5 Member States Declaration | Declaration of the Representatives of the Governments of the Member States, dated 16 January 2019, on the enforcement of the Judgment of the Court of Justice in Achmea and on the investment protection in the European Union signed by the Representatives of the Governments of Finland, Luxembourg, Malta, Slovenia and Sweden |
22 Member States Declaration | Declaration of the Representatives of the Governments of the Member States, dated 15 January 2019, on the legal consequences of the judgment of the Court of Justice in Achmea and on Investment Protection in the European Union signed by the Representatives of the Governments of Belgium, Bulgaria, Czech Republic, Denmark, Germany, Estonia, Ireland, Greece, Spain, France, Croatia, Italy, Cyprus, Latvia, Lithuania, Netherlands, Austria, Poland, Portugal, Romania, Slovakia and United Kingdom of Great Britain and Northern Ireland |
1977 Electricity Law or Law 54/1997 | Law 54/2007 on the Electricity Sector of 27 November 1997 |
2001 Directive | Directive 2001/77/CE "on the promotion of electricity produced from renewable energy sources in the internal electricity market" |
2009 Renewable Energy Directive | Directive 2009/28/EC approved by the European Parliament and Council of 23 April 2009 "on the promotion of the use of energy from renewable sources and subsequently repealing Directives 2001/77/EC and 2003/30/EC" |
Achmea Judgment | Slovak Republic v. Achmea BV, Case C-284/16, Judgment of the Court, 6 March 2018, Exhibit CL-151 |
Alternative Tariff | An alternative damages calculation prepared in Brattle's Second Quantum Report, presenting a reasonable return that assumes an entitlement not to the FIT Tariffs under the Original Regime, but rather to the "reasonable return" that was implicit in the FIT Tariff under Royal Decree 1578/2008 |
Arbitration Rules | ICSID Rules of Procedure for Arbitration Proceedings of 2006 |
BDO's First Report | BDO's First Expert Report dated 9 July 2018, submitted with Respondent's Counter-Memorial |
BDO's Second Report | BDO's Rejoinder Expert Report dated 13 February 2019, submitted with Respondent's Rejoinder |
Brattle's First Quantum Report | Brattle's quantum expert report "Financial Damages to Investors" dated 29 March 2018, submitted with Claimants' Memorial |
Brattle's First Regulatory Report | Brattle's first regulatory expert Report entitled "Changes to the Regulation of Photovoltaic Installations in Spain since December 2012" dated 29 March 2018, submitted with Claimants' Memorial |
Brattle's Rebuttal Regulatory Report | Brattle's rebuttal regulatory expert report entitled "Rebuttal: Changes to the Regulation of Photovoltaic Installations in Spain since December 2012" dated 28 November 2018, submitted with Claimants' Reply |
Brattle's Second Quantum Report | Brattle's second expert report entitled "Report: Financial Damages to Investors" dated 28 November 2018, submitted with Claimants' Reply |
C-[#] | Claimants' Exhibit |
CJEU | European Union Court of Justice |
CL-[#] | Claimants' Legal Authority |
Cl. Memorial | Claimants' Memorial on the Merits dated 29 March 2018 |
Cl. PHB | Claimants' Post-Hearing Brief dated 11 May 2020 |
Cl. Rejoinder on Jurisdiction | Claimants' Rejoinder on Jurisdiction dated 25 April 2019 |
Cl. Reply | Claimants' Reply on the Merits and Counter-Memorial on Jurisdiction dated 29 November 2018 |
Cl. Reply PHB | Claimants' Reply Post-Hearing Brief dated 17 June 2020 |
Claimants | Infracapital F1 S.a.r.l. and Infracapital Solar B.V. |
Claimants' PV Plants | Jointly, the First and Second Investment Plants |
Clean Hands Objection | Respondent's Objection to Jurisdiction dated 20 December 2019 |
CNE | Comisión Nacional de Energía or National Energy Commission |
CPI | Consumer Price Index |
Disputed Measures | Measures adopted by Spain between 2012 and 2014, including Law 15/12, Royal Decree-Law 2/2013, Royal Decree-Law 9/2013, Law 24/2013, Royal Decree 413/2014 and the June 2014 Order |
EC | European Commission |
EC's Application | European Commission's Application for Leave to Intervene as a Non-Disputing Party dated 29 October 2018 |
EC Decision | Decision C(2017) 7384 of the European Commission, rendered on 10 November 2017, regarding the Support for Electricity generation from renewable energy sources, cogeneration and waste (S.A. 40348 (2015/NN), Legal Authority RL-0060 |
ECT | Energy Charter Treaty |
EU | The European Union |
First Investment Plants | Jointly, the Tordesillas Plants and the Valtierra I, II and & III Plants |
FIT | "feed-in-tariff" which represents the tariff that has a right to receive a premium payment over and above the market price per kWh produced |
Fontellas Plants | PV installations acquired by Claimants from OPDE Investment España S.L. (Spanish-incorporated company) via Promociones Fotovoltaicas Castanea, S.L., Promociones Fotovoltaicas Fagus, S.L., Promociones Fotovoltaicas Corylus, S.L., and Promociones Fotovoltaicas Betula, S.L. |
Hearings | The Hearing on Jurisdiction and the Merits held on 24-28 June 2019 in Paris (the "June Hearing"), and the Hearing held at the International Dispute Resolution Centre Ltd (IDRC) in London on 27 February 2020 (the "Second Hearing"). |
ICSID Convention | Convention on the Settlement of Investment Disputes Between States and Nationals of Other States dated 18 March 1965 |
ICSID or the Centre | International Centre for Settlement of Investment Disputes |
IDAE | "Instituto de Diversificación y Ahorro de Energía" or Institute for the Diversification and Saving of Energy |
Intra-EU Objection I | Objection raised by Respondent to the jurisdiction of the Tribunal ratione materiae, arguing that Claimants are not investors protected under the ECT, because Article 26 of the ECT, which establishes the dispute settlement mechanism, does not apply to disputes arising between an investor of an EU Member State and an EU Member State. |
Intra-EU Objection II | Objection raised by Respondent to the jurisdiction of the Tribunal ratione materiae, arguing that the Tribunal is "called upon to interpret and apply" EU law since the dispute affects the EU fundamental freedoms and State Aid. |
June 2014 Order | Ministerial Order IET/1045/2014 issued on 16 June 2014 by the Ministry of Industry, Energy and Tourism to further implement the New Regime |
June Hearing | Hearing on Jurisdiction and the Merits held on 24-28 June 2019 in Paris |
Lasesa Plants | PV installations acquired by Claimants from Dalkia Solar, S.L, Forcimsa Empresa Constructora, S.A. and Forcimsa AOC Obra Civil, S.L. (Spanish entities), through Sariñena Solar, S.L. (Spanish-incorporated company) via its 40 Spanish subsidiaries, Lasesa Solar I 1, S.L. to Lasesa Solar I 40, S.L |
Law 15/2012 | Law 15/2012 adopted on 27 December 2012 "Tax Measures for Energy Sustainability," which entered into effect on 1 January 2013 |
Law 2/2011 | Law 2/2011 on Sustainable Economy of 4 March 2010 |
Law 24/2013 | Law 24/2013 of 26 December 2013 on the Electricity Sector, which superseded Law 54/1997 |
Lief WS1 | Witness Statement of Mr. Mathieu Lief dated 22 March 2018, submitted with Claimants' Memorial |
Lief WS2 | Second Witness Statement of Mr. Mathieu Lief dated 26 November 2018, submitted with Claimants' Reply |
Montoya WS | Witness Statement of Mr. Carlos Montoya dated 5 July 2018, submitted with Respondent's Counter-Memorial |
New Regime | Regime for compensation introduced under Royal Decree-Law 9/2013 whereby renewable energy producers received: (i) a payment of the wholesale market price for the electricity produced; (ii) a possible additional "specific remuneration" based on the electricity produced to compensate operating costs not covered by the wholesale market price; and (iii) a payment per MWh of installed capacity based on the net investment costs of a "standard facility" or "instalación tipo" during its "useful life. |
Ordinary Regime | Chapter I of the 1997 Electricity Law, which applies to conventional electricity generation plants |
R-[#] | Respondent's Exhibit |
RAIPRE | Administrative Registry for Electricity Production Facilities ("Registro Administrativo de Instalaciones de Producción de Energía Eléctrica") kept by the Ministry of Energy and Tourism |
Ratione Temporis Objection | Objection made by Respondent to the jurisdiction of the Tribunal, arguing that Claimants cannot prove the ownership of their investment before the Disputed Measures were adopted |
Ratione Temporis Objection | Objection made by Respondent to the jurisdiction of the Tribunal to hear Claimants' claim in respect to part of their investment that was made during and after the Disputed Measures were adopted. |
RD 1565/2010 | Royal Decree 1565/2010 dated 19 November 2010 "regulating and modifying certain aspects of the electricity generation activity under the Special Regime" |
RD 1578/2008 | Royal Decree 1578/2008 dated 26 September 2008 "on the remuneration for electric energy production using photovoltaic technology for plants subsequent to the deadline for maintenance of the remuneration under RD 661/2007" |
RD 1614/2010 | Royal Decree 1614/2010 dated 7 December 2010 "regulating and modifying certain aspects relating to the production of electricity based on thermoelectric and wind technologies" |
RD 2818/1998 | Royal Decree 2818/1998 dated 30 December 1998 to promote the development of renewable energy facilities under the Special Regime |
RD 413/2014 | Royal Decree 413/2014 dated 6 June 2014 "regulating the activity of electric power production from renewable energy sources, cogeneration and waste" |
RD 436/2004 | Royal Decree 436/2004 dated 12 March 2004 "establishing the methodology for the updating and systemization of the legal and economic regime for electric power production in the Special Regime" |
RD 661/2007 | Royal Decree 661/2007 dated 25 May 2007 "regulating the activity of electricity production under the Special Regime" |
RDL | Royal Decree Law |
RDL 14/2010 | Royal Decree-Law 14/2010 dated 23 December 2010 on "urgent measures to correct the tariff deficit in the electricity sector" |
RDL 2/2013 | Royal Decree-Law 2/2013 dated 1 February 2012 concerning "urgent measures within the electricity system and the financial sector " |
RDL 6/2009 | Royal Decree-Law 6/2009 dated 30 April 2009, adopting certain measures within the energy sector and approving the social bond |
RDL 7/2006 | Royal Decree-Law 7/2006 of 24 June 2006, on the "adoption of urgent measures for the energy sector" |
RDL 9/2013 | Royal Decree-Law 9/2013 of 12 July 2013 on "urgent measures to ensure the financial stability of the electricity system" |
RE | Renewable Energy |
Report 30/2008 | Report 30/2008 issued by the CNE dated July 29, 2008 on "the royal decree proposal to reward the production of electrical energy using photovoltaic solar technology in plants subsequent to the cut-off date for maintaining the rewards set forth by royal decree 661/2007, of the 25th of May, for said technology" |
Request for Arbitration | Request for Arbitration from Claimants against Respondent dated 15 June 2016, and supplemented on 29 June 2016 |
Resp. C-Memorial | Respondent's Counter-Memorial on the Merits and Memorial on Jurisdiction dated 9 July 2018 |
Resp. PHB | Respondent's Post-Hearing Brief dated 3 June 2020 |
Resp. Rejoinder | Respondent's Rejoinder on the Merits and Reply on Jurisdiction dated 14 February 2019 |
Resp. Reply PHB | Respondent's Reply Post Hearing Brief dated 26 June 2020 |
RL-[#] | Respondent's Legal Authority |
RRR | Reasonable Rate of Return |
Resp. Second Submission on the New Objection | Submission by Respondent on 19 March 2020 in respect to its Clean Hands Objection, entitled Lack of Clean Hands by Claimants as a Jurisdictional Objection, and subsidiarily, of Inadmission. Validity of the allegation in respect to timeliness and merits." ("Falta de manos limpias de los Demandantes como Objeción de Jurisdicción y, subsidiariamente, de Inadmisión: Procedencia de la alegación en cuanto al tiempo y al fondo ") |
Second Hearing | A one-day hearing held at the International Dispute Resolution Centre Ltd (IDRC) in London on 27 February 2020. |
Second Investment Plants | Jointly, the Fontanellas and Lasesa Plants |
SES | Spanish Electricity System |
Special Regime | Chapter II of the 1997 Electricity Law, which covers electricity generators from non-consumable renewable energies, carried out in power plants with an installed capacity that does not exceed 50 MW |
TMR | "tarifa media de referencia" or average electricity tariff fixed by the Spanish Government on an annual basis |
Tordesillas Plants | PV installations acquired by Claimants from OPDE Investment España S.L., a Spanish-incorporated company, through Tordesillas Solar, S.A. (Spanish entity) via its ten subsidiaries, Tordesillas Solar FV 1, S.L. to Tordesillas Solar FV 10, S.L. |
Tr. Day [#], [page:line] [Speaker(s)] | Transcript of the Hearing |
Tribunal | Arbitral tribunal constituted on 24 October 2017 |
TVPEE | "Impuesto sobre el valor de la producción de energía eléctrica", a 7% tax introduced by Law 15/2012, levied on "the total amount that corresponds to the tax payer for the production of electricity and its incorporation into the electricity system, measured at power station bus bars, for each facility, in the tax period." |
TVPEE Objection | Objection made by Respondent to the jurisdiction of the Tribunal to hear Claimants' claim for breach of Article 10(1) deriving from Spain's introduction of the TVPEE in Law 15/2012, arguing that, pursuant to Article 21 of the ECT, Article 10(1) does not apply to tax measures |
UNFCCC | United Nations Framework Convention on Climate Change of 1992 |
Valtierra I & II Plants | PV installations acquired by Claimants from Valsingula S.L. (Spanish-incorporated company) via Promociones Fotovoltaicas Azara, S.L.U. and Promociones Fotovoltaicas Articulata, S.L.U. |
Valtierra III Plants | PV installations acquired by Claimants from Valsingula S.L. (Spanish-incorporated company) via Promociones Fotovoltaicas Daphne, S.L.U., Promociones Fotovoltaicas Retama, S.L.U. and Promociones Fotovoltaicas Faginea, S.L.U. |
This case concerns a dispute submitted to the International Centre for Settlement of Investment Disputes ("ICSID" or the "Centre") on the basis of the Energy Charter Treaty which entered into force on 16 April 1998, for Spain, Luxembourg and the Netherlands (the "ECT") and the Convention on the Settlement of Investment Disputes between States and Nationals of Other States, dated 14 October 1966 (the "ICSID Convention").
On 29 June 2016, the Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified the Parties of the registration. In the Notice of Registration, the Secretary-General invited the Parties to proceed to constitute an arbitral tribunal as soon as possible in accordance with Rule 7(d) of ICSID's Rules of Procedure for the Institution of Conciliation and Arbitration Proceedings.
Tribunal:
Dr. José Emilio Nunes Pinto President
Prof. Peter D. Cameron Arbitrator
Mr. Luis González García Arbitrator
ICSID Secretariat:
Mrs. Mercedes Cordido-Freytes de Kurowski Secretary of the Tribunal
For Claimants:
Counsel:
Mr. Jeffrey Sullivan Gibson, Dunn & Crutcher UK LLP
Ms. Sarah Wazen Gibson, Dunn & Crutcher UK LLP
Ms. Nadia Wahba Gibson, Dunn & Crutcher UK LLP
Mr. Antonio Vázquez-Guillén Allen & Overy LLP (Madrid)
Mr. David Ingle Allen & Overy LLP (Madrid)
Ms. Millicent Domínguez Allen & Overy LLP (Madrid)
Parties:
Mr. Martin Lennon Infracapital
Mr. Mathieu Lief Infracapital
Mr. Nikolaus Roessner Infracapital
Experts:
Mr. Carlos Lapuerta The Brattle Group
Mr. Richard Caldwell The Brattle Group
Mr. José Antonio García The Brattle Group
Ms. Sara Vojvodic The Brattle Group
Ms. Annika Opitz The Brattle Group
For Respondent:
Counsel:
Mr. José Manuel Gutiérrez Delgado Abogacía General del Estado
Ms. Ma José Ruiz Sánchez Abogacía General del Estado
Mr. Rafael Gil Nievas Abogacía General del Estado
Ms. Alicia Segovia Marco Abogacía General del Estado
Mr. Alberto Torró Molés Abogacía General del Estado
Mr. Mariano Rojo Pérez Abogacía General del Estado
Ms. Gloria de la Guardia Limeres Abogacía General del Estado
Experts:
Mr. Gervase MacGregor BDO
Mr. Eduardo Pérez BDO
Mr. Javier Espel BDO
Mr. David Mitchell BDO
Mr. Manuel Vargas BDO
Mr. Adam Cuthbertson BDO
Ms. Susan Blower BDO
Court Reporters:
Mr. Trevor McGowan English Court Reporter
Ms. Elizabeth Cicoria Spanish Court Reporter
Ms. Luciana Sosa Spanish Court Reporter
Interpreters:
Mr. Jesus Getan Bornn English-Spanish Interpreter
Ms. Amalia Klemm-Thaler English-Spanish Interpreter
Ms. Luciana Sosa English-Spanish Interpreter
On behalf of Claimants:
Witnesses:
Mr. Mathieu Lief Infracapital
Mr. Nikolaus Roessner Infracapital
Experts:
Mr. Carlos Lapuerta The Brattle Group
Mr. Richard Caldwell The Brattle Group
Mr. José Antonio García The Brattle Group
On behalf of Respondent:
Experts:
Mr. Gervase MacGregor BDO
Mr. David Mitchell BDO
On 12 September 2019, Respondent filed a proposal for disqualification of arbitrator Dr. José Emilio Nunes Pinto. The proceeding was suspended in accordance with ICSID Arbitration Rule 9(6).
Tribunal:
Mr. Eduardo Siqueiros T. President
Prof. Peter D. Cameron Arbitrator
Mr. Luis González García Arbitrator
ICSID Secretariat:
Mrs. Mercedes Cordido-Freytes de Kurowski Secretary of the Tribunal
For Claimants:
Mr. Jeffrey Sullivan Gibson, Dunn & Crutcher UK LLP
Ms. Sarah Wazen Gibson, Dunn & Crutcher UK LLP
Ms. Nadia Wahba Gibson, Dunn & Crutcher UK LLP
Mr. Antonio Vázquez-Guillén Allen & Overy LLP (Madrid)
Mr. David Ingle Allen & Overy LLP (Madrid)
Ms. Millicent Domínguez Allen & Overy LLP (Madrid)
Ms. Joanne Horridge Infracapital
Ms. Sara Vojvodic The Brattle Group
For Respondent:
Mr. José Manuel Gutiérrez Delgado Abogacía General del Estado
Ms. María del Socorro Garrido Moreno Abogacía General del Estado
Mr. Rafael Gil Nievas Abogacía General del Estado
Mr. David Mitchell BDO
Court Reporters:
Mr. Trevor McGowan English Court Reporter
D-R Estreno Spanish Court Reporter
Interpreters:
Mr. Juan María Pérez English-Spanish Interpreter
Ms. Marta Buján English-Spanish Interpreter
Ms. Pilar Fernández English-Spanish Interpreter
I recently learned that in an non-ICSID investor-State arbitration case, administered by the ICC, where I had been appointed by Claimant, Respondent has designated Dr. José Emilio Nunes Pinto as arbitrator. I don't believe that this circumstance affects my independence and impartiality to serve as an arbitrator in this case, but I nevertheless wish to disclose it in the abundance of caution.
No observations were filed by the Parties in this regard.
"4. [...] the production of electrical energy from non-hydro renewable energy, biomass as well as that generated by hydroelectric plants, with an operating power capacity equal or inferior to 10MW shall be subsidised with a premium established by the Government whereby the price of electricity sold by these plants shall fall into a percentage category between 80 and 90 percent of an average electricity price; this shall be calculated by dividing the revenue collected from the supply of electrical energy by the energy supplied. The items to be used in calculating said price shall be determined without the Value Added Tax and free of any other tax that might levy electrical energy consumption.
To work out the premiums, the voltage level on delivery of the power to the network, the effective contribution to environmental improvement, to primary energy saving and energy efficiency, the generation of economically justifiable useful heat and the investment costs incurred shall all be taken into account so as to achieve reasonable profitability rates with reference to the cost of money on capital markets."15
"There is no legal obstacle that exists to prevent the Government, in the exercise of the regulatory powers and of the broad entitlements it has in a strongly regulated issue such as electricity, from modifying a specific system of remuneration."34
"""..." electricity producers under the special regime do have an "unalterable right" to remain in an unchanged economic regime governing the collection of premiums. The scheme is, in fact, to encourage the use of renewable energy through an incentive mechanism, like all of this genre, and cannot be guaranteed to remain unchanged in the future".
"(...) the payment regime under examination does not guarantee to special regime electricity producers that a certain level of profits or revenues will be unchanged relative to those obtained in previous years, or that the formulas for fixing the premiums will stay unchanged."38
"The future application of the new special regime for the production of electricity to all facilities, including those already existing that already enjoy the tariffs, Premium, incentives and complements of the prior regime does not imply the loss of acquired or patrimonialized rights.41
[...] ... the proposed Royal Decree in terms of this criteria is positive, given that, firstly, remuneration is substantially increased for energies and technologies that are further away from the planning targets (biomass, biodigestion biogas, photovoltaic and thermoelectric solar power, and cogeneration)."42
"[...] (b) Minimising regulatory uncertainty. The [CNE] understands that transparency and predictability in the future of economic incentives reduces regulatory uncertainty, incentivising investments in new capacity and minimizing the cost of financing projects, thus reducing the final cost to the consumer. The regulation must offer sufficient guarantees to ensure that the economic incentives are stable and predictable throughout the service life of the facility."43
"[A]lthough the growth seen overall in the special regime for electricity generation has been outstanding, in certain technologies the targets posed are still far from being reached.
From the point of view of compensation, the business of the production of electrical energy under the special regime is characterised by the possibility that the compensation system can be supplemented by the receipt of a premium under the terms and conditions established in the regulations, in order to determine which such factors as the voltage level of the energy delivered into the grid, the contribution to the improvement in the environment, primary energy saving, energy efficiency, and the investment costs incurred, may all be taken into account."45
"... facilities for the production of electrical energy under the special regime shall be subject to compulsory registration in Section Two of the Public Authority Register of facilities for the production of electrical energy indicated in Article 21.4 of Law 54/1997, which is a part of the Ministry of Industry, Tourism, and Trade. Section Two of the Public Authority Register indicated above shall hereinafter be known as the Public Authority Register for production facilities under the Special Regime."49
• "[s]ell the electricity to the system through the transport or distribution grid, receiving for it a regulated tariff, which shall be the same for all scheduling periods expressed in Euro cents per kilowatt/hour;" (the FIT) or
• "[s]ell the electricity in the electrical energy production market" at "the price obtained in the organised market or the price freely negotiated by the proprietor or the representative of the facility, supplemented where appropriate by a premium, in Eurocents per kilowatt/hour."50
"[...] The values of the tariffs, premiums, supplements, and lower and upper limits to the hourly price of the market as defined in this Royal Decree, for Category b) [...] shall be updated on an annual basis using as a reference the increase in the CPI less the value set out in the Additional Provision One of the present Royal Decree."53
"During the year 2010 ... there shall be a review of the tariffs, premiums, supplements and lower and upper limits defined in this Royal Decree with regard to the costs associated with each of these technologies, the degree of participation of the special regime in covering the demand and its impact upon the technical and economic management of the system, and a reasonable rate of profitability shall always be guaranteed with reference to the cost of money in the capital markets. Subsequently a further review shall be performed every four years, maintaining the same criteria as previously.
The revisions to the regulated tariff and the upper and lower limits indicated in this paragraph shall not affect facilities for which the deed of commissioning shall have been granted prior to 1 January of the second year following the year in which the revision shall have been performed."54
"b) Legal security and protection of legitimate expectations. Stability and predictability of economic incentives (tariffs and premiums) reduce regulatory uncertainty, which encourages investments in new capacity to address their projects, while minimizing the cost of financing and thereby reducing the final cost to the consumer. The current regulation has established annual updates of economic incentives, based on robust indexes (such as the IPC, ten-year bonds, etc.), and periodic reviews every four years, which in this case only affect the new facilities.
Certainly, the principles of legal certainty and the protection of legitimate expectations (Article 9.3 EC) do not constitute insurmountable obstacles to the innovation of the legal system and cannot therefore be used as instruments to petrify the legal framework in force at any given time. In this sense, these principles do not prevent the dynamic innovation of the regulatory frameworks, nor of new normative provisions which can be applied pro-future to situations initiated before it comes into force. But these principles do require that regulatory innovation - especially if it is abrupt, unforeseeable or unexpected - is carried out with certain guarantees and cautions (transitional periods to adapt to the new regimes, where appropriate compensatory measures, etc.) that dampen, moderate and minimize, as far as possible, the disappointing of any expectations generated by the previous regulations."61
"... The growth of installed capacity experienced by photovoltaic solar technology has been much greater than expected.
... It has become necessary to provide continuity and expectations to these investments, as well as to establish progressive guidelines for the implementation of this type of technology, which, in addition, can contribute to achieving the goals of the 2005-2010 Renewable Energy Plan and those set in the new 2011-2020 Renewable Energy Plan, based on the objectives assigned to Spain in the new Renewable Energy Directive. Therefore, it has been determined that it would be appropriate to raise the current goal of 371 MW of installed capacity connected to the network, set in Royal Decree 661/2007 of May 25, 2007.
To that end, it has been proposed that an annual output target be set which will evolve upwards in coordination with technological advancements instead of using the total accumulated power to set the market limits for this technology. This must be accompanied by a new economic arrangement which stimulates the long-term technological development and competitiveness of photovoltaic facilities in Spain.
... Just as insufficient compensation would make the investments nonviable, excessive compensation could have significant repercussions on the costs of the electric power system and create disincentives for investing in research and development, thereby reducing the excellent medium-term and long-term perspectives for this technology. Therefore, it is felt that it is necessary to rationalize compensation and, therefore, the royal decree that is approved should modify the economic regime downward, following the expected evolution of the technology, with a long-term perspective."63
"4. The Government is empowered to amend the provisions of paragraph 2 by Royal Decree to adjust it to technological developments. Any amendments shall only affect the facilities that are not in operation at the time said Royal Decree enters into force, which will be considered to be the date that they are enrolled in the register of pre-allocation of payment for photovoltaic facilities."89
"as a matter of urgency, a series of measures that are balanced, proportionate and wide-ranging, aimed at ensuring the financial stability of the electricity system as indispensable premise of its economic sustainability and the security of its supply, and addressed at all the activities of the electricity sector."98
"shall focus, before taxes, on the average yield in the secondary market for ten years prior to the entry into force of this Royal Decree-Law of the Obligations of the State within ten years increased by 300 basic points, without prejudice to the revision envisaged in the last paragraph of that article."102
"[E]nter an Award in their favour and against Spain as follows:
(a) declaring that Spain has violated Article 10 of the ECT, as well as its obligations under the applicable rules and principles of international law;
(b) requiring that Spain make full reparation to the Claimants for the injury or losses to their investments arising out of Spain's violations of the ECT and international law, by way of:
(i) full restitution to the Claimants by reinstating the legal and regulatory framework in place at the time the Claimants made their investments in its territory and compensating the Claimants for their losses suffered prior to such reinstatement; or
(ii) full compensation to the Claimants for all losses suffered by them as a result of Spain's violations of the ECT and international law, in an amount to be determined, including interest on all amounts awarded at a reasonable rate;
(c) directing Spain to pay all costs incurred in connection with these arbitration proceedings, including the costs of the arbitrators and ICSID, as well as the legal and other expenses incurred by the Claimants, including but not limited to the fees of their legal counsel, experts and consultants and those of the Claimants' own employees, on a full indemnity basis, plus interest thereon at a reasonable rate;
(d) directing Spain to pay post-award interest, compounded monthly, on the amounts awarded until full payment thereof; and
(e) any other relief that the Arbitral Tribunal may deem appropriate in the circumstances."132
"In view of the arguments put forward in its Memorials, during the Hearings and in the PHB, the Kingdom of Spain respectfully requests that the Arbitral Tribunal:
a) Declares its lack jurisdiction regarding two EU Claimants' claims due to the lack of notice of controversy and lack of a Claimants' good faith attempt to seek an amicable solution;
b) Declares its lack of jurisdiction due to the lack of clean hands in the Claimants as it is evidenced that they committed gross wrongdoings in their investment;
c) Declares its lack of jurisdiction due to the intra-EU objection;
d) Declares its lack of jurisdiction regarding the 50% of the Lasesa plants are they were subject to anew negotiation and agreement freely executed by the Claimants after the Disputed Measures;
e) Declares its lack of jurisdiction regarding the TVPEE;
f) In the event that the Tribunal were to decide that it has jurisdiction to hear this all or part of the controversy, it rejects all the claims of the Claimants on the merits, since (i) we are in front of an investment made with no clean hands and (ii) in front of an improperly fabricated claim that has no actual merits and, (iii) in any case, the Kingdom of Spain has not breached in any way, the ECT.
g) Secondarily, dismisses all of the compensation claims of the Claimants in as much as they do not have a right to compensation; and
h) Orders the Claimants to pay all costs and expenses derived from this arbitration, including ICSID administrative expenses, arbitrators' fees, and the arbitrators' fees and the fees of the legal representatives of the Kingdom of Spain, their experts and advisers, as well as any other cost or expense that has been incurred, all of this including a reasonable rate of interest from the date on which these costs are incurred and the date of their actual payment."
Respondent argues that the Tribunal must apply Article 20 of the Treaty on the Functioning of the EU ("TFEU") to determine the nationality of EU investors.143 Pursuant to Article 20 of the TFEU, Respondent contends that "all citizens of a Member State, whether natural or legal persons, simultaneously hold European nationality. This nationality is concurrent and does not exclude the nationality of the Member State to which it belongs."144
Respondent draws support for this argument from the award in Terra Raf Trans v. Kazakhstan, where the tribunal held that the ECT was applicable to Gibraltar because it is part of the EU, which itself is a party to the ECT.150
Claimants contend that, had the Contracting Parties to the ECT desired to exclude intra-EU disputes from the scope of Article 26, they would have included an exception to that effect; but they did not. And this has been acknowledged by other tribunals. It adds that the "[...] objection has [...] been dismissed by all investment treaty tribunals and national courts seized of this objection, including ECT tribunals in cases involving Spain itself, such as the RREEF decision, the Eiser award and, more recently, Antin, Novenergia, Masdar and Greentech" and, add, that the fact that "Spain is persisting with a jurisdictional objection that has never succeeded is remarkable and should, in the Claimants' view, have cost consequences."158
"(1) Disputes between a Contracting Party and an Investor of another Contracting Party relating to an Investment of the latter in the Area of the former, which concern an alleged breach of an obligation of the former under Part III shall, if possible, be settled amicably.
(2) If such disputes cannot be settled according to the provisions of paragraph (1) within a period of three months from the date on which either party to the dispute requested amicable settlement, the Investor party to the dispute may choose to submit it for resolution:
(a) to the courts or administrative tribunals of the Contracting Party to the dispute;
(b) in accordance with any applicable, previously agreed dispute settlement procedure; or
(c) in accordance with the following paragraphs of this Article.
(3) (a) Subject only to subparagraphs (b) and (c), each Contracting Party hereby gives its unconditional consent to the submission of a dispute to international arbitration or conciliation in accordance with the provisions of this Article. [...]159" (Emphasis added)
"Article 31. General Rule of Interpretation
1. A treaty shall be interpreted in good faith in accordance with the ordinary meaning to be given to the terms of the treaty in their context and in the light of its object and purpose"160. (Emphasis added)
First, contrary to natural persons, legal persons such as Claimants cannot have the nationality of the EU, in addition to that under which laws they have been established. Article 20 of the TFEU165 provides for European nationality only in respect to natural persons. Not juridical entities. When this provision allocates the European citizenship, it does so in the context of the grant of rights to individuals, such as the right to vote and stand as a candidate, which is incompatible with legal persons.166 It is therefore without merit to argue that this article also grants the European citizenship to legal entities established with the nationality of a Member State.
"[...] According to settled case-law of the Court, the autonomy of EU Law with respect both to the law of the Member States and to international law is justified by the essential characteristics of the EU and its law, relating in particular to the constitutional structure of the EU and the very nature of that law. EU Law is characterized by the fact that it stems from an independent source of law, the Treaties, by its primacy over the laws of the Member States, and by the direct effect of a whole series of provisions which are applicable to their nationals and to the Member States themselves. Those characteristics have given rise to a structured network of principles, rules and mutually interdependent legal relations binding the EU and its Member States reciprocally and binding its Member States to each other.
"[...] EU Law is thus based on the fundamental premise that each Member State shares with all the other Member States, and recognises that they share with it, a set of common values on which the EU is founded, as stated in Article 2 TEU. That premise implies and justifies the existence of mutual trust between the Member States that those values will be recognised, and therefore that the law of the EU that implements them will be respected. It is precisely in that context that the Member States are obliged, by reason inter alia of the principle of sincere cooperation set out in the first subparagraph of Article 4(3) TEU, to ensure in their respective territories the application of and respect for EU Law, and to take for those purposes any appropriate measure, whether general or particular, to ensure fulfilment of the obligations arising out of the Treaties or resulting from the acts of the institutions of the EU."175
According to Respondent, the application of EU Law as international law under Article 26 of the ECT has also been recognised by tribunals in investment arbitration.176 Respondent cites in support of its argument the awards in Electrabel v. Hungary and Blusun v. Italy.177 Spain further refers to the award in Mr. Jurgen Wirtgen, Mr. Stefan Wirtgen, Ms. Gisela Wirtgen and JSW Solar (zwei) GmbH & Co. KG v. Czech Republic of 11 October 2017, and argues that it "does not apply to the ECT, but [...] the Arbitral Tribunal concluded that EU Law was International Law applicable to the dispute under the principle of proximity enshrined in Article 31.3 of the Vienna Convention."178
"any compensation which an Arbitration Tribunal were to grant to an investor on the basis that Spain has modified the premium economic scheme by the notified scheme would constitute in and of itself State aid. However, the Arbitration Tribunals are not competent to authorize the granting of State aid. That is an exclusive competence of the Commission. If they award compensation, such as in Eiser v. Spain, or were to do so in the future, this compensation would be notifiable State aid pursuant to Article 108(3) TFEU and be subject to the standstill obligation.
[...] Finally, the Commission recalls that this Decision is part of Union Law, and as such also binding on Arbitration Tribunals, where they apply Union Law. The exclusive forum for challenging its validity are the European Courts."184
Reference is also made by Respondent to Opinion 2/13 in which, inter alia, the CJEU (i) observed that the submission of an application to the control mechanisms of the Convention for the Protection of Human Rights and Fundamental Freedoms and the European Court of Human Rights ("ECHR") was liable in itself to undermine the autonomy and primacy of EU Law; and (ii) found an infringement of Article 344 TFEU pursuant to the draft accession agreement to the ECHR, since EU Member States were able to bring proceedings before the ECHR against each other or the EU for alleged breaches of the ECHR when implementing EU Law.189
"Articles 267 and 344 TFEU must be interpreted as precluding a provision in an international agreement concluded between Member States., under which an investor from one of those Member States may, in the event of a dispute concerning investments in the other Member State, bring proceedings against the latter Member State before an arbitral tribunal whose jurisdiction that Member State has undertaken to accept."192
"the arbitration clause of the ECT excludes disputes between an investor and a Member State of the EU from the jurisdiction of their own Courts. Thus, following the reasoning of the Judgment as regards preliminary judgments, it prevents these disputes, to which Community Law must be applied, from being resolved in a manner that guarantees the full enforceability of EU Legislation, as required by article 344 TFEU."196
Respondent takes the view that the principle that arbitral tribunals established under the ECT are not part of the EU judicial system for the purposes of Article 267 TFEU is recognised by numerous tribunals, including the decisions in Blusun v. Italy and Eiser v. Spain.200
In support of its position, Spain notes that the Svea Court of Appeal in Stockholm has "welcomed" this position in its stay of enforcement decision of the Novenergia award.204
For Respondent, Article 1.3 of the ECT definition of an Regional Economic Integration Organization ("REIO") implies that matters such as fundamental freedoms and State Aid should be negotiated by the EU because its Member States do not have competence over them, and therefore, could never grant consent to submit such matters to arbitration.211 Spain cites as support Article 25 of the ECT, which provides that the obligation to accord most-favoured-nation treatment ("MFN") does not oblige a Contracting Party to an Economic Integration Agreement ("EIA") to grant preferential treatment to investors that are not part of the EIA.212 The primacy of EU Law is also recognised in Articles 1(3) and 36(7) of the ECT.213
• the judgment itself makes clear that it applies only to a treaty concluded by Member States, not the EU, and the case related to a BIT concluded between the Netherlands and Slovakia before Slovakia became a Member State;
• the applicable choice of law at issue in Achmea is considerably different from that of Article 26(6) if the ECT and, contrary to Spain's assertion, the Tribunal is not called upon to apply EU Law but rather, the ECT and customary international law;
• the question referred to the CJEU in Achmea, whether the Netherlands-Slovakia BIT provisions were compatible with the TFEU, has no relevance in this arbitration as the Netherlands and Luxembourg had already acceded to the EU when they ratified the ECT;
• the present dispute has been brought before an ICSID tribunal whereas the arbitral tribunal in Achmea was subject to German law provisions and EU Law arguments have no place within the ICSID framework; and
• this Tribunal's jurisdiction derives from the ECT provisions and is not bound by the decisions of European institutions.262
For Claimants, the protection of EU Member States' nationals offered by EU Law is different from that of the ECT, in that only the ECT allows investors to bring a direct claim against Contracting States through international arbitration.288 Because of those additional rights under the ECT, there can be no conflict between the ECT and EU Law.289 Claimants refer to the decisions in Novenergia, Electrabel, Eastern Sugar, Charanne, RREEF and Vattenfall to contend that EU Law and the ECT coexist without interfering with each other.290
"The ECT's purpose does not support the Respondent's interpretation. Article 2, captioned 'Purpose of the Treaty', declares that '[t]his Treaty establishes a legal framework in order to promote long-term co-operation in the energy field, based on complementarities and mutual benefits, in accordance with the objectives and principles of the Charter.' [...] Nothing in this wording suggests the exclusion of claims by investors who are nationals of an EU Member State who is also a party to the ECT against another EU Member State. Moreover, such context does not call into question the ordinary meaning of Article 26."307
"If the arbitration clause, which is at the very heart of the Treaty to which the EU consented, were to exclude the variety of treaties and legislation mentioned by Spain, then the EU, which the Tribunal must assume acted in good faith when it negotiated and signed the ECT, would have, under international law, provided a formal warning, or an express exclusion or a reserve."308 (Emphasis added)
"an international tribunal lacks ratione temporis jurisdiction in cases in which an investor not protected by a certain BIT restructures their investment for the purpose of being included within the scope of application of said BIT, on a date after the dispute arises against the State receiving the investment."327
• "02/06/2010: Investment in the photovoltaic plants of Tordesillas, Valtierra I, II and III
• 8=6[sic]/2011: Investment in the Fontellas and Lasesa plants
• 19/12/2011: Announcement of the reform on the SES by the Prime Minister in his inaugural address.
• 28/12/2011: CNE press release which reiterates the need to implement immediately, inter alia, proposals on the regulation of activities aimed at eliminating the structural deficit of the system and mitigating debt financing costs.
• 27/01/2012: Publication of RD-Act 1/2012, which suspended the remuneration pre-assignment procedures and the elimination of the economic incentives for new electric energy production plants based on cogeneration, renewable energy sources, and waste.
• 07/03/2012: CNMC report on 'Measures to guarantee the financial-economic sustainability of the electricity sector.': in which short-term measures are recommended (materialised in RD-Act 2/2013). Birth of the dispute.
• 30/3/2012: The Council of Ministers approved Royal Decree Act 13/2012 on Measures for correcting deviations due to imbalances between costs and revenues of the electricity and gas sectors, which is enacted as a first step towards a 'profound reform of the energy system'.
• 27/4/2012: The Government approved the 'National Reform Program 2012' which reaffirms the commitment of the Kingdom of Spain to eliminate the tariff deficit.
• 13/7/2012: Royal Decree-Act 20/2012, of 13 July, on measures to ensure budget stability and promote competitiveness, was enacted, stating in its eighth provision: 'The tariff deficit caused by the imbalances between the costs of the electricity system and the income obtained from the regulated prices set by the General State Administration is a structural problem whose solution is urgent because of the threat it poses to the system's economic sustainability'
• 20/07/2012: The Kingdom of Spain signed the Memorandum of Understanding with the European Union as a result of the need that certain Spanish banks had for a bailout. Said Memorandum links the financial situation with other macroeconomic imbalances and commits the Kingdom of Spain to adopt structural reform measures to correct these imbalances.
• September 2012: the Government published another document 'The reforms of the Government of Spain: Determination against the crisis'. In the chapter entitled 'Planned reforms', it refers to the 'Reform of the energy sector'.
• 27/09/2012: The Government approved in the Spanish Cabinet Meeting Decision the 'Draft Act on State Budgets for 2013'. In that Cabinet Meeting the 'Spanish Strategy for Economic Policy' was also approved: Assessment and structural reforms over the next six months'. In this Strategy the 'Energy reform' was mentioned and structural measures were announced to correct the tariff deficit permanently, as well as the presentation of a new Electricity Sector Act, to address inefficiencies that were detected.
• 27/12/2012: Act 15/2012 on fiscal measures for energy sustainability is approved, as a first measure for the reforms on the Electricity Sector, which had an impact on renewable energies. First measure appealed, in execution of the short-term measures included in the CNE's 7 March 2012 report.
• 1/2/2013: the Government of Spain approved two more of the short-term measures recommended by the CNMC Report112, on 7 March 2012, through the publication of Royal Decree-Act 2/2013113: (i) the replacement with effect of the Consumer Price Index that governed the adjustment of the remunerations, fees and premiums of the electricity sector's activities, among them, the production of renewable energy, by the Consumer Price Index to constant taxes without food not elaborated or energy products and, (ii) the reduction of the premium amount to a value of €0 in the pool option plus premium provided for in Royal Decree 661/2007. 19/03/2013.
• 11/4/2013: the document of the 2013 National Reform Plan is published, in which (i) the same date expected for publishing the Reform is again stated, on 30 June of the same year, (ii) that the package of Measures provided for a preliminary draft bill for the reform of Act 54/1997 and (iii) that mechanisms to review the remuneration will be introduced: '... Before June 30 of this year, a package of regulatory measures will be presented... Preliminary Draft Bill for the Reform of Law 54/1997..., that introduces remuneration stabilisation and revision mechanisms periodically and adapted to the circumstances'.
• 12/7/2013: RD-Act 9/2013, of July 12, is approved. Urgent measures to guarantee the financial stability of the electricity system, the first measure and core issue of this dispute.
• January 2014: Investment of the remaining 50% of the Lasesa plant"338
They contest Spain's presentation of the chronology of events, arguing that Spain's measures post-date Claimants' investments, which were made between March and October 2011.341 In their Reply, Claimants include their own timeline of events, highlighting the Disputed Measures in shaded text below:342
Date | Event |
Spain 2009 | The Claimants begin looking at investment opportunities in Spain. |
January/February 2010 | The Claimants commence due diligence on the First Investment Plants. |
March 2010 | Rumours of potential rumours [sic] change to the RE framework emerge. |
Mid-April 2010 | Rumours of possible regulatory change to the RE framework intensify. |
9 April 2010 | The Claimants meet with the CNE. The CNE indicates that there is no risk of retroactive amendment to the tariffs for existing PV plants and emphasizes the important of stability in the economic regime. |
2 June 2010 | The Claimants sign conditional SPAs for the acquisition of the First Investment Plants. The closing of the SPAs is contingent upon certain Regulatory Conditions. |
21 December 2010 | The Claimants pay the sellers a portion of the price of the First Investment Plants, subject to the right to unwind. |
21 February 2011 | The Claimants meet with the Ministry of Energy. A representative of Ministry reassures the Claimants that no further retroactive changes to the regulatory regime for PV plants are planned. |
March 2011 | The parties complete the transactions under the SPAs in relation to the First Investment Plants. |
22 June 2011 | The Claimants acquire the Fontellas Plants. |
18 October 2011 | The Claimants acquire 50% of the Lasesa Plants. The Claimants enter into put/call option agreements for the remaining 50% with the sellers, Dalkia/Forcimsa binding them to acquire the remaining 50% at Dalkia's request. |
27 December 2012 | Spain enacts Law 15/2012 (entry into force on 1 January 2013). |
1 February 2013 | Spain enacts RDL 2/2013. |
12 July 2013 | Spain enacts RDL 9/2013. |
December 2013 | Dalkia/Forcimsa communicate their intention to exercise the Put Option for the remaining 50% shares in Lasesa. |
26 December 2013 | Spain enacts Law 24/2013. |
29 January 2014 | The Claimants acquire the remaining 50% of the Lasesa Plant as required under the Put Option signed in October 2011. |
6 June 2014 | Spain enacts RD 413/2014. |
16 June 2014 | Spain enacts the June 2014 Order. |
• The TVPEE is a tax of general application, covering both renewable and conventional energy production facilities.381
• The TVPEE does not discriminate against RE producers in terms of "repercussion," that is, the possibility to transfer the amount of the tax by the payer to another person.382 The TVPEE is a direct tax, which means that there is no "legal repercussion" of its amount. 383 There is also no discrimination from the perspective of the "economic repercussion"384 This is because the costs of this tax are remunerated to RE producers under the applicable regulatory regime.385
• Spain's conduct reveals that the TVPEE was intended as a tariff cut. By applying the TVPEE to all revenues generated by the plants, the measure is equivalent to a tariff cut because (i) the PV plants operate under a regulated regime and they have no choice but to absorb the decrease in those revenues; and (ii) the cost of paying the tax is higher for RE facilities.397
• The TVPEE is discriminatory and unrelated to its official aim. If the measure adopted applies to all electricity installations but has the effect of unfairly targeting a particular sector, the measure cannot be in good faith.398 Spain has also not provided any link between the TVPEE and its professed aim for benefitting the environment.399
• The TVPEE is a Government scheme to dismantle the economic regime under RD 1578/2008 through which Claimants invested.400 For Claimants, the TVPEE is part of a series of interconnected measures that deprived them of the economic regime under RD 1578/2008.401
"7. For the purposes of this Article:
a) The term "taxation measure " includes:
i) Any provision relating to taxes of the domestic law of the Contracting Party or of a political subdivision thereof or a local authority therein; and
ii) any provision relating to taxes of any convention for the avoidance of double taxation or of any other international agreement or arrangement by which the Contracting Party is bound"407 (Emphasis added)
"Article 1. Nature. The tax on the value of the production of electric energy is a tax of direct character and real nature that taxes the performance of activities of production and incorporation into the electric system of electric energy, measured in power plant busbars, through each of the facilities indicated in Article 4 of this Law" (Emphasis added)
"Article 2. Concept, purposes and types of taxes:
1. The taxations are public revenue consisting in cash entitlements required by public Tax Authorities as a consequence of those qualifying conditions which the Law associates to the duty to contribute to the primary purpose of obtaining the revenue needed to sustain public expenses.
These taxations besides being means to obtain the necessary resources for sustaining public e