, and does not amount to consent to submit two or more distinct disputes to a tribunal in a single proceeding. This is not a question of the ECT or the ICSID Convention or Arbitration Rules imposing "a requirement of separate consent to a multi-party arbitration", as the Claimants put it:171 it is a question of the precise scope of the Respondent’s actual consent.
Cl. Response to Preliminary Objections, 2 March 2016, p. 9.
Resp. Rej., ¶ 95, quoting Giovanni Alemanni (RL-023), ¶ 292. Cf. Resp. Rej., ¶¶ 75–103. A similar approach has been taken in other cases. See the materials listed in Claimants' Response to Preliminary Objections under ICSID Arbitration Rule 41(5), 2 March 2016, pp. 9–13.
2006 | |
30/05 | Joachim Kruck ("JK") Purchase of 50% of the shares in real estate lessor Solar Andaluz Grundstucks S.L. (C-203, company renamed at C-209), which owns the land on which Project Alcolea is located (C-202). Ownership interest reduced on 15 Jan. 2008 to 25% (C-204). The company owns a right to 30% of excess profit from the sale of electricity produced by the Alcolea plants (Id.). The company also owns the right to purchase the Project Alcolea plants after twenty-five years of operation (C-246). Rolf Schumm ("RS") Purchase of 25% of the shares in real estate lessor Solar Andaluz Grundstucks S.L. through the company Monte Grace Paradise, S.L. in which he owned a 50% interest (C-206), which owns the land on which Project Alcolea is located (C-202). On 31 Oct. 2007, Monte Grace Paradise, S.L. reduced its ownership share in Solar Andaluz Grundstucks S.L. to 25%, with the result that Rolf Schumm owned a 12.5% interest in the real estate company (C-205). On 1 Aug. 2013, Rolf Schumm sold his interest in Monte Grace Paradise, S.L. and thereby Solar Andaluz Grundstucks S.L. (C-206). The company owns a right to 30% of excess profit from the sale of electricity produced by the Alcolea plants (C- 202). Frank Schumm ("FS") Purchase of 25% of the shares in real estate lessor Solar Andaluz Grundstucks S.L. through the company Monte Grace Paradise, S.L. in which he owned a 50% |
interest (C-206), which owns the land on which Project Alcolea is located (C-202). On 31 Oct. 2007, Monte Grace Paradise, S.L. reduced its ownership share in Solar Andaluz Grundstucks S.L. to 25%, with the result that Frank Schumm owned a 12.5% interest in the real estate company (C-205). On 1 Aug. 2013, Frank Schumm acquired the remaining 50% interest in Monte Grace Paradise, S.L. and thereby Solar Andaluz Grundstucks S.L. (C-206), thereby owning Monte Grace Paradise, S.L.'s full 25% share of Solar Andaluz Grundstucks S.L. The company owns a right to 30% of excess profit from the sale of electricity produced by the Alcolea plants (Id.). The company also owns the right to purchase the Project Alcolea plants after twenty-five years of operation (C-246). | |
2007 | |
2008 | |
JK Acquisition of interest in right to profits from excess production from all three plants by way of his 57% ownership interest in Claimant DSG GmbH, which was acquired in 2006 (C-005, C-197, C-198). [This claim is forwarded by DSG GmbH, the party to the contract, rather than Mr. Kruck]. Peter Flaschmann ("PF") Acquisition of interest in right to profits from excess production from all three plants by way of his 43% ownership interest in Claimant DSG GmbH, which was acquired in 2006 (C-005, C-197, C-198). [This claim is forwarded by DSG GmbH, the party to the contract, rather than Mr. Flaschmann. It is mentioned here for sake of completeness in describing Mr. Flaschmann's investments.]. | |
15/01 | PF Purchase of 25% of the shares in real estate lessor Solar Andaluz Grundstucks S.L. (C-204), which owns the land on which Project Alcolea is located (C-202). The company owns a right to 30% of excess profit from the sale of electricity produced by the Alcolea plants (Id.). The company also owns the right to purchase the Project Alcolea plants after twenty-five years of operation (C-246). |
27/02 | DSG Deutsche Solargesellschaft mbH DSG Deutsche Solargesellschaft GmbH owns rights174 to 50% of excess profit from the sale of electricity produced by the Project Alcolea PV plants (C-199). |
28/02 | Solar Andaluz 120 GmbH Purchase by each Claimant company of the assets of one of the Project Alcolea PV plants through the Claimant companies' wholly-owned Spanish subsidiaries (20 Claimants, 20 SPVs, and 20 plants in all) (C-223). Documents demonstrating Claimants' purchase of the SPVs: C-221; C-222. |
27/03 | Ralf Hofmann ("RH") Purchase of 25% of the shares in real estate lessor Solar Andaluz Grundstucks S.L. (C-205), which owns the land on which Project Alcolea is located (C-202). The company owns a right to 30% of excess profit from the sale of electricity produced by the Alcolea plants (Id.). The company also owns the right to purchase the Project Alcolea PV plants after twenty-five years of operation (C-246). |
10/04 | FS Purchase of 100% of the shares in Claimant Solar Andaluz 4 GmbH & Co. KG, which owns one of the Project Alcolea PV plants (C-192). |
11/04 | JK Purchase of 100% of the shares in Claimant Solar Andaluz 3 GmbH & Co. KG, which owns one of the Project Alcolea PV plants (C-339). |
RH Purchase of 100% of the shares in Claimant Solar Andaluz 1 GmbH & Co. KG, which owns one of the Project Alcolea PV plants (C-195). | |
17/04 | PF Purchase of 100% of the shares in Claimant Solar Andaluz 2 GmbH & Co. KG, which owns one of the Project Alcolea PV plants (C-193). |
28/04 | Karsten Reiss Purchase of a 50% interest in the Project Cuenca I Bravosonnen plant (C-288). Jürgen Reiss Purchase of a 50% interest in the Project Cuenca I Bravosonnen plant (C-288). |
19/05 | JK Purchase of 33.3% of the shares in real estate lessor Deutsche Solar Ibérica Real Estate S.L. (C- 210), which owns the right to purchase the Project Calasparra and Tordesillas plants after twenty-five years of operation (C-247, C-248). PF Purchase of 33.3% of the shares in real estate lessor Deutsche Solar Ibérica Real Estate S.L. (C-245), which owns the right to purchase the Project Calasparra and Tordesillas PV plants after twenty-five years of operation (C-247, C-248). |
26/06 | TS Abuzaderas 1-30 GmbH Purchase by each Claimant of 100% of the shares in one of the Project Abuzaderas SPVs (for a total of 30 Claimants and 30 SPVs) (C-271). On the same day, each SPV purchased the one of the Project Abuzaderas plants (for a total of 30 plants) (C-272). |
15/07 | DSG Deutsche Solargesellschaft mbH DSG Deutsche Solargesellschaft GmbH owns rights to 50% of excess profit from the sale of electricity produced by the Project Calasparra PV plants (C-200). |
31/07 | RH Purchase of 33.3% of the shares in real estate lessor Deutsche Solar Ibérica Real Estate S.L. (C-249), which owns the right to purchase the Project Calasparra and Tordesillas PV plants after twenty-five years of operation (C-247, C-248). |
05/08 | TRC Energy GmbH Purchase of four of the Project Cuenca III plants(C-297). |
06/08 | Sunburn Verwaltungs GmbH. Purchase of ten of the Project Cuenca I plants (C- 304). |
12/08 | TS Villalba GmbH Purchase of one of the Project Cuenca III plants (C-300). |
21/08 | Solarpark Calasparra 251-265 Purchase by each Claimant company of 100% of the shares in one of the SPVs that owned one of the Project Calasparra plants (15 Claimants, 15 SPVs, and 15 plants in all) (C-230). Documents demonstrating that the SPVs owned the plants: C-227. Solarpark Tordesillas 401-430 GmbH Purchase by each Claimant company of 100% of the shares in one of the SPVs that owned one of the Project Tordesillas plants (30 Claimants, 30 SPVs, and 30 plants in all) (C-229). Documents demonstrating that the SPVs owned the plants: C-228. |
31/08 | TS Cuenca zwei GmbH Purchase of two of the Project Cuenca I plants (C-282). |
08/10 | TS Avila eins GmbH Purchase by TS Avila 1-20 GmbH each of one of the Project Avila plants (C-280). In August 2009 TS Avila 1-20 GmbH merged into Claimant TS Avila eins GmbH (C-007). |
02/11 | DSG Deutsche Solargesellschaft mbH DSG Deutsche Solargesellschaft GmbH owns rights to 50% of excess profit from the sale of electricity produced by the Project Tordesillas PV plants (C-201). |
20/11 | TRC Energy GmbH Purchase of one of the Project Cuenca I plants (C-293). |
01/12 | JK Purchase of 50% of the shares in Claimant Solarpark Calasparra 253 GmbH & Co. KG, which owns one of the Project Calasparra PV plants (C-338). Mathias Kruck ("MK") Purchase of 50% of the shares in Claimant Solarpark Calasparra 253 GmbH & Co. KG, which owns one of the Project Calasparra PV plants (C-338). |
29/12 | RH Purchase of 100% of the shares in Claimant Solarpark Tordesillas 407 GmbH & Co. KG, which owns one of the Project Tordesillas PV plants (C-196). |
2009 | |
10/03 | RH Purchase of 100% of the shares in Claimant Solarpark Calasparra 251 GmbH & Co. KG, which owns one of the Project Calasparra PV plants (C-214). |
31/03 | RH Purchase of 100% of the shares in Claimant Solarpark Tordesillas 413 GmbH & Co. KG, which owns one of the Project Tordesillas PV plants (C-336). |
03/04 | PF Purchase of 50% of the shares in Claimant Solarpark Tordesillas 418 GmbH & Co. KG, which owns one of the Project Tordesillas PV plants (C-194). |
06/04 | JK Purchase of 100% of the shares in Claimant Solarpark Tordesillas 414 GmbH & Co. KG, which owns one of the Project Tordesillas PV plants (C-190). |
23/04 | RH Purchase of 1% of the shares in Claimant Solarpark Tordesillas 421 GmbH & Co. KG, which owns one of the Project Tordesillas PV plants (C-337). |
05/05 | JK Purchase of 43% of Claimant Solarpark Tordesillas 422 GmbH & Co. KG, which owns one of the Project Tordesillas PV plants (C-191). |
11/07 | Sunburn Verwaltungs GmbH Purchase of the six Project Cabeza Oliva plants (C-309). |
30/09 | WBG GmbH Purchase of three of the Project Cuenca I plants (C-292). |
2010 | |
06/12 | Tauber-Solar Sierra GmbH Purchase of the two Project Pozoblanco Rooftop plants (C-314). |
07/12 | Tauber-Solar Sierra GmbH Purchase of the two Project Pozoblanco Rooftop plants (C-314). |
2011 | |
2012 | |
18/04 | ZKS GmbH Purchase of the Project Málaga Henibra plant (C-319). TS Cuenca 20 GmbH Purchase of the Project Málaga Boguar plant (C-325). |
22/06 | TS Valtou GmbH Purchase of the Project Valtou plant (C-329). |
10/07 | TS Cuenca 40 GmbH Purchase of the Project Juan del Valle plant (C-334). |
The TS Investors Group made all of the foregoing investments in Spain in reliance on certain incentive regimes that Spain specifically established to attract the type of projects that the TS Investors Group owns and operates. The TS Investors Group developed or acquired six of the projects mentioned above — Cuenca I, Cuenca III, Cabeza Oliva, Pozoblanco Rooftop, Abuzaderas and Gotarrendura — with the expectation that those parks would benefit from the remunerative regime established in Royal Decree 661/2007 of May 25, 2007, regulating the activity of electrical energy generation by means of renewable facilities ("RD 661"). TS Investors Group expected its four additional solar projects — Henibra, Boguar, Valtou and Juan del Valle — to benefit from the remunerative regime established in Royal Decree 1578/2008 of September 26, 2008 ("RD 1578").
Both RD 661 and RD 1578 contained attractive remuneration schemes that made creating photovoltaic facilities in Spain worthwhile and economically viable. The TS Investors Group would not have invested in Spain by acquiring and developing those photovoltaic facilities in the absence of the incentives included in that legislation.184
a. the DSG Claimants and the TS Claimants were at no stage prior to these proceedings in contact with one another;
b. there is no evidence that they shared a one and the same approach to their respective investments or common facilities;
c. they did not invest in the same projects; and
d. the two groups took their advice from different sources and in different ways and at different times.189
The Preliminary Award on Jurisdiction in the PV Investors case190 contains a careful and detailed consideration of the question of multiple claims, reviewing earlier decisions on the topic. The PV Investors tribunal distinguished between "aggregate proceedings", in which multiple, individual claimants bring claims in their own name ab initio in one single arbitration, and "consolidation", in which pending parallel proceedings are joined into a single one, finding that the joinder of claims in consolidation requires specific consent but that aggregate proceedings do not.191 Importantly, however, the PV Investors tribunal referred to the need for a "sufficient connection" between the claimants in that case. It said,
... the Tribunal is satisfied that a sufficient connection exists between them to justify hearing the Claimants’ claims in one single arbitration. The Claimants complain of the same measures taken by Spain in relation to the PV sector, which they allege have negatively affected their investments. In addition, they invoke the same Treaty provisions and claim the same type of relief. Thus, the Tribunal does not believe that any diversities in the Claimants’ situations would make the proceedings unmanageable or unworkable.192
As was noted above, this might be described as a being the result of a jurisdictional defect, because the Claimants have not accepted the ‘offer' to arbitrate made by the Respondent in ECT Article 26 but have in effect proposed an alternative mode of arbitration of disputes, permitting the concurrent handling of a number of disparate disputes in a single proceeding, to which the Respondent has not agreed.
As was indicated above, the Tribunal will now address the question whether it has jurisdiction ratione personae over each of the DSG Claimants. Jurisdiction ratione personae exists under ECT Article 26(1) if there is a dispute "between a Contracting Party and an Investor of another Contracting Party relating to an Investment of the latter in the Area of the former, which concern an alleged breach of an obligation of the former under Part III" of the ECT. An "Investor" is defined in ECT Article 1(7). So far as is material it reads as follows:
"Investor" means:
(a) with respect to a Contracting Party:
(i) a natural person having the citizenship or nationality of or who is permanently residing in that Contracting Party in accordance with its applicable law;
(ii) a company or other organisation organised in accordance with the law applicable in that Contracting Party
The registration certificates of Claimants 66 and 67,204 the private companies DSG Deutsche Solargesellschaft mbH and Kruck Beteiligungs GmbH (later renamed DSG Spanien Verwaltungs GmbH205), have established their German nationality. So, too, have the registration certificates of Claimants 1-65, the limited liability partnerships Solar Andaluz 1-20 GmbH & Co. KG, Solarpark Calasparra 251-265 GmbH & Co. KG, and Solarpark Tordesillas 401-430 GmbH & Co. KG.206 Each being a "company or other organization organized in accordance with the law applicable in [Germany]", these companies and limited partnerships fall within the definition of an investor in ECT Article 1(7)(a)(ii). As nationals of Germany, the Claimants are also "nationals of another Contracting State" within the meaning of Article 25 of the ICSID Convention. The Tribunal therefore decides that it has jurisdiction ratione personae over these Claimants under ECT Article 26 and Article 25 of the ICSID Convention.
ECT Article 1(6) sets out the definition of an "investment." Together with its accompanying ‘Understanding’, it reads as follows:
(6) "Investment" means every kind of asset, owned or controlled directly or indirectly by an Investor and includes:
(a) tangible and intangible, and movable and immovable, property, and any property rights such as leases, mortgages, liens, and pledges;
(b) a company or business enterprise, or shares, stock, or other forms of equity participation in a company or business enterprise, and bonds and other debt of a company or business enterprise;
(c) claims to money and claims to performance pursuant to contract having an economic value and associated with an Investment;
(d) Intellectual Property;
(e) Returns;
(f) any right conferred by law or contract or by virtue of any licences and permits granted pursuant to law to undertake any Economic Activity in the Energy Sector.
A change in the form in which assets are invested does not affect their character as investments and the term "Investment" includes all investments, whether existing at or made after the later of the date of entry into force of this Treaty for the Contracting Party of the Investor making the investment and that for the Contracting Party in the Area of which the investment is made (hereinafter referred to as the "Effective Date") provided that the Treaty shall only apply to matters affecting such investments after the Effective Date.
"Investment" refers to any investment associated with an Economic Activity in the Energy Sector and to investments or classes of investments designated by a Contracting Party in its Area as "Charter efficiency projects" and so notified to the Secretariat.
[UNDERSTANDING] With respect to Article 1(6)
For greater clarity as to whether an Investment made in the Area of one Contracting Party is controlled, directly or indirectly, by an Investor of any other Contracting Party, control of an Investment means control in fact, determined after an examination of the actual circumstances in each situation. In any such examination, all relevant factors should be considered, including the Investor’s
(a) financial interest, including equity interest, in the Investment;
(b) ability to exercise substantial influence over the management and operation of the Investment; and
(c) ability to exercise substantial influence over the selection of members of the board of directors or any other managing body.
Where there is doubt as to whether an Investor controls, directly or indirectly, an Investment, an Investor claiming such control has the burden of proof that such control exists.
DSG Claimants' Investments | ||||
No | Claimant | Project(s) | Investment and Ownership Share | Allocation of Compensation Claimed |
1-20 | Solar Andaluz 1-20 GmbH & Co. KG (the "Alcolea Claimants'") | Alcolea | Each Alcolea Claimant owns 100% of a Spanish SPV and one of the twenty 100 kW PV facilities comprising this Project | Each Alcolea Claimant claims 5% of the harm caused to Project Alcolea for the first 25 years of operation, reflecting its shareholding in Alcolea |
21- 35 | Solarpark Calasparra 251-265 GmbH & Co. KG (the "Calasparra Claimants") | Calasparra | Each Calasparra Claimant owns 100% of a Spanish SPV and one 100 kW of the fifteen 100 kW PV facilities comprising this Project | Each Calasparra Claimant claims 6.67% of the harm caused to Project Calasparra for the first 25 years of operation, reflecting its shareholding in Calasparra |
36- 65 | Solarpark Tordesillas 401-430 GmbH & Co. KG (the "Tordesillas Claimants") | Tordesillas | Each Tordesillas Claimant owns 100% of a Spanish SPV and one of the thirty 100 kW PV facilities comprising this Project | Each Tordesillas Claimant claims 3.33% of the harm caused to Project Tordesillas for the first 25 years of operation, reflecting its shareholding in Tordesillas |
66 | DSG Deutsche Solargesellschaft mbH ("DSG GmbH") | Alcolea. Calasparra. and Tordesillas | Claims to bonus payments resulting from higher-than-projected revenue when Projects Alcolea. Calasparra. and Tordesillas surpass projected electricity production | 100% of the harm caused to DSG GmbH as a result of lost bonus payments from Alcolea, Calasparra. and Tordesillas |
67 | DSG Spanien Verwaltungs GmbH ("DSG Spain") | Alcolea. Calasparra. and Tordesillas | Indirect Interests in the Alcolea. Calasparra. and Tordesillas Claimants as their General Partner | None - compensation for this claim is covered through the compensation allocated to the Alcolea. Calasparra. and Tordesillas Claimants |
68 | Mathias Kruck | Calasparra | 50% of Claimant Solarpark Calasparra 253 GmbH & Co. KG | None - compensation for this claim is covered through the compensation allocated to Claimant Solarpark Calasparra 253 GmbH & Co. KG |
69 | Joachim Kruck | Alcolea | 100% of Claimant Solar Andaluz 3 GmbH & Co. KG | None - compensation for this claim is covered through the compensation allocated to Claimant Solar Andaluz 3 GmbH & Co. KG |
25% of real estate lessor. Solar Andaluz Grundstücks S.L., related bonus payments, and purchase right | 25% of the harm caused to Solar Andaluz Grundstücks S.L. | |||
Calasparra | 50% of Claimant Solarpark Calasparra 253 GmbH & Co. KG | None - compensation for this claim is covered through the compensation allocated to Claimant Solarpark Calasparra 253 GmbH & Co. KG | ||
Tordesillas | 100% of Claimant Solarpark Tordesillas 414 GmbH & Co. KG | None - compensation for this claim is covered through the compensation allocated to Claimant Solarpark Tordesillas 414 GmbH & Co. KG | ||
43% of Claimant Solarpark Tordesillas 422 GmbH & Co. KG | None - compensation for this claim is covered through the compensation allocated to Claimant Solarpark Tordesillas 422 GmbH & Co. KG | |||
Alcolea. Calasparra. and Tordesillas | 57% of Claimant DSG GmbH | None - compensation for this claim is covered through the compensation allocated to Claimant DSG GmbH | ||
Calasparra & Tordesillas | 33.3% of real estate lessor. Deutsche Solar Ibérica Real Estate S.L. and related purchase rights | 33.3% of the harm caused to Deutsche Solar Ibérica Real Estate S.L. | ||
70 | Peter Flachsmann | Alcolea | 100% of Claimant Solar Andaluz 2 GmbH & Co. KG | None - compensation claimed through Claimant Solar Andaluz 2 GmbH & Co. KG |
25% of real estate lessor. Solar Andaluz Grundstücks S.L., related bonus payments, and purchase right | 25% of the harm caused to Solar Andaluz Grundstücks S.L. | |||
Tordesillas | 50% of Claimant Solarpark Tordesillas 418 GmbH & Co. KG | None — compensation claimed through Claimant Solarpark Tordesillas 418 GmbH & Co. KG | ||
Alcolea. Calasparra. and Tordesillas | 43% of Claimant DSG GmbH | None — compensation claimed through Claimant DSG GmbH | ||
Calasparra and Tordesillas | 33.3% of Deutsche Solar Ibérica Real Estate S.L. and related purchase rights | 33.3% of the harm caused to Deutsche Solar Ibérica Real Estate S.L. |
71 | Ralf Hofmann | Alcolea | 100% of Claimant Solar Andaluz 1 GmbH & Co. KG | None — compensation claimed through Claimant Solar Andaluz 1 GmbH & Co. KG |
Calasparra | 100% of Claimant Solarpark Calasparra 251 GmbH & Co. KG | None — compensation claimed through Claimant Solarpark Calasparra 251 GmbH & Co. KG | ||
Tordesillas | 100% of Claimants Solarpark Tordesillas 407 GmbH & Co. KG and Solarpark Tordesillas 413 GmbH & Co. KG and 1% of Claimant Solarpark Tordesillas 421 GmbH & Co. KG | None - compensation claimed through relevant Tordesillas Claimants | ||
Alcolea | 25% of real estate lessor. Solar Andaluz Grundstücks S.L. and related bonus payments and purchase right | 25% of the harm caused to Solar Andaluz Grundstücks S.L. | ||
Calasparrra and Tordesillas | 33.3% of Deutsche Solar Ibénca Real Estate S.L. and related purchase rights | 33.3% of the harm caused to Deutsche Solar Ibérica Real Estate S.L. | ||
72 | Rolf Schumm | Alcolea | 12.5% of real estate lessor. Solar Andaluz Grundstücks S.L., related bonus payments, and purchase right (until August 1, 2013) | 12.5% of the harm caused to Solar Andaluz Grundstücks S.L. |
73 | Frank Schumm | Alcolea | 100% of Claimant Solar Andaluz 4 GmbH & Co. KG | None - compensation for this loss is covered through the compensation allocated to Claimant Solar Andaluz 4 GmbH & Co. KG |
12.5% of real estate lessor. Solar Andaluz Grundstücks S.L., related bonus payments, and purchase right (until August 1, 2013) | 12.5% of the harm caused to Solar Andaluz Grundstücks S.L. |