AIA | Integrated Environmental Authorisation (Autorizazzione Integrata Ambientale) |
Arbitration Rules | ICSID Rules of Procedure for Arbitration Proceedings 2006 |
ECT | Energy Charter Treaty |
C-[#] | Claimants' Exhibit |
CJEU | Court of Justice of the European Union |
Cl. Memorial on Jurisdiction, Liability, and Quantum or Memorial | Claimants' Memorial on Jurisdiction, Liability, and Quantum dated 22 December 2017 |
Cl. Observations on Vattenfall | Claimants' Observations on the Vattenfall Tribunal Decision on the Achmea Issue dated 4 October 2018 |
Cl. PHB on the Declaration | Claimants' Post Hearing Brief dated 4 March 2019 |
Cl. PHB | Claimants' Post-Hearing Brief dated 11 October 2019 |
Cl. Rejoinder on the Intra-EU Jurisdictional Objection | Claimants' Rejoinder on Respondent's Objections to Jurisdiction under Article 41(1) of the Arbitration Rules dated 1 June 2018 |
Cl. Reply Memorial | Claimants' Reply Memorial on Jurisdiction, Liability, and Quantum dated 24 October 2018 |
Cl. Response on the Intra-EU Jurisdictional Objection | Claimants' Response on Respondent's Objections to Jurisdiction under Article 41(1) of the Arbitration Rules dated 4 May 2018 |
CL-[#] | Claimants' Legal Authority |
Declaration | Declaration of the Representatives of the Governments of the Member States, of 15 January 2019 on the Legal Consequences of the Court of Justice in Achmea and on Investment Protection in the European Union |
EIA | Environmental Impact Assessment |
Hearing | Hearing on Jurisdiction and Merits held from 4 to 8 February 2019 |
ICSID Convention | Convention on the Settlement of Investment Disputes Between States and Nationals of Other States, which entered into force on 14 October 1966 |
ICSID or the Centre | International Centre for Settlement of Investment Disputes |
Medoilgas Italia | Medoilgas Italia S.p.A. (formerly, Intergas Più S.r.L.), MOG's wholly owned subsidiary |
MOG | Mediterranean Oil and Gas Plc |
October Hearing | Hearing on Post-Hearing Briefs held in Paris on 30 October 2019 |
R-[#] | Respondent's Exhibit |
Request for Arbitration | Request for Arbitration dated 14 April 2017 |
Resp. Counter-Memorial | Respondent's Counter-Memorial dated 15 May 2018 |
Resp. Intra-EU Jurisdictional Objection | Respondent's Objection to Jurisdiction under Article 41(1) of the Arbitration Rules dated 28 March 2018 |
Resp. Observations on Vattenfall | Respondent's Observations on the Vattenfall Tribunal Decision on the Achmea Issue dated 4 October 2018 |
Resp. Observations on Masdar | Respondent's Brief Commentary over Masdar and the Relevance of Achmea Decision over the current proceedings dated 11 June 2018 |
Resp. PHB on the Declaration | Respondent's Post Hearing Brief dated 28 February 2019 |
Resp. PHB | Respondent's Post-Hearing Brief dated 11 October 2019 |
Resp. Rejoinder | Respondent's Rejoinder dated 9 January 2019 |
Resp. Reply on the Intra-EU Jurisdictional Objection | Respondent's Reply on Objections to Jurisdiction under Article 41(1) of the Arbitration Rules dated 25 May 2018 |
Request for Termination | Respondent's Request for Termination of the Proceedings dated 29 January 2019 |
RL-[#] | Respondent's Legal Authority |
Tr. Day [#], [page:line] | Transcript of the Hearing |
Tribunal | Arbitral Tribunal constituted on 26 September 2017 |
VCLT | Vienna Convention on the Law of Treaties |
On 19 May 2017, the Secretary-General of ICSID registered the Request for Arbitration in accordance with Article 36(3) of the ICSID Convention and notified the Parties of the registration. In the Notice of Registration, the Secretary-General invited the Parties to constitute an arbitral tribunal as soon as possible in accordance with Rule 7(d) of ICSID's Rules of Procedure for the Institution of Conciliation and Arbitration Proceedings.
Whether or not on the date of the Request for Arbitration was there a valid offer on the part of the Respondent to arbitrate, and if the answer to that question is yes, with the consequence that an arbitration agreement came into existence as between the parties, was that arbitration agreement vitiated at a later point in time? If so, when, and how.
Tribunal:
Mr. Klaus Reichert SC President
Dr. Charles Poncet Arbitrator
Prof. Pierre-Marie Dupuy Arbitrator
ICSID Secretariat:
Ms. Marisa Planells-Valero Secretary of the Tribunal
For the Claimants:
Mr. Thomas Sprange QC King & Spalding
Mr. Viren Mascarenhas King & Spalding
Mr. Benjamin Williams King & Spalding
Ms. Flora Jones King & Spalding
Ms. Kateryna Frolova King & Spalding
Ms Pui Yee (Lisa) Wong King & Spalding
Parties:
Mr. Samuel Moody Rockhopper
Mr. Stewart MacDonald Rockhopper
Ms. Lucinda (Lucy) Williams Rockhopper
Mr. Michael (Paul) Culpin Rockhopper
Mr. Alun Griffiths Rockhopper
Mr. Mark King Harbour Litigation Funding
Mr. Dominic Afzali Harbour Litigation Funding
Mr. Joseph (Joe) Skilton Berkeley Research Group
Mr. Don Munn ERCE
Ms. Giorgia Diotallevi Ughi e Nunziante – Studio Legale
Witnesses:
Mr. Samuel Moody Rockhopper
Mr. Stewart MacDonald Rockhopper
Ms. Fiona MacAulay(Barkham) Echo Energy (formerly Rockhopper)
Mr. Roberto Leccese Ughi e Nanziante – Studio Legale
Experts:
Mr. Peter Velez Peter Velez Engineer L.L.C.
Mr. Richard Boulton One Essex Court
Mr. Tim Chapman Geopoint Advisory Limited
Mr. David Wilson ERCE
For the Respondent:
Mr. Giacomo Aiello Avvocatura dello Stato
Mr. Pietro Garofoli Avvocatura dello Stato
Mr. Andrea Giordano Avvocatura dello Stato
Ms. Laura Delbono Avvocatura dello Stato
Ms. Maria Chiara Malaguti Ministero degli Affari Esteri e della Cooperazione Internazionale - consultant
Ms. Giuditta Marra Avvocatura dello Stato – trainee
Ms Annalisa Signorelli Avvocatura dello Stato – trainee
Parties:
Gilberto Dialuce Ministero dello Sviluppo Economico
Witnesses:
Mr. Gilberto Dialuce Ministero dello Sviluppo Economico
Mr. Franco Terlizzese Ministero dello Sviluppo Economico
Mr. Mariano Grillo Ministero dell'Ambiente e della Tutela del Territorio e del Mare
Experts:
Mr. Eugenio Picozza Università Roma Tor Vergata – Emerito
Mr. Enzo Mesini Università di Bologna
Mr. Angelo Di Gregorio Università Milano Bicocca
Mr. Tiago Duarte-Silva CRA
Ms. Sharon McCollough Axis
Court Reporters:
Ms. Anne Marie Stallard Trevor McGowan
Mr. Trevor McGowan Trevor McGowan
Interpreters:
Ms. Monica Robiglio English-Italian interpreter
Ms. Daniela Ascoli English-Italian interpreter
Ms. Francesca Geddes English-Italian interpreter
Tribunal:
Mr. Klaus Reichert SC President
Dr. Charles Poncet Arbitrator
Prof. Pierre-Marie Dupuy Arbitrator
ICSID Secretariat:
Ms. Anna Toubiana Secretary of the Tribunal
For the Claimants:
Mr. Thomas Sprange QC King & Spalding
Mr. Viren Mascarenhas King & Spalding
Mr. Benjamin Williams King & Spalding
Ms. Flora Jones King & Spalding
Ms. Kateryna Frolova King & Spalding
Ms Pui Yee (Lisa) Wong King & Spalding
Mr. Kwasi Mills-Bampoe King & Spalding
Mr. Roberto Leccese Ughi e Nunziante – Studio Legale
Parties:
Mr. Samuel Moody Rockhopper
Mr. Stewart MacDonald Rockhopper
For the Respondent:
Mr. Giacomo Aiello Avvocatura dello Stato
Mr. Andrea Giordano Avvocatura dello Stato
Court Reporters:
Ms. Claire Hill Claire Hill Realtime Ltd
The Tribunal refers to the Respondent's application to add the CJEU judgment (and Opinion of the Advocate General) in C-741/19 to the file of this case, as well as to the Claimants' comments on the application. The Tribunal has decided to admit these materials, and invites the Parties to comment on them by filing consecutive submissions limited to five pages per Party. The Respondent's submission shall be received by Wednesday, September 29, 2021. The Claimants' submission shall be received by Wednesday, October 6, 2021.
On 29 September 2021, the Respondent submitted its Considerations on Republic of Moldova v. Komstroy (C-741/19) and AG Szpunar's Opinion.
The Claimants' request for relief appears in its Post-Hearing Brief as follows:7
164. For the reasons outlined above and in prior submissions, the Claimants seek an award granting the following relief:
164.1 a declaration that the Tribunal has jurisdiction to decide this dispute under the ECT and the ICSID Convention and dismissing Italy's preliminary objections to the Tribunal's jurisdiction to decide Rockhopper's claims;
164.2 a declaration that Italy has violated Part III of the ECT, including but not limited to Article 10 and Article 13, as well as international law, with respect to the Claimants' investments. Specifically, the obligations that Italy breached are:
164.2.1 the FET Standard as set out in Article 10(1) of the ECT;
164.2.2 its obligation to prevent impairment of Rockhopper's investment by unreasonable or discriminatory measures as set out in Article 10(1) of the ECT;
164.2.3 its obligation not to unlawfully expropriate Rockhopper's investment as set out in Article 13 of the ECT.
164.3 compensation to the Claimants of €281,675,391 million, comprising €275 million for lost profits and €6,675,391 for decommissioning costs;
164.4 pre- and post-award interest at 9% per annum compounded annually from 29 January 2016 until the date of Italy's final satisfaction of the award, which from 29 January 2016 to 4 February 2019 amounts to €83,792,062;
164.5 an order for Italy to reimburse all of the Claimants' costs incurred in connection with this arbitration, including fees and expenses of the arbitrators, legal counsel, witnesses, experts and consultants; and
164.6 such other relief as the arbitral tribunal deems just and proper.
The Respondent's request for relief appears in its Counter-Memorial as follows:8
In light of the above, the Respondent requests the Tribunal to:
a) Declare its lack of competence over the matter because
i. does not apply to intra-EU disputes, and
ii. prohibits the Claimants to request relief for the second time for the same dispute in front of this Tribunal for a matter already decided by domestic courts.
Should the Tribunal uphold its own jurisdiction on the claim and consider it admissible, the Respondent requests the Tribunal to:
b) Declare, on the merits, that all the claims of the Claimants under Article 10(1) and article 13 of the ECT are unfounded, and that the Respondent's conduct does not constitute a violation of such rules.
c) In the unfortunate event that the Tribunal were to uphold one of the claims of the Claimants and award some form of compensation, declare the requests for damages not supported by sufficient evidence of injury.
d) Ordering the Claimant to pay the expenses incurred by the Italian Republic in connection with these proceedings, including professional fees and disbursements, and to pay the fees and expenses of the Members of the Tribunal and the charges for the use of the facilities of the Centre, in accordance with Article 61(2) of the ICSID Convention.
Resp. Counter-Memorial, p. 86 (emphasis in original).
TO
Rockhopper Italia S.p.A.
Via Cornelia 498
00166 Rome
... ...
Subject Application for the offshore exploitation concession of liquid and gas hydrocarbon called "d30 B.C-MD". Notice of termination of procedure with subsequent rejection.
_______________________________________________________________
We would like to refer to the application for the offshore production concession of liquid and gas hydrocarbons called "d 30 B.C.-MD.", submitted by the company Rockhopper Italia S.p.A. on 18 December 2008, published in BUIG LIII-7, in order to notify the following: Law No. 208 of 28 December 2015 (2016 Law on Stability), published in the Official Gazette of the Italian Republic No. 302 of 30 December 2015, amended Article 6, paragraph 17 of Italian Legislative Decree No. 152 of 3 April 2006, laying down that: "for environmental and ecosystem purposes, (…) the research, prospection and exploitation of offshore liquid and gas hydrocarbons under Articles 4, 6 and 9 of Italian Law No. 9 of 9 January 1991 shall be forbidden within the boundaries of sea and coastal areas protected on any grounds for environmental protection purposes. Such prohibition shall also apply to sea areas up to twelve miles from the coastline around the entire Italian Peninsula and from the external perimeter of the aforementioned protected sea and coastal areas.
The relevant in-depth technical and cartographic studies carried out by the Directorate- General for the safety – including environmental safety - of mining and energy activities (UNMIG) of this Ministry have ascertained that the area subject to the application for the offshore exploitation concession of liquid and gas hydrocarbons called "d 30 B.C.-MD.", identified by the geographical coordinates included in the aforementioned application, interferes in full with the areas subject to the above-mentioned prohibition under environmental laws.
At the time these prohibitions became effective, this Administration was examining the supplementary documentation supporting the technical and economic capabilities requested by Italian Ministerial Decree of 25 March 2015 and by Directorate Decree of 15 July 2015 (Update of Standard Regulation) finally submitted by the Company on 16 December to complete the procedure downstream of the Decree on Environmental Compatibility issued on 17 August 2015 by the Minister of Environment and Protection of Land and Sea and of the Conference concluded on 9 November 2015.
In view of the above, pursuant to Article 2, paragraph 1 of Italian Law No. 241/1991, we hereby notify you of the completion of the proceeding and the rejection of the application for the offshore production concession of liquid and gas hydrocarbons called "d 30 B.C.-MD".
The abstract of this notice shall be published in the Official Hydrocarbons and Geo Resources Bulletin.
DIRECTOR-GENERAL
(1) The Claimants had a pending application (C-70) for an offshore production concession, since 2008, and this presupposes that the exploration permit stage had itself been addressed at an earlier time. Also, while the Claimants describe the period from 2008 onwards as being a "roller coaster ride" as regards how that application was dealt with by the Respondent (para. 5 of the Memorial on Jurisdiction, Liability and Quantum), factually speaking as of late 2015 they were still "in the game" as regards their intended offshore production concession. That application had not been rejected outright throughout the "roller coaster ride" years, but the aforementioned letter of 29 January 2016 unequivocally does so. It is a matter of ready logical inference than until such time as an application is rejected expressly, or by some rule which deems a certain amount of time passing to be a rejection (which does seem to apply in this matter), it is live and pending.
(2) A law14 was published in the Respondent's Official Gazette on 30 December 2015 which prohibited research, prospection and exploitation in waters within a 12-mile limit of the Italian Peninsula. That was a new legal position as had such a law been in place before that time no-one, including the Claimants, would go to the trouble of spending any time, effort and money on exploring hydrocarbon production in waters within such a limit.
(3) The Claimants' pending application was rejected as a result of the new law as the proposed production wells would be within the new geographical limit. The Respondent's letter does not go beyond that reason as a stated basis for rejection of the Claimants' pending application. The letter notes, in addition, that at the time the new law came into force, the Respondent was examining the supplementary documentation supporting the technical and economic capabilities submitted by the Claimants on 16 December 2015 "to complete the procedure downstream of the Decree on Environmental Compatibility." The detail of what the Respondent was examining at that time is discussed in more detail below.
(4) The Tribunal also notes that the letter indicates that the pending application was "in play" for quite a few years having been filed in 2008. The Parties have also stipulated a number of pertinent facts in that regard as to the overall duration of the process (using that term in its widest and generic sense) in relation to the putative production in Ombrina Mare and the background going back over many years:
The MED granted a production concession to Elf on the basis of production data submitted by Elf. [Fact No. 5, 1992]
Edison acquired the Ombrina Mare production concession from Elf. [Fact No. 6, 1998]
Edison relinquished the production concession. [Fact No. 7, 2000]
The MED granted Rockhopper Italia an Exploration Permit to explore the Ombrina Mare Field for the duration of six years. [Fact No. 8, 5 May 2005]
Rockhopper Italia conducted exploration activity pursuant to the Exploration Permit, including acquiring 2D and 3D seismic data from Edison, obtaining an EIA for the "Ombrina Mare 2" exploratory well, and drilling the Ombrina Mare 2 and Ombrina Mare 2 Dir wells. Rockhopper Italia spent approximately €18 million on conducting these exploration activities. [Fact No. 9, 2005-2008]
A flow test on the OM2Dir well confirmed the presence of oil, similar to that confirmed by OBM-1. The OM2 well also confirmed the presence of methane gas on the overlying Pliocenic levels. [Fact No. 10, 2008]
Rockhopper Italia submitted/the MED received Production Concession Application. [Fact No. 11, 16/17 December 2008]
The MED wrote to Rockhopper to confirm: "having heard the opinion of the Commission for Hydrocarbons and Mining Resources (CIRM) during the session held on the 23 June 2009, has come to the decision to begin the procedure to grant the concession". [Fact No. 12, 23 June 2009]
Rockhopper Italia submitted its EIA application to MEPLS and MCHA. [Fact No. 13, 3 December 2009]
The MCHA approved the EIA. [Fact No. 14, 30 June 2010]
Law 28 December 2015, No. 208
Art. 1, para 239
Article 6, para. 17, of legislative decree 3 April 2006, no. 152, second and third sentences are hereby replaced with the following: "The prohibition also applies to the marine areas located within twelve miles of the coastlines alongside the whole national coast perimeter and of the external perimeter of such protected marine and coastal areas. Enabling titles that have already been issued remain valid for the entire lifecycle of the oilfield, in compliance with safety and environmental protection standards. Maintenance activities aimed at implementing the technological upgrades necessary for the safety of the plants and the protection of the environment, as well as final environmental restoration activities must always be ensured".
The Italian original thereof is:
LEGGE 28 dicembre 2015, n. 208.
Disposizioni per la formazione del bilancio annual e pluriennale dello Stato (legge di stabilità 2016).
239. All'articolo 6, comma 17, del decreto legislativo 3 aprile 2006, n. 152, il secondo e il terzo periodo sono sostituiti dai seguenti: «Il divieto è altresì stabilito nelle zone di mare poste entro dodici miglia dale linee di costa lungo l'intero perimetro costiero nazionale e dal perimetro esterno delle suddette aree marine e costiere protette. I titoli abilitativi già rilasciati sono fatti salvi per la durata di vita utile del giacimento, nel rispetto degli standard di sicurezza e di salvaguardia ambientale. Sono sempre assicurate le attività di manutenzione finalizzate all'adeguamento tecnologico necessario alla sicurezza degli impianti e alla tutela dell'ambiente, nonché le operazioni finali di ripristino ambientale».
Law decree 22 June 2012, No. 83 as amended by Law 134 of 7 August 2012
Art. 35, para. 1
Article 6, para. 17 of legislative decree 3 April 2006, no. 152, is hereby replaced with the following:
17. For the purposes of protecting the environment and the ecosystem, within the perimeter of marine and coastal areas which are for any reason protected for environmental protection purposes, pursuant to national or regional laws or in implementation of EU or international deeds or conventions, the exploration, prospecting or exploitation of liquid or gaseous hydrocarbons in the sea, as envisaged by articles 4, 6 and 9 of Law no. 9 of 9 January 1991, are prohibited. The prohibition also applies to the marine areas located within twelve miles of the coastlines alongside the whole national coast perimeter and of the external perimeter of such protected marine and coastal areas, except to the concession procedures under articles 4, 6 and 9 of Law no. 9 of 1991, ongoing as at the date of entry into force of legislative decree 29 June 2010 no. 128 and subsequent or connected authorization and concession procedures, as well as the validity of authorizations issued within that same date, also for the purposes of performing exploration, prospecting or exploitation activities yet to be authorized within the framework of the authorizations themselves, of any relevant extensions and of subsequent and connected authorization and concession procedures. The authorization of the above activities is subject to the prior completion of the environmental impact procedure under article 21 et seq. of this decree, and after hearing the opinion of the local authorities located within twelve miles from the marine and coastal areas affected by the activities under the first sentence, without prejudice to the activities under article 1, paragraph 82-sexies, of Law 23 August 2004, no. 239, authorized by the territorial supervisory offices of the national mining office for hydrocarbons and geo-resources, in compliance with the environmental restrictions imposed by the same, which shall send a copy of the relevant authorizations to the Ministry of economic development and the Ministry of the environment and the protection of land and sea. Upon the entry into force of the provisions under this paragraph, paragraph 81 of article 1 of Law 23 August 2004, no. 239 shall be repealed. As of the entry into force of this provision, the owners of offshore production concessions are required to pay on an annual basis the production rate under article 19, para. 1 of Legislative Decree 25 November 1996, no. 625 is hereby increased from 7% to 10% for gas and from 4% to 7% for oil. The sole owner or co-owner of each concession is required to pay the sums corresponding to the increase of the percentage to a specific income component of the State budget, all of which shall be reallocated, in equal parts, to specific income components of the budget of the Ministry of the environment and the protection of land and sea and of the Ministry of economic development, so as to ensure the full performance, respectively, of activities aimed at monitoring and countering marine pollution and activities for the supervision and control of the safety, also environmental, of offshore exploration and production plants.
The Italian original is as follows:
1. L'articolo 6, comma 17, del decreto legislativo 3 aprile 2006, n. 152, e' sostituito dal seguente: «17. Ai fini di tutela dell'ambiente e dell'ecosistema, all'interno del perimetro delle aree marine e costiere a qualsiasi titolo protette per scopi di tutela ambientale, in virtu' di leggi nazionali, regionali o in attuazione di atti e convenzioni internazionali sono vietate le attivita' di ricerca, di prospezione nonche' di coltivazione di idrocarburi liquidi e gassosi in mare, di cui agli articoli 4, 6 e 9 della legge 9 gennaio 1991, n. 9. Il divieto e' altresi' stabilito nelle zone di mare poste entro dodici miglia dalle linee di costa lungo l'intero perimetro costiero nazionale e dal perimetro esterno delle suddette aree marine e costiere protette, fatti salvi i procedimenti concessori di cui agli articoli 4, 6 e 9 della legge n. 9 del 1991 in corso alla data di entrata in vigore del decreto legislativo 29 giugno 2010 n. 128 ed I procedimenti autorizzatori e concessori conseguenti e connessi, nonche' l'efficacia dei titoli abilitativi gia' rilasciati alla medesima data, anche ai fini della esecuzione delle attivita' di ricerca, sviluppo e coltivazione da autorizzare nell'ambito dei titoli stessi, delle eventuali relative proroghe e dei procedimenti autorizzatori e concessori conseguenti e connessi. Le predette attivita' sono autorizzate previa sottoposizione alla procedura di valutazione di impatto ambientale di cui agli articoli 21 e seguenti del presente decreto, sentito il parere degli enti locali posti in un raggio di dodici miglia dalle aree marine e costiere interessate dalle attivita' di cui al primo periodo. Dall'entrata in vigore delle disposizioni di cui al presente comma e' abrogato il comma 81 dell'articolo 1 della legge 23 agosto 2004, n. 239. A decorrere dalla data di entrata in vigore della presente disposizione, i titolari delle concessioni di coltivazione in mare sono tenuti a corrispondere annualmente l'aliquota di prodotto di cui all'articolo 19, comma 1 del decreto legislativo 25 novembre 1996, n. 625, elevata dal 7% al 10% per il gas e dal 4% al 7% per l'olio. Il titolare unico o contitolare di ciascuna concessione e' tenuto a versare le somme corrispondenti al valore dell'incremento dell'aliquota ad apposite capitolo dell'entrata del bilancio dello Stato, per essere interamente riassegnate, in parti uguali, ad appositi capitoli istituiti nello stato di previsione del Ministero dell'ambiente e della tutela del territorio e del mare e del Ministero dello sviluppo economico, per assicurare il pieno svolgimento rispettivamente delle azioni di monitoraggio e contrasto dell'inquinamento marino e delle attivita' di vigilanza e controllo della sicurezza anche ambientale degli impianti di ricerca e coltivazione in mare».
The new government, led by Mario Monti, enacted Decree 83/2012 which further amended Article 6 of the Environmental Code to confirm that the Prohibition did not apply to applications for production concessions that were under review at the time Decree 128/2010 came into force. [Fact No. 21, 26 June 2012]
Decree 83/2012 did not withdraw the 12-mile ban, it excluded from its scope those who already had started a production concession application at the time of Decree 128/2010. [Fact No. 22, 26 June 2012]15
One of the stated purposes of Decree 83/2012, which was set out in the accompanying Government report, was to avoid contingent litigation that would follow from permit holders such as Rockhopper Italia who would understandably seek compensation for the denial of their legal rights. [Fact No. 23, 26 June 2012]16
First, it must have been a deliberate choice on the part of the Respondent to create a specific, and limited exception to the Law No. 128 of 2010. The exception was only made for those applications which had been pending prior to that law, and not any others which might have come along in the interim (if any).
Secondly, this exceptional step was therefore confined to a limited range of persons or entities, and not erga omnes. The fact that the Respondent must have had such a limited range of persons or entities in mind is confirmed by the following. The Respondent specifically took this step to avoid litigation and claims for damages from such companies. The Tribunal infers that it would have been reasonable for the Respondent to have had a clear sense of the number of companies in mind when considering the avoidance of the risk of litigation. It would have reasonably known from the records held by the relevant instrumentalities where the risks would lie and who the effected parties would be. By taking this step the Respondent must have considered it a risk worth abating.
Thirdly, this was not a "one-way-street" in favour of the companies, but came with a price. The royalty rates were increased, significantly (40%, as noted on p. 36 of the Italian original17 of C-89), from 7% to 10% for gas and from 4% to 7% for oil. Nor indeed were these increases a blunt instrument resulting in simply more money in due course for the Respondent, but rather had within them a specific (and sophisticated) component directly related to the environment. The amount of the increased royalty would be reallocated, in equal parts, to specific income components of the budgets of two Ministries. This was specifically stated to be for "the full performance, respectively, of activities aimed at monitoring and countering marine pollution and activities for the supervision and control of the safety, also environmental, of offshore exploration and production plants."
Legislative decree 29 June, No. 128
Art. 2, para. 3, lett. h)
[The following paragraphs are added to article 6 of legislative decree 3 April 2006, No. 152 (…)]: (…) 17. For the purposes of protecting the environment and the ecosystem, within the perimeter of marine and coastal areas which are for any reason protected for environmental protection purposes, pursuant to national or regional laws or in implementation of international deeds or conventions, the exploration, prospecting or exploitation of liquid or gaseous hydrocarbons in the sea, as envisaged by articles 4, 6 and 9 of Law no. 9 of 9 January 1991, are prohibited. The prohibition also applies to the marine areas located within twelve nautical miles of the external perimeter of such protected marine and coastal areas, as well as – exclusively with regard to liquid hydrocarbons – in the area enclosed within five miles from the baseline of territorial waters along the entire national coastal perimeter. Outside such areas, the authorization of the above activities is subject to the prior completion of the environmental impact procedure under article 21 et seq. of this decree, and after hearing the opinion of the local authorities located within twelve miles from the marine and coastal areas affected by the activities under the first sentence. The provisions under this paragraph apply to authorization procedures ongoing at the date of the entry into force of this paragraph. Enabling titles that have already been issued at the same date remain valid. Upon the entry into force of the provisions under this paragraph, paragraph 81 of article 1 of Law no. 239 dated 23 August 2004 shall be repealed.
The relevant Italian original is as follows:
17. Ai fi ni di tutela dell'ambiente edell'ecosistema, all'interno del perimetro delle aree marine e costiere a qualsiasi titolo protette per scopi di tutela ambientale, in virtù di leggi nazionali, regionali o in attuazione di atti e convenzioni internazionali sono vietate le attività di ricerca, di prospezione nonché di coltivazione di idrocarburi liquidi e gassosi in mare, di cui agli articoli 4, 6 e 9 della legge 9 gennaio 1991, n. 9. Il divieto è altresì stabilito nelle zone di mare poste entro dodici miglia marine dal perimetro esterno delle suddette aree marine e costiere protette, oltre che per i soli idrocarburi liquidi nella fascia marina compresa entro cinque miglia dalle linee di base delle acque territoriali lungo l'intero perimetro costiero nazionale. Al di fuori delle medesime aree, le predette attività sono autorizzate previa sottoposizione alla procedura di valutazione di impatto ambientale di cui agli articoli 21 e seguenti del presente decreto, sentito il parere degli enti locali posti in un raggio di dodici miglia dalle aree marine e costiere interessate dalle attività di cui al primo periodo. Le disposizioni di cui al presente comma si applicano ai procedimenti autorizzatori in corso alla data di entrata in vigore del presente comma. Dall'entrata in vigore delle disposizioni di cui al presente comma è abrogato il comma 81 dell'articolo 1 della legge 23 agosto 2004, n. 239.
The Government enacted Decree 128/2010 (amending Article 6 of the Environmental Code and imposing the Prohibition) pursuant to Delegation Law 69 of 18 June 2009 which introduced a prohibition on oil-and-gas exploration and production activities in proximity to certain protected marine and coastal areas, as well as in marine areas located within five miles of the national coastline. [Fact No. 15, 26 August 2010]
Uncertainty existed as to the interpretation of Decree 128/2010. The MEPLS sought clarification from the Council of State on how to interpret and apply Decree 128/2010, in particular whether operators who had exploration permits and had already applied for production concessions would fall within the scope of the Prohibition contained in Decree 128/2010. [Fact No. 17, 12 January 2011]
The Council of State requested the opinion of the MED, as well as the Ministry for European Policies and the Ministry for Regional Affairs, on the questions raised by the MEPLS. [Fact No. 18, 16 March 2011]
The MED confirmed that, in its opinion, an exploration permit holder that has made a discovery has a legitimate expectation to obtain a production concession and should be allowed to file a production concession application for fields located in the marine and coastal areas affected by the Prohibition. [Fact No. 19, 14 June 2011]
The Council of State confirmed that an operator holding an exploration permit had no right to obtain a production concession. [Fact No. 20, 20 October 2011]
(1) in 2010 the Respondent seems to have banned all new offshore (within 12 miles) drilling projects though it is not absolutely clear that this was precisely the case from the text of the law.18 This lack of clarity prompted the clarification exercise leading ultimately to the Council of State's confirmation on 20 October 2011;
(2) in 2012 the Respondent made an exception to its 2010 position insofar applications for new offshore (within 12 miles) drilling projects were pending prior to the entry into force of Law No. 128 of 2010. It is also a matter of fact that when the Claimants' investment was made in August 2014 (as noted above in paragraph 94), this was the state of the law at that time; and
(3) in late 2015 the exception for pending applications, which had been made in 2012 (i.e. as noted in the immediately preceding sub-paragraph of this Award), was removed. It was the late 2015 "removal" of the exception for pending applications which, as discussed above, led to the Respondent rejecting the Claimants' application recorded in the letter of 29 January 2016.
Documents prepared or commissioned by the Respondent between 30 September 2015 and 1 January 2016 proposing Article 1, paragraph 239 of the Budget Law [CLA-7] (namely, the reinstatement of Decree 128/2010) including:
(i) initiative, proposal, and consultation documents;
(ii) memoranda containing an analysis of Article 1, paragraph 239 of the Budget Law;
(iii) transcripts of floor debates concerning the enactment of Article 1, paragraph 239 of the Budget Law;
(iv) minutes of Ministers' and/or Ministers' Council and/or Ministers' Presidency Council meetings in which the enactment of Article 1, paragraph 239 of the Budget Law was discussed; and
(v) memoranda prepared by the Italian Parliament regarding the impact of the enactment of Article 1, paragraph 239 of the Budget Law on the questions that had been certified by the Regional Councils for Referendum.
3. On 22 December 2015 the Senate definitively approved the Budget Law:
A. During a meeting of the Advisory Committee, and in particular during meeting no. 190 of 21 December 2015 of the 13th Permanent Committee (Territory, environment, environmental assets) the ban introduced by paragraph 239 and the life cycle of oilfields were discussed (…).
B. Lastly, the list of amendments inserted at this stage shows the following:
- "G/2111B/16/5 DE PETRIS, URAS - UPHELD AS RECOMMENDATION
The Senate, whereas:
• Paragraphs 129-ter et seq. of article 1, of the 2016 Budget Law, in the version approved by the Chamber of Deputies, contain amendments to current legislation on the granting of authorization titles for hydrocarbon exploration and extraction.
• Over the past months, such issues have been dealt with in multiple popular protest and participation initiatives which have led, among other things, to the formalization of six referendum proposals, pursuant to art. 75 of the Constitution, subject to the prior issue of a resolution on part of ten regional Councils;
• On 27 November last, the Court of Cassation expressed, for its part, its favourable opinion on the formal correctness of the six fundamental referendum demands and on 13 January next, the Constitutional Court is expected to issue its ruling;
• The changes in legislation introduced on the matters at hand by the Chamber of deputies respond only in part to the issues raised by the Regions with the referendum requests, and in particular, the issues raised in referendum demands no. 2, no. 3 and no. 6 concerning the local entities' approval, the duration of enabling titles for exploration and extraction and the actual prohibition to grant permits within twelve nautical miles were eluded;
• The legal framework which would originate as a result of the provisions introduced by the Chamber of deputies gives rise to several issues open to ambiguous interpretation, with particular reference to ongoing authorization procedures, and it does not appear to be in line with the intention clearly expressed by the regional Councils, which points to the envisaged referendum.
Orders the Government to:
• Interrupt the ongoing authorization procedures for the exploration and extraction of hydrocarbons within twelve nautical miles from the coastline, along the entire national coastal perimeter and from the external perimeter of protected marine areas, for the purpose of preventing the circumvention of the ban under article 6, paragraph 17 of Legislative Decree dated 3 April 2016, no. 152;
• Ensure the approval on part of the Regions and the local authorities represented in the Single Committee (Conferenza unificata) in relation to the planning of the hydrocarbon exploration and extraction activities;
• Define a limited and indisputable duration both of enabling titles concerning the exploration and of enabling titles concerning the extraction of hydrocarbons;
• Adequately assess the positioning expressed by the ten regional councils on the envisaged referendum on hydrocarbon exploration and extraction, also taking into account the need to revisit national energy policies in light of the agreement recently reached in Paris during the Conference of the Parties to the UN Framework Convention on Climate Change (COP21). [Emphasis added.]
The Italian original thereof is as follows:
3. Il 22 dicembre 2015 il Senato ha approvato definitivamente la Legge di Stabilità:
A. In una seduta della Commissione Consultiva, in particolare nella seduta n. 190 del 21 dicembre 2015 della 13ª Commissione permanente (Territorio, ambiente, beni ambientali) si parla del divieto introdotto dal comma 239 e della vita utile dei giacimenti (v. qui).
B. Infine, nell'elenco degli emendamenti inseriti in questa fase risulta quanto segue:
- "G/2111B/16/5 DE PETRIS, URAS - ACCOLTO COME RACCOMANDAZIONE
Il Senato, premesso che:
• i commi 129-ter e seguenti, dell'articolo 1, della Legge di Stabilità per il 2016, nel testo approvato dalla Camera dei deputati, contengono modifiche della vigente disciplina in materia di rilascio dei titoli autorizzativi concernenti la ricerca e l'estrazione di idrocarburi;
• tale materia è stata oggetto, nei mesi scorsi, di molteplici iniziative di protesta e di partecipazione popolare che hanno condotto, fra l'altro, alla formalizzazione di sei proposte di referendum abrogativo, ai sensi dell'art. 75 della Costituzione, previa deliberazione di dieci Consigli regionali;
• il 27 novembre scorso la Corte di Cassazione, ha espresso, per quanto di propria competenza, parere favorevole sulla correttezza formale dei sei quesiti referendari, e il 13 gennaio prossimo è previsto il pronunciamento della Corte Costituzionale;
• le modifiche legislative introdotte in materia dalla Camera dei deputati rispondono solo parzialmente alle questioni poste dalle Regioni con le richieste di referendum, risultando in particolare eluse le questioni poste dai quesiti referendari n. 2, n. 3 e n. 6, concernenti l'intesa con gli Enti territoriali, la durata dei permessi dei titoli abilitativi per la ricerca e l'estrazione e il divieto effettivo di rilascio di permessi entro le dodici miglia marine;
• il quadro legislativo che si verrebbe a determinare con le disposizioni introdotte dalla Camera dei deputati presenta diverse problematiche di dubbia interpretazione, con particolare riferimento ai procedimenti autorizzativi in corso, e non appare rispondente alla volontà chiaramente espressa dai Consigli regionali, nella direzione della prevista consultazione popolare referendaria,
impegna il Governo:
• a interrompere l'iter dei procedimenti autorizzativi in corso concernenti ricerca ed estrazione di idrocarburi entro le dodici miglia marine dalle linee di costa, lungo l'intero perimetro costiero nazionale, e dal perimetro esterno delle aree marine protette, al fine di assicurare che non sia eluso il divieto di cui all'articolo 6, comma 17, del decreto legislativo 3 aprile 2006, n. 152;
• ad assicurare l'intesa con le Regioni e con gli enti locali rappresentati nella Conferenza unificata in ordine alla pianificazione delle attività di ricerca ed estrazione di idrocarburi;
• a definire una durata temporalmente limitata e certa sia per i titoli abilitativi concernenti la ricerca che per i titoli abilitativi concernenti l'estrazione di idrocarburi;
• a valutare adeguatamente l'orientamento espresso dai dieci consigli regionali in ordine all'effettuazione della prevista consultazione popolare referendaria in materia di ricerca ed estrazione di idrocarburi anche in considerazione della necessità di rivedere le politiche energetiche nazionali alla luce dell'accordo recentemente raggiunto a Parigi in occasione della Conferenza delle parti sulla Convenzione Quadro delle Nazioni Unite sui Cambiamenti Climatici (COP21).
In particular, I refer to the meeting mentioned by Mr. Moody [of the Claimants] (paragraphs 56 to 58) with the then Ambassador of Italy to the United Kingdom, Pasquale Q. Terracciano. The meeting took place on April 2016 at the Embassy of Italy in London and, as correctly reported by Mr. Moody, I was present in my capacity of First Counsellor for Economic Affairs at the Embassy.
[Transcript, day 3, p. 5]
Q. Prior to the meeting on 16th April, what was your knowledge of the Ombrina Mare project?
A. I was -- I was pretty well aware of the Ombrina Mare project because we had regular meetings with the Mediterranean Oil & Gas management first, and Rockhopper eventually, on a pretty regular basis.
Q. When you say "we", do you mean you and the ambassador or you individually?
A. Well, mainly myself, because of my competence at the time.
[Transcript, day 3, p. 11]
Q. So, Mr Brandi, my first question is this: do you accept that during 2015, and particularly the latter half of 2015, there was a battle going on between the federal government and the regions as to power? Do you accept that as a fact?
A. Yes.
Q. Do you also accept as a fact, Mr Brandi, that one of the results of that power struggle was that the ban was reintroduced in January 2016?
A. Yes.
Q. Do you also accept that as a result of that, Rockhopper did not receive the production concession?
A. No, I cannot say that.
...
MR SPRANGE: So, Mr Brandi, do you agree that as a matter of fact the ban reintroduced in 2016 had a negative impact upon Rockhopper's production concession application?
A. Well, what I recognise is that there was a struggle and some dialogue between local and central authorities in Italy upon developing investments in oil and gas sector, not only in Abruzzo, which is the region, but also in other Italian regions. This is what I acknowledge.
Q. Yes. And that led to a referendum; and then to avoid the referendum, the central government reintroduced the ban. I think you've agreed with me so far on that; correct?
A. These are facts. I mean, this is just history.
(l) Ombrina Mare
(i) Ombrina Mare Exploration Permit
• MOG Italia has a 100 per cent participating interest in the Ombrina Mare Exploration Permit.
• The term of the Ombrina Mare Exploration Permit was extended in 2012 until 5 May 2015 by MED decree. We understand that the Ombrina Mare Exploration Permit was suspended for one year from 5 May 2011 until 5 May 2012.
• We understand from the Target that the Ombrina Mare 2d well has been completed but is shut-in pending field development.
(ii) Ombrina Mare Production Concession Application (d30BC MD)
• We understand that an application has been filed with the MED to obtain an exploitation production concession in relation to the well called "Ombrina Mare". However, such request has not yet been granted due to the pending arbitration proceedings. Please refer to section 7.1 for further details.
... ... ... ... ... ...
7. LITIGATION
7.1 Ombrina Mare (administrative litigation)
(a) We understand that MOG Italia has challenged (before the Lazio Regional Administrative Court (the "Court")) a decision of the Italian Ministry of the Environment and Protection of Land and Sea (the "MEPLS") which found that an Integrated Environmental Authorisation ("AIA") must be obtained before the MEPLS would provide sign off on the Environmental Impact Assessment ("EIA") already initiated by MOG Italia.
(b) An Environmental Impact Assessment is a statutory review of the potential environmental, social and economic effects that a proposed hydrocarbon development project may have and aims to identify, predict, evaluate and mitigate those effects.
(c) The claim submitted by MOG Italia sought to:
(i) obtain a declaration from the Court confirming that an AIA is not a precondition to the MEPLS signing off on the EIA; and
(ii) require the MEPLS to commence its sign off of the EIA on the Ombrina Mare well.
(d) On 17 April 2014, the Court rejected the claim filed by MOG Italia. As a result, MOG Italia has been required to apply for an AIA. We understand that MOG Italia has already prepared the necessary documentation in anticipation of this result and is ready to initiate the AIA procedure as soon as possible. However, we do not have visibility on how long it may take to obtain the AIA, as timings can vary widely from project to project.
(e) The Court has instructed MOG Italia to pay its own court costs while MOG Italia has reserved its right of appeal against the Court's ruling.
The boards of Rockhopper Exploration plc ("Rockhopper") and of Mediterranean Oil & Gas plc ("MOG") are pleased to announce that they have reached agreement on the terms of a recommended acquisition under which Rockhopper will acquire the entire issued and to be issued ordinary share capital of MOG (the "Acquisition"). The Acquisition is to be effected by means of a Court sanctioned scheme of arrangement under Part 26 of the Companies Act 2006.
5.5 Rockhopper sees significant potential in the 100 per cent owned and operated Ombrina Mare project, which already has 2C Contingent Resources of 26.5 mmboe with the ability for this to be increased materially depending on the results of the next planned appraisal well. Rockhopper has spent time understanding the Ombrina Mare discovery and Rockhopper believes that with additional technical and engineering work, combined with some patience and funds available to support an appraisal of the discovery, its value can be significantly increased over time.
(1) a pending application for a production concession;
(2) the relevant law in force prohibited exploration within 12 miles of the Italian coastline but provided for an exception for pending applications (i.e. there was a carve-out saver for applications such as that of the Claimants pending since 2008);
(3) the outcome of administrative litigation concerning a requirement to file an Integrated Environmental Authorisation as a prerequisite to the relevant Ministry signing off on the Environmental Impact Assessment had recently emerged. That litigation outcome was to the effect that the Claimants were going to have to file such an Integrated Environmental Authorisation or an "AIA" (which in fact was submitted on 13 May 2014 (C-113)); and
(4) the Claimants understood that "additional technical and engineering work, combined with some patience and funds available to support an appraisal of the discovery, its value can be significantly increased over time."
WITH REGARD TO, HAVING CONSIDERED AND ASSESSED the above, the Environmental Impact Assessment Technical Commission - VIA and VAS
EXPRESSES
its positive opinion on the environmental compatibility assessment regarding the implementation of the "Cultivation project of Ombrina Mare hydrocarbons in the scope of the d30 B.C-MD concession", provided that all of the proposed mitigation measures by the Applicant are taken and, as it is a VIA-AIA opinion, that it complies with the following prescriptive framework, which completely replaces the prescriptive frameworks of the VIA VAS Commission Opinions no. 541 of 7/10/2010, no. 1154 of 25/1/2013 and no. 1192 of 3/4/2013 and the requirements for the PMC (Monitoring and Control Plan) prepared by the IPPC Commission, Relevant Risk Division-AIA, included in this opinion
The Italian original is as follows:
Tutto ciò VISTO, CONSIDERATO E VALUTATO la Commissione Tecnica per la Verifica dell'Impatto Ambientale - VIA e VAS,
ESPRIME
giudizio positive di compatibilità ambientale concernente la realizzazione del "Progetto di coltivazione del giacimento di idrocarburi "Ombrina Mare nell'ambito della concessione di coltivazione d30 B.CMD" a condizione che vengano adottate tutte le misure di mitigazione proposte dal Proponente e, trattandosi di un parere VIA-AIA, che si ottemperi al seguente quadro prescrittivo, che sostituisce integralmente i quadri prescrittivi dei pareri della Commissione VIA VAS, n. 541 del 7/10/2010, n.1154 del 25/1/2013 e n. 1192 del 3/4/2013, e alle prescrizioni relative al PMC (Piano di Monitoraggio e Controllo) redatto dalla Commissione IPPC, Divisione Rischio Rilevante-AIA, incluso nel presente parere:
the Applicant must present the detailed design of the pipelines, the means and methods of laying or placing pipelines, and the technical choices that motivate such methods by including the following: 1) design of pipes (thickness, curvature, elasticity, mechanical and cathodic protections, thickeners, etc., 2) execution of reliefs along the pipeline corridors with detailed bathymetry, obstacle relief, geo-referencing of outlines, 3) seabed sediment characteristics, granulometry and lithology, 5) seabed currents for predicting interactions between pipelines and solid-state transport on the seabed, 6) safety sheets of the materials used for the protection of the new marine pipelines and cables for the hydraulic conductivity testing, 7) methods and point of withdrawal and disposal of water used for pressurisation and cleaning of the pipeline during the final testing phase[…]
The Italian original is:
il Proponente, prima dell'inizio dei lavori, dovrà presentare il progetto di dettaglio dei tracciati delle condotte, dei mezzi e delle modalita' di posa o di interramento delle condotte e le scelte tecniche che motivano tali modalità comprensivo dei seguenti elaborati: 1) progettazione delle condotte (spessori, curvature, elasticità, protezioni meccaniche e catodiche, appesantimenti, ecc), 2) esecuzione di rilievi lungo i corridoi dei tracciati delle condotte con batimetrie di dettaglio e georeferenziazione dei tracciati e degli ostacoli, 3) caratteristiche dei sedimenti di fondo con campionature di granulometria e litologia, 5)rappresentazione delle correnti di fondo per la previsione delle interazioni tra le condotte e il trasporto solido su fondale, 6) schede di sicurezza dei materiali utilizzati per la protezione delle nuova condotte marina e dei cavi per il collaudo idraulico della condotta, 7) modalità ed il punto di prelievo e smaltimento dell'acqua utilizzata per la pressurizzazione e pulizia della condotta nella fase di collaudo[…]
HAVING HELD that, on the basis of the foregoing, all the conditions have been met providing for the issuance of the decree herein below pursuant to Articles 10 and 26 of Legislative Decree no. 152 of 3 April 2006 and its subsequent amendments and additions;
DECREES
the environmental compatibility of the execution of the project "Development of the Ombrina Mare deposit in the context of the application for the awarding of the Production Concession conventionally known as d 30 B.C-MD", located in the Adriatic Sea adjacent the Abruzzo coast and the AIA for the operation of the Ombrina Mare platform submitted by the Company Medoilgas Italia S.p.A, now "Rockhopper Italia S.p.A", with its registered office in Via Cornelia 498, 00166 Rome Italy on the condition that the prescriptive and administrative requirements indicated in the following Annexes, which are an integral part of this decree, are fulfilled:
- Annex 1: EIA Prescriptive Framework
- Annex 2: AIA Prescriptive Framework
- Annex 3: Administrative Prescriptions for the AIA
- Annex 4: Monitoring and Audit Plan for the AIA
The Italian original is as follows:
RITENUTO che, sulla base di quanto premesso, sussistono tutte le condizioni per dovere provvedere ai sensi degli articoli 10 e 26 del D.lgs 3 aprile 2006, n. 152 e ss.mm.ii. all'emanazione del presente provvedimento;
DECRETA
la compatibilità ambientale concernente la realizzazione del progetto di "Sviluppo del giacimento Ombrina Mare nell'ambito dell'istanza di conferimento della Concessione di Coltivazione convenzionalmente denominate d 30 B.C-MD'~ ubicata nel Mare Adriatico adiacente alla costa Abruzzese e la Autorizzazione Integrata Ambientale per l'esercizio delle piattaforma "Ombrina Mare" presentato dalla Società Medoilgas Italia S.p.a., ora "Rockhooper Italia S.p.A." con sede in Via Cornelia, 498 - 00166 Roma, a condizione che vengano ottemperate le prescrizioni e gli adempimenti amministrativi indicati net seguenti allegati che costituiscono parte integrante del presente decreto:
- Allegato 1: Quadro prescrittivo relativo alla VIA;
- Allegato 2: Quadro prescrittivo relativo all' AIA;
- Allegato 3: Adempimenti amministrativi relativi all' AIA;
- Allegato 4: Piano di monitoraggio e controllo relativo all'AIA.
128. These environmental approvals (EIA) were published by Rockhopper in the Official Gazette number 93 - Part Two of Thursday 13 August 2015. As testified by Mr. Terlizzese, by then MISE had a firm belief that the current conditions rendered the project unviable.
129. Further, at that same time, the favorable EIA news provoked an enormous reaction against the project by Abruzzo Region and by the local communities and administrations, culminating in a climate of strong media pressure. Despite the high probability of a precautionary suspension of the environmental compatibility measure by the Regional Administrative Court, following the announced appeals by public bodies and / or environmental associations, the MED nonetheless continued the process, calling for a Conference of Services on 14 October 2015. The Conference of Services was called for in order to acquire the missing opinions of the Ministry of Infrastructure and Transport, the Ministry of Defense and the Ministry of Agriculture and Forestry, as well as to "feel" the local administrations within 12 nautical miles from the places concerned from activities (as envisaged by the then current formulation of Article 6 paragraph 17 of Legislative Decree 152/2006).
In view of the above, the company Rockhopper Italia S.p.A.
lodges this application
for the start of the procedure for granting the production concession conventionally called 'd30B.C-MD'.
Decree of the President of the Republic 18 April 1994, No. 484
Art. 16, para. 3
The Ministry [translator's note: Ministry of economic development], within fifteen days from the receipt of the environmental compatibility decree by the Ministry of the environment, issues the decree for the award of the production concession.
The Italian original is:
3. Il Ministero, entro quindici giorni dalla notifica da parte del Ministero dell'ambiente della pronuncia di compatibilità ambientale, emana il decreto di conferimento di concessione di coltivazione.
We expected that the decision on the Production Concession would come within 15 days, as required by law. [Emphasis added.]
The amendments to the Environmental Code that allegedly impacted Articles 16 and 17 of Decree no. 484/1994 did not regulate the specific issues contained in those provisions. As Mr. Leccese explains, Decree no. 484/1994 and the Environmental Code regulate different matters: the former regulates applications for hydrocarbons permits before the MED, while the latter governs environmental matters, such as EIA applications pending before the MEPLS.
The 15-day term pursuant to Decree no. 484/1994 (art. 16, paragraph 3) for the issue of the concession following the EIA was neither expressly nor tacitly repealed by the Environment Code, since (a) as stated above, the latter does not regulate the Production Concession Application process nor the MED's powers on the granting of a production concession; and, in any case, (b) the 15-day deadline set forth by Decree no. 484/1994 has nothing to do with the EIA process in that in that [sic] it applies after completion of the same.
I also supported the argument of the implicit repeal of the art. 16 of Presidential Decree 484/1994, which, moreover, expressly referred to both art. 2 paragraph 3 of the law 9.1.1991 (article completely repealed by the aforementioned article 36, paragraph 3, letter h) of the Environmental Code and of the art. 6 paragraph 4 of the law 8th July 1986, n. 349 (in turn repealed by Article 36 paragraph 3 letter a) of the Environmental Code).
Q. How engaged were you, on a day-to-day basis, on Rockhopper's production concession application between August 2015 and December 2015?
A. A fair amount. I would say that a significant part of my time that is not simply dedicated to this side of oil production was dedicated to this file, because it was very important, it was urgent, and it was important from many points of view. So I did give a lot of my time. I took part in meetings and I was also briefed regularly by the manager in charge.
Q. When you say it was very urgent, is that because the law requires a production concession to be granted within 15 days of the environmental decree being granted?
A. No, this is not so. The concession needs to formally be given within 150 days from the application. So my aim was to finish this work, having received the file around 15th August 2015, by the end of 2018 (sic).
Q. Are you sure it's not the fact that the concession has to be provided within 150 days of it being filed, and that it's 15 days after the EIA has been granted? I can show you the provisions of the law if you're unsure.
A. Yes, but I could also show you a list of the concessions that were granted in the whole history, and none of them were granted within 15 days of the EIA. And this is impossible because the operator is not in a position to give all the material, the documents that are necessary, within 15 days of the decree.
Q. Is it your evidence that you couldn't do it in 15 days because Rockhopper didn't give you some documents?
A. Even if Rockhopper had provided the documents, technically it would have been impossible for our offices to contact all the local administrations and follow this process that goes back to 2008/2009. So something that had happened at a very different time, with a different price scenario, but also from a technical, economic, structural and development the situation was completely different, so it had to completely be reviewed, and I think here there was nothing said by the company. The company wanted to obtain quickly the concession, like all other companies do. So we try, because the law asks us, to keep to the timing of the applications. So this is what we were doing. So we were committed, I was personally committed, and it was urgent, and the law states that. So we were completely compliant.
Re-direct examination by MR GAROFOLI
Q. (Interpreted) Mr Terlizzese, we mentioned the files that exist at the ministry on this procedure, the production concession application by Rockhopper, and we also talked about some draft documents that, as a result of meetings and exchanges, were included in these files. Do these files contain also the assessments on the technical and financial producibility of this oilfield that were discussed with Mr Morandi?
A. Yes, there were a number of discussions, especially on the development project. We acknowledged that it would have been impossible to have more information on the amount available in this oilfield on the basis of a single well. The Rockhopper assessment is based particularly on how complex the treatment and recovery would be.
Q. So Rockhopper knew that the ministry had some doubts on the producibility from a technical and financial point of view of this oilfield? And here I refer to a question asked at 10.46 --
MR SPRANGE: I can be a patient man, but when a supposedly non-leading question starts with, "So Rockhopper knew the ministry had some doubts", even I lose my patience.
THE PRESIDENT: Could I say that, particularly in re-direct --
MR GAROFOLI: (In English) Okay, I'll go on.
THE PRESIDENT: -- it's probably best not to suggest the answer, because the answer that would come perhaps may not necessarily have the same weight with the Tribunal.
MR GAROFOLI: (Interpreted) Do you know whether Mr Morandi had been informed about these critical points and this doubt?
A. Yes.
Q. Did you discuss with Mr Morandi only the technical aspects or also the economic and financial aspects linked to this oilfield and the project in general?
A. We discussed the technical and economic capability of Rockhopper Italia and we discussed the economic viability of the project.
Q. Okay. Let's go to slide 49 of the Claimants' presentation. Maybe you were taken a bit by surprise when you replied, when you answered, because the way we interpret this slide, these are the studies made over time relating to the Ombrina Mare oilfield, and which were prepared and presented over time. Did you take into account all the technical studies prepared and presented by the applicants in the various phases of the project?
A. Yes. Even though they didn't have this form, we examined and compared the different scenarios, starting from when Elf submitted the first project. At that time the amount of data available were far more limited than what we later had. We could follow the evolution of the value of the figures, and obviously we focused on the recoverable oil, which is what was of interest to us. We also especially focused on the recovery rate, because this is a very controversial criterion. But if we look at the literature, we can see that the value[s] given by Elf in 2010 are very optimistic values.
MR GAROFOLI: (In English) Thank you, Mr President. This is enough for us.
Q… Do you agree that there is a timeline in the law for the Ministry of Economic Development to decide an applicant's request for a production concession?
A. Yes. But I would like to point out the fact that the minister does not have a contractual obligation, but it also has administrative powers. This is quite different. So we cannot reason in terms of obligations. Otherwise the law would have not made a distinction between a damage caused by a delay and a damage caused by a tort. You may like it or not, but that's the truth.
Q. I like your answer very much because it's the truth, but also the answer to my question was: yes, there is a timeline. So now I want to ask you the next question. What is that timeline for the ministry to decide the application?
A. We are talking about the Ministry of Economic Development, aren't we? We are talking about the Ministry of Economic Development, aren't we? Because we have already exhausted the example with the Ministry of Environment.
Q. We are.
A. According to Decree 484, there were 15 days. But in my opinion, this rule is not applicable because it was based on the assumption that the ministry could decide independently from the EIA, regardless of the EIA. This is no longer true. But if we want to talk of who is at fault, I don't think it was the government, but the Parliament and the council of European ministers, because they said that the EIA was mandatory for these type of activities. And they also said that if a country did not comply, if a Member State did not comply with this, it could be subject to proceedings for breach of the regulations. This affected also the United Kingdom; obviously before Brexit, if it will take place.
Q. So I want to go to the first part of your answer. You say that there were 15 days for the Ministry of Economic Development to decide the production concession application after the Ministry of the Environment has issued the environmental permit, but you suggest that this should not be the case. What I want to know then is: affirmatively, what do you put forward as any indication of the timeline that the Ministry of Economic Development must act within after the Ministry of Environment has awarded the environmental permit?
A. It's important to say, first of all, that here we are talking about non-peremptory terms, if we talk about compensation. This has to be clear. Normally the same Law 241, which, as you know, is the main law of reference for administrative procedures, the law states 30 days. But this can be -- you can also have a challenge in a --
Q. Professor, if I may interrupt you. I don't want to talk about whether something is peremptory or non-peremptory, or the consequences that may follow if a timeline is not respected. I just want to know that if you are in Rockhopper's position, the Ministry of Environment has issued its environmental application permit on 7th August, and Rockhopper came to you and said, "Professor, what is the timeline now that the Ministry of Economic Development is supposed to act within on my production concession application?", what would you say in terms of the timeline under law?
A. I would tell them to be as patient -- to have biblical patience, patience in a biblical sense, because the ministry does what they can. But you can also use an injunction, which is an instrument which is used quite often, and which is very important also according to the Italian Civil Code, an injunction that we notify by means of court officer. It has to be official; obviously an email or a letter sent by registered post is not enough. And this is very important to establish alleged fault. It's very important. Today this system is used also for public tenders, public procurement. If a company wants to appeal, they first have to send an injunction to the public body involved, and the public body has the opportunity to withdraw its measures if they are considered unlawful.
Q. So if Rockhopper came to you in August 2015, I understand your answer to be that you would tell them to be patient, that you would not be able to provide any timeline. So if they said, "Is it 15 days, 30 days, a year, two years?", you could not answer that, but you would say, "Perhaps you can seek an injunction at some point". Is that a fair summary of what you just said?
A. This is a statement that I don't entirely agree with. I would have indicated a timeframe, 30 days, because that's what the law says. I would have said, "Wait for 30 days. Maybe first send them a very polite letter. If they don't answer within 30 days, then issue an injunction, get an injunction issued". If I may add something, after 30 days, after another 30 days, you can start proceedings in front of the administrative tribunal, the power to demand the granting of the permit. This is how the Italian system works. In my presentation I forgot to say that I was a member of the committee that prepared the Administrative Procedure Code, so I know it inside out.
Re-direct examination by MR GAROFOLI
Q. (Interpreted) Only one question and then we are done. Can you remember the judgment of the Council of State 943/2016 that involved Rockhopper Italia SpA?
A. (Interpreted) Yes, of course.
Q. For the record, it is L-0137.
MR MASCARENAS: I did not discuss any Council of State judgments.
THE PRESIDENT: Although you did not in fact discuss it, it may still touch upon the cross-examination.
MR MASCARENAS: Fair enough.
MR GAROFOLI: As a result of this judgment, in terms of delay of the public administration or what could be considered lawful by the judges, was there a margin to request compensation in Italy by Rockhopper?
A. I can only express my opinion obviously; it is not necessarily the truth. Rockhopper also had another possibility: they could challenge the final rejection of the concession. I think it was dated 17th January 2017. And they could have also raised a constitutionality issue of the Budget Law, and they could have reported Italy to the European Commission. And they could have requested the annulment and compensation or even just compensation. I would like to add that in the case law of the Court of Justice, although the assessment of responsibility does not necessarily go hand in hand with compensation, we have to decide, it has to be decided whether a breach has been committed or not. This is my opinion.
Q. So because they didn't do this, could they apply for compensation?
A. They didn't do this, and then they kind of lost the right to do it, because our code has two provisions: Article 29, that provides for annulment that must happen between 60 days; and then within 120 days from when the fact was assessed or the judgment became final, then they can apply for compensation.
MR GAROFOLI: Thank you very much, Professor.
THE PRESIDENT: Sir, thank you for your testimony. It's now concluded. Thank you. There are no questions from the Tribunal.
During the October Hearing the Claimants presented arguments encapsulated in a PowerPoint presentation and one page thereof is replicated now in full.
Italy knew that the 15 day deadline was law and carried consequences
• Italy failed to issue the Production Concession by 22 August 2015
• MED under obligation, pursuant to Article 16 paragraph 3 of Decree 484/1994 [L-3], to issue the production concession within 15 days from the EIA Decree
• Italy was aware of the deadlines:
• "Q. Do you agree that there is a timeline in the law of the Ministry of Economic Development to decide an applicant’s request for a production? A. Yes." - Professor Picozza, [Day 5/191:4-7]
• "So we try, because the law asks us, to keep to the timing of the applications [...] So we were committed, and it was urgent, and the law states that." - Mr Terlizzese, [Day 3/54:19-23]
• Non-compliance with peremptory deadlines carries legal consequences:
"[...] if the measure is not adopted, there are legal consequences, such as, for example, the possibility to resort to the Council of Ministers, to the president of the Council of Ministers, for substitution powers [...] the terms are peremptory because if the measure is not adopted within those terms, measures are adopted; there are possible consequences.
- Mr Leccese, [Day 2/119:5-13]
I just refer you to slide 36, I would like you to start with the fact that Italy was very aware of the deadlines, and both Professor Picozza and Mr Terlizzese, who was considering the production concession, were aware of that, and Mr Leccese's evidence regarding the legal consequences of non-compliance is, as far as we see, unchallenged.
The MED sent Rockhopper a letter, stating: "For the purpose of completing the procedure concerning the application in the subject […] this Company is required to transmit an update to the documentation regarding its technical-economic capability in the light of the recent Management Decree of 15 July 2015 […]" [Fact No. 43, 11 December 2015]
Rockhopper responded to the 11 December 2015 letter from the MED providing documentation supporting its financial capability. The letter concluded, "Therefore, we herewith declare that, according to the annexed documentation, the Company meets all the technical and economic requirements established by Directorial Decree of 15 July 2015." [Fact No. 44, 14 December 2015]
Considering that to date all the time limits for the conclusion of the procedure have long since expired, invites this Ministry to conclude, without any further delay and by means of an express measure, the procedure to issue the production concession.
Should it fail to do so, expressly reserving the right to implement every available remedy against its non-compliance with the obligation to conclude the main procedure, it requests that this Ministry promptly suspend the elapsing of the allotted term of Permit B.R269.GC:
• at least until the definitive conclusion of the procedure underway to award the production concession for offshore hydrocarbons indicated in application "d 30 B.C.-MD", through the issuance of the Decree to award the production concession by this Ministry;
• and also to enable the company Rockhopper to see to the maintenance and safety of the Ombrina Mare 2 dir well constructed for oil production and the existing temporary platform installed to support the wellhead.
For the purpose of completing the procedure concerning the application in the subject and following the outcome of the Service Conference held on 14 October and 9 November 2015 and after the subsequent technical meeting of 27 November 2015, this Company is required to transmit an update to the documentation regarding its technical-economic capability in the light of the recent Management Decree of 15 July 2015 – Implementing Operational Procedures of Ministerial Decree dated 25 March 2015 and Performance Procedures for the Prospection, Research and Exploitation of Liquid and Gas Hydrocarbons Activities and related Checks published in the Official Journal of 3 September 2015, General Series, No. 204.
In particular, it is hereby requested that the corporate and technical data pursuant to the provision of Article 6 thereof, "Evidence of the applicant's technical and economic capabilities" be added:
- paragraph 3, also with regard to the "parent company" in the event details of the financial statements of this Company are not available yet;
- paragraphs 13, 14, 15 and 16.
We would like to refer to the letter dated 11 December 2015 (Prot. No. 0033009) from this Ministry related to the procedure in the subject, through which the company, Rockhopper Italia S.p.A., formerly named Medoilgas Italia S.p.A. (hereinafter, "Rockhopper" or the "Company") was required to forward the updated documentation on its technical capabilities, pursuant to the recent Directorial Decree of 15 July 2015 – Implementing Operational Procedures of Ministerial Decree dated 25 March 2015 and Performance Procedures for the Prospection, Research and Exploitation of Liquid and Gas Hydrocarbons Activities and related Controls (hereinafter, the "Decree") and, in particular, to supplement corporate data pursuant to Article 6, paragraph 3 and paragraphs 13, 14, 15 and 16.
Without prejudice to the information provided in Rockhopper's letter dated 27 November 2015 and Ughi e Nunziante – Law Firm's letter on behalf of the Company, forwarded on the same day, in the spirit of the upmost co-operation that our Company has always shown in its relationship with the institutions, we would like to reply to the Ministry's requests as detailed below.
With regard to the financial capability requirements under Article 6, paragraph 3 of Directorial Decree, we hereby submit:
(i) a copy of the Rockhopper's approved Financial Statements for the last three financial years (2012, 2013, 2014) together with the reports of the administrative body and the Board of Independent and Statutory Auditors on the management of the Company (Annexes 1, 2 and 3);
(ii) a copy of the latest Consolidated Financial Statements (Annex 4);
(iii) a copy of the latest published Financial Statements of the parent company (such Financial Statements are enclosed with the Consolidated Financial Statements, see Annex 4 from page 74through page 79);
(iv) declaration in lieu of notary deed signed by Mr Morandi, in his capacity as legal representative pursuant to Articles 38, 47 and 76 of Decree of the President of the Italian Republic No. 445 of 28 December 2000 (Annex 5) concerning, in relation to the last three financial years, the following:
a. Rockhopper's turnover (business volume) - both global and specific;
b. Rockhopper's shareholders' equity
c. the ratio between the circulating assets and current liabilities;
d. the ratio between the net debt and the net equity;
(v) the Company's bankruptcy certificate and the anti-Mafia self-certifications of the managers, auditors and the legal representative of the sole shareholder (Annex 6);
(vi) the certified copy of the Articles of Association or the Memorandum of Association (Annex 7);
(vii) the report on Health, Safety, Environment and Waste Management (Annex 8);
(viii) data on the parent company, Rockhopper Exploration Plc:
Rockhopper Exploration Plc, with registered office in the United Kingdom, Hilltop Park Devizes Road – Salisbury SP3 4UF, is a company operating in the research and exploitation of liquid and gas hydrocarbons fields listed in the AIM segment of the London Stock Exchange until August 2005. It was founded in 2004 and holds investments in the Falklands Islands as well as in the Mediterranean basin. Rockhopper Exploration Plc holds 40% of the share in the PL032 and PL033 exploitation concessions and is in the process of completing a "farm-in" announced in October 2013 to purchase 24% of the share in the PL004a, PL004b and PL004c blocks. The aforesaid blocks are located offshore the Falkland Islands and are managed by the operator Premier Oil. Likewise, offshore the Falkland Islands, the Company holds a 3% share in the PL003 block, managed by the company Falkland Oil and Gas.
Further information is available at the website: http://rockhopperexploration.co.uk/rockhopper.html;
(ix) With regard to the financial capability requirements under Article 6, paragraphs 13, 14, 15 and 16 of Directorial Decree, we hereby provide the Technical Capability Specifications (Annex 9 and related annexes), whose information, data and documentation were prepared in strict compliance with factual, legal and technical elements listed under paragraphs 13, 14, 15 and 16 of the aforementioned Article.
Therefore, we herewith declare that, according to the annexed documentation, the Company meets all the technical and economic requirements established by Directorial Decree of 15 July 2015.
1. The suspension of the time limit of the "B.R269.GC" research permit, which is held by the company ROCKHOPPER ITALIA S.p.A. (tax code no. 08344911006), with registered office in Rome, via Cornelia, 498 (post code 00166) shall be extended from 1 January 2016 and up to the date of the granting of the hydrocarbon cultivation concession at sea as provided for in the "d 30 BC-MD" application, and not later than 31 December 2016.
At the end of 2015, the cost-effectiveness of the Ombrina Mare project - a legal requirement for the awarding of the concession – was not demonstrated yet, taking into consideration the sharply reduced market prices of crude oil. In particular, when Law 208/2015 came into force, the preliminary investigation was still ongoing and the last documents presented on 16 December 2015 by the Company were still under examination.
160. The fact of the matter is that the MED did not do any material analysis of the economics of Rockhopper Italia's proposal in November and December 2015. Rockhopper requested documents prepared or commissioned by the Respondent following the Conference of Services that took place on 27 November 2015 and 29 January 2016, when the MED rejected Rockhopper Italia's pending application, regarding the economic viability of the Ombrina Mare project. Italy produced only one document— PowerPoint slides prepared by DSG-UNMIG on 18 November 2015 comparing certain macroeconomic data relating to the Ombrina Mare Field in 2009 and 2015. Italy did not produce any other documents, which must be taken to mean that the MED did not generate any documents assessing the economic viability of the Ombrina Mare project between the period of 27 November 2015 to 29 January 2016.
161. Rockhopper also requested that Italy produce documents prepared or commissioned by the MED between 1 December 2015 and 29 January 2016 setting forth the bases for denying the Production Concession Application. Italy produced two documents. The first document was a Memorandum prepared for the Minister of the MED after the Conference of Services took place on 9 November 2015. The Memorandum does not contain any information about why the MED denied the Production Concession Application. …
162. The second document is also not helpful to Italy: Italy produced an e-mail from a Rockhopper Italia employee to Mr. Terlizzese of the MED dated 17 November 2015 attaching documents regarding Rockhopper's financial assessment of the Ombrina Mare project, and other documents. All that this e-mail shows is that Rockhopper was keen to help the MED with the review process, and promptly submitted any documentation requested by the MED.
163. In sum, Italy did not produce any documents created or commissioned by the MED between 1 December 2015 and 29 January 2016 setting forth the bases for rejecting Rockhopper Italia's Production Concession Application.
...
166. The inference that should be drawn from the lack of contemporaneous documentation demonstrating real-time analysis of the project's economic viability is that this simply was not the focus of whether or not the MED should grant the Production Concession Application. Rather, the MED was waiting to see whether the Budget Law would be enacted, which would reintroduce the Prohibition, and serve as the actual basis for the MED's rejection of the Production Concession Application.
The conclusions reached by the Tribunal in its 26 June 2019 Decision on the Intra-EU Jurisdictional Objections read as follows:
211. For the reasons set forth above, the Tribunal decides as follows:
(1) The Respondent's Intra-EU Jurisdictional Objection is hereby denied;
(2) The Tribunal will address separately in its Award the remaining jurisdictional and/or merits issues in this case;
(3) The Respondent's Request for Suspension is hereby denied; and
(4) Decisions regarding costs are deferred until a later time in these proceedings.
The conclusions reached by the Tribunal in its 20 December 2021 Decision on the Italian Republic's Request for Reconsideration of 29 September 2021 read as follows:
52. For these reasons, the Tribunal DECIDES and ORDERS that:
a) The Respondent's Request for Reconsideration is denied.
The Respondent argues that the Claimants have requested satisfaction on the same grounds before the domestic courts, and, therefore, the following provision of the ECT applies (Art. 26(2) and (3)):
(2) If such disputes cannot be settled according to the provisions of paragraph (1) within a period of three months from the date on which either party to the dispute requested amicable settlement, the Investor party to the dispute may choose to submit it for resolution:
(a) to the courts or administrative tribunals of the Contracting Party party to the dispute;
(b) in accordance with any applicable, previously agreed dispute settlement procedure; or
(c) in accordance with the following paragraphs of this Article.
(3) (a) Subject only to subparagraphs (b) and (c), each Contracting Party hereby gives its unconditional consent to the submission of a dispute to international arbitration or conciliation in accordance with the provisions of this Article.
(b) (i) The Contracting Parties listed in Annex ID do not give such unconditional consent where the Investor has previously submitted the dispute under subparagraph (2)(a) or (b).
[The Respondent is included in Annex ID]
163. In 2013, MOG introduced an appeal before TAR Lazio against the note of the Ministry for the Environment to the MATTM services of 8 July 2013 requesting a supplement of investigation, including as for the granting of the AIA, and the subsequent communication of the MATTM to MOG/Rockhopper of 9 July 2013 with the request to submit all relevant information and documentation to obtain the AIA.
164. MOG claimed inter alia that the defendant would have violated general principles of good administration and relevant procedures for having requested a certification that was not deemed to be due, as well as its legitimate expectations to receive the due authorization. The Tribunal rejected all claims.
PROFESSOR MALAGUTI: Then I will continue briefly on the fork in the road, so we can finally get into the merits of the case. (Slide 32) On the fork in the road, I mean, I carefully heard what was said this morning, and I would say that basically we do not disagree on the principles of Article 26. I think the real disagreement is on whether the requirements are met in this particular case. The counsel for Claimants was already very kind in summarising the cases, so I don't think I need to get into details on what happened at the domestic level. Just a few clarifications. (Slide 35) First of all, in this specific case you do have one of the Claimants sitting here being the one who introduced the procedure at Italian level. I must say that of course -- we write it in our submissions -- if we keep using the triple identity test extremely formalistically, you never use the fork in the road, because it is always the case that a claimant uses its Italian domestic vehicle for its claims in the Member State territory; and then, even if it doesn't work, they can go with a company of the group and use an arbitration for getting exactly to the same point. So if you had this interpretation, there is no history, there is nothing to discuss. There is simply no effet utile of the fork in the road. In this specific case I think it's quite clear that the Italy company who is sitting here was the one starting the procedure in Italy, and also there was a clear challenge of exactly the same facts and circumstances that are challenged here, in terms of procedure and legitimacy of asking an AIA. Also it is tricky the way the Claimants present the fact of not having asked for compensation. They lost the case, so they could not get compensation. But it was exactly the reason why they were asking for that procedure to obtain compensation. I would simply say that we repeat what we said in our Memorial, and that we should apply what Professor Jan Paulsson stated in the Pantechniki case (CL-69). The real question to ask would be: "... whether or not 'fundamental basis of a claim' sought to be brought before the international forum is autonomous of claims to be heard elsewhere." We state that it is exactly the same issue, and compensation was asked under legitimate expectations also on that case.
[Tr. Day 1, pp. 80-81]
In 2013 a new minister of the Ministry of the Environment changed that position and required a further environmental permission process, the AIA, to be submitted. Now, clearly that was contrary to prior representation and decision of the relevant ministry, so the Claimants -- in this case the Claimant entity, the Italian subsidiary -- filed an action in the local courts in Italy seeking to annul that decision, essentially to annul the requirement to provide the further environmental permit. That application was made immediately after the decision to require them to do so was issued in 2013 and it took its time to proceed through the Italian court system. A judgment at first instance was handed down in April 2014, which decided that the ministry's additional requirement, as a matter of Italian administrative and environmental law, was lawful. Rockhopper's response to that was twofold: in the first instance, they sought to appeal that decision at first instance; but without prejudice to that, they submitted the AIA application, and both those processes proceeded in tandem. And what in fact happened, as was alluded to in the wider chronology that Mr Sprange presented, was that the AIA, including the EIA, was formally granted in August 2015. What that left was the appeal hanging, and the question of: well, what purpose does this appeal have, in circumstances where the AIA has now been granted and so annulling it is a moot point? And the position that was taken in those proceedings by Rockhopper was that they did have a purpose, in the sense that it was still worthwhile, potentially, to have a ruling on whether the additional environmental requirement had been lawful or not, because that may well be of relevance to any subsequent and separate -- and that's the important point -- separate legal proceeding in unspecified fora regarding any damages that might arise from those decisions of the ministry that had been challenged. The chronology proceeds that the Budget Law obviously occurred in around the end of 2015 and the production concession application was rejected in January 2016, and subsequent to that, that's when the Appeal Court in Italy upholds the first-instance judgment that determined that it was lawful to require the AIA, and that's where the proceedings in Italy ended.
...
[p. 85]
It's very much not the position where the Claimants in this case have, post-2016, said, "Well, the production concession has been rejected and now we're going to go to the Italian courts to challenge and seek an annulment of that production concession rejection, and also we want damages for that decision if we can't get specific performance to reverse that rejection". If that was the factual position, there would be more strength in Italy's argument. But the Claimants have taken an active position, after that production concession has been rejected, not to go to the local courts to challenge it or seek damages in relation to it. That highlights the fact that there's no causative link between the action in Italy and the action in this arbitration, because the causation in this case this week is not to do with delays and changes of position in terms of environmental permitting.
(1)
Investments of Investors of a Contracting Party in the Area of any other Contracting Party shall not be nationalised, expropriated or subjected to a measure or measures having effect equivalent to nationalisation or expropriation (hereinafter referred to as "Expropriation") except where such Expropriation is:
(a) for a purpose which is in the public interest;
(b) not discriminatory;
(c) carried out under due process of law; and
(d) accompanied by the payment of prompt, adequate and effective compensation.
Such compensation shall amount to the fair market value of the Investment expropriated at the time immediately before the Expropriation or impending Expropriation became known in such a way as to affect the value of the Investment (hereinafter referred to as the "Valuation Date").
Such fair market value shall at the request of the Investor be expressed in a Freely Convertible Currency on the basis of the market rate of exchange existing for that currency on the Valuation Date. Compensation shall also include interest at a commercial rate established on a market basis from the date of Expropriation until the date of payment.
(2) The Investor affected shall have a right to prompt review, under the law of the Contracting Party making the Expropriation, by a judicial or other competent and independent authority of that Contracting Party, of its case, of the valuation of its Investment, and of the payment of compensation, in accordance with the principles set out in paragraph (1).
(3) For the avoidance of doubt, Expropriation shall include situations where a Contracting Party expropriates the assets of a company or enterprise in its Area in which an Investor of any other Contracting Party has an Investment, including through the ownership of shares.
The MED's decision to deny Rockhopper Italia's Production Concession Application amounts to an expropriatory measure. With this decision, Rockhopper Italia no longer enjoyed the right—nor even the legitimate expectation—that it would be awarded the Production Concession to exploit the Ombrina Mare Field.
Italy's actions constitute an unlawful expropriation. Article 13 of the ECT provides that investments shall not be subject to Expropriation except where such Expropriation is (a) for a purpose which is in the public interest; (b) not discriminatory; (c) carried out under due process of law; and (d) accompanied by the payment of prompt, adequate and effective compensation. Where a treaty requires several conditions for a lawful expropriation "arbitral tribunals seem uniformly to hold that failure of any one of those conditions entails a breach of the expropriation provision". In Crystallex v Venezuela, the tribunal concluded that Venezuela was in breach of the applicable treaty because no prompt, adequate and effective compensation was either offered or provided to Crystallex. The tribunal therefore concluded that Venezuela had expropriated Crystallex's assets, even though the tribunal accepted Venezuela's public interest goal in expropriating the investment, did not find Venezuela in breach of the due process standard, and was not satisfied that there were conclusive elements to support that the expropriation was discriminatory. Thus, any expropriation that does not satisfy all of these elements is unlawful, and violates Article 13.
ITALY HAS NOT EXPROPRIATED CLAIMANTS' INVESTMENT
267. Claimants assert that MED's refusal to deny their concession application was expropriatory and amounted to a breach of Article 13 of the ECT.
268. Two reasons, which are autonomous from each other, are sufficient to dismiss this claim.
269. First, the extractive business of the Claimants never started and had never been authorised. Thus, it could not be expropriated to begin with.
270. Second, reasonable regulatory measures that a State passes to pursue societal policies without discriminating among its addresses constitute the legitimate exercise of police powers and, therefore, any economic impact that they might cause on investors is not compensable.
271. On the other side, the facts of the case are completely different from Metalclad. In that case the project had been already approved and endorsed by the central government, and the denial of the right to operate a landfill jeopardized a project otherwise fully authorised. In this case it is the very "approval and endorsement" of the central government that is missing.
272. The awards in the cases cited by the Claimants do not assist their case. In Occidental, Abengoa and Tecmed, the State measured discontinued or rescinded an existing legal relationship that underpinned the investment. In the present case, instead, the State measure did not interfere with an existing title, but simply acknowledged the impossibility to confer a new one to the Claimants.
273. Certainly, Italian law prevents the Claimants from starting extraction and, as far as Claimants has made preparatory expenditures with that purpose, these will be lost. However, it cannot be said that Italy deprived Claimants of their extractive business, because they had never been in the position to commence it.
274. More importantly, Italy owes no compensation for the incidental inconvenience caused by its regulatory measures of general application. Claimants conceded as much, when it tried to deny that Italy's measures had any public purpose.
275. Of course, the Prohibitions served instead the goal of adopting a cautionary approach to the protection of the environment, prohibiting new extractions in the sensitive areas close to the coasts and the protected zones. Italy therefore can indeed "justify its expropriation on the basis that it was acting in the public interest," thus averting Claimants' view that its acts constituted unlawful expropriation.
276. Claimants contended that the grandfathering of previously authorised extraction activities is discriminatory.
277. As noted above, the distinction, far from being unreasonable or arbitrary, is possibly even necessary to safeguard actual vested rights and avoid retroactive prohibitions.
278. Claimants' suggestion that the regime allows permit-holders to amend their work is irrelevant, because amendments are allowed only within the authorised terms, and the clarification made above should suffice to rebut the suggestion that any subject could carry out new extractions circumventing the 2016 Prohibition.
(1) The Tribunal must ascertain the facts. This process includes the making of findings on any facts which are in dispute. However, it must be remembered that not every fact put before the Tribunal, nor indeed every matter of factual dispute is relevant to the task at hand. The Tribunal has already ascertained the facts of the case as set out earlier in this Award.
(2) The Tribunal ascertains the law. In a case such as this one, bound by an international treaty such as the ECT, the primary focus is on such principles as may have been chosen by the sovereigns (and any other type of signatory) to form part of the appropriately interpreted text. Article 13 of the ECT is the applicable law and is recorded above.
(3) In the light of the facts and the law so ascertained, the Tribunal reaches its decision. In some cases, this third stage may be quite straightforward. Once the law is correctly ascertained, the decision follows inevitably from the application of it to the facts found. In other instances, however, the third stage involves an element of judgment on the part of an arbitrator or tribunal. There is no uniquely 'right' answer to be derived from marrying the facts and the law, merely a choice of answers, none of which can be described as 'wrong'. The Tribunal will now move to this third stage in light of the facts and the law.
First, the extractive business of the Claimants never started and had never been authorised. Thus, it could not be expropriated to begin with.
Second, reasonable regulatory measures that a State passes to pursue societal policies without discriminating among its addresses constitute the legitimate exercise of police powers and, therefore, any economic impact that they might cause on investors is not compensable.
164.2 a declaration that Italy has violated Part III of the ECT, including but not limited to Article 10 and Article 13, as well as international law, with respect to the Claimants' investments. Specifically, the obligations that Italy breached are: … its obligation not to unlawfully expropriate Rockhopper's investment as set out in Article 13 of the ECT.
In this arbitration, Rockhopper seeks and is entitled to full reparations for Italy's breaches of its obligations under the ECT and international law….
… reparation must, as far as possible, wipe out all the consequences of the illegal act and re-establish the situation which would, in all probability, have existed if that act had not been committed.23
… it is generally accepted today that, regardless of the type of investment, and regardless of the nature of the illegitimate measure, the level of damages awarded in international investment arbitration is supposed to be sufficient to compensate the affected party fully and to eliminate the consequences of the state's action.26
See, for example, MTD Equity Sdn. Bhd. and MTD Chile S.A. v. Republic of Chile, ICSID Case No. ARB/01/7, Award, 25 May 2004 ("MTD v. Chile"), ¶ 238 (CL-50); ADC Affiliate Ltd. and ADC & ADMC Management Ltd. v. Republic of Hungary, ICSID Case No. ARB/03/16, Award, 2 October 2006, ¶ 484 (CL-11); Biwater Gauff Ltd., v. Tanzania, ICSID Case No. ARB/05/22, Award, 24 July 2008, ¶¶ 775-776 (CL-19); Mr. Franck Charles Arif v. Republic of Moldova, ICSID Case No. ARB/11/23, Award, 8 April 2013 ("Arif v Moldova"), ¶ 559 (CL-35).
Vivendi, ¶ 8.2.7 (CL-115).
…[i]n this case, 29 January 2016 is an appropriate Date of Assessment because that is the effective date of the final and most significant measure that Claimants' challenge, namely, the denial of Claimants' Production Concession Application to develop and exploit the Ombrina Mare Field.32
Cl. Reply Memorial, ¶ 199, citing Gold Reserve Inc. v. Venezuela, ICSID Case No. ARB(AF)/09/1, Award, 22 September 2014, ¶ 830 (CL-39).
…it is a simple tool, so it is manageable for the administration; and it is an objective tool, because there are no factors such as the cost of money and other factors, but it carries out a net analysis of the economic result, on which several speculations can be made subsequently. So it is a basic platform that can be used with operators who also use different systems to assess investments when they make their submissions.51
it is undisputed that Claimants have never started extraction, nor did they ever receive the authorisation to commence operation. Moreover, and obviously, Claimants' investments, which were essentially limited to the exploratory stage, never yielded any profit.66
…[h]ow Claimants can validly argue that Mr. Boulton's opinions about a model outside of his expertise and built by someone else could somehow be helpful to the Tribunal is beyond comprehension of the Respondent.81
[t]his makes intuitive sense: in a declining oil market, it takes unusual circumstances for a company to gain value (e.g., new discoveries). I do not see any such circumstances occurring with Ombrina Mare between 2014 and the Valuation Date… More generally, I find that the very few component companies which showed unusually large stock price increases experienced exceptional events which increased their value against the industry average.86
…when Rockhopper acquired MOG, it paid €36 million for both oil assets and approximately €12 million in cash that was held by MOG. So, net of the cash that was already in MOG, Rockhopper acquired MOG's oil assets for considerably less than €36 million. I have conservatively ignored this fact, which would result in a valuation of less than €9 million for Ombrina Mare as of the Valuation Date.89
The majority of companies on this index did decrease in value over this period. However, the changes in share price ranges between an increase of 585% and a decrease of 99.98%. This range highlights the effect that specific risks have on oil and gas companies, and the inappropriateness of the comparable company approach for oil and gas concessions.98
… [Ombrina Mare] in MOG's hands was near worthless, because MOG did not have the means to actually develop the field. In contrast, the value of the asset in Rockhopper's hands better reflected its inherent fair market value (i.e. the DCF), because Rockhopper had the capital, expertise and commitment to commence production.101
Resp. Rejoinder, ¶ 280, citing Bear Creek Mining Corporation v. Republic of Peru, ICSID Case No. ARB/14/2, Award, 30 November 2017 (CL-165).
Resp. Rejoinder, ¶ 281, citing Caratube v. Kazakhstan (fn 68 above) (RL-23).
…should we value an asset by refer to what's been spent on it? […] almost always that's irrelevant because the fact that you've spent money on something doesn't mean it's worth what you spent. You may have spent money foolishly and be left with an asset that's not worth what you've spent, or you may have spent money on an asset that now has a very significant future value.111
…the application [of a DCF model] might be justified, inter alia, where the exploration of hydrocarbons is at issue. The determination of the future cash flow from the exploitation of hydrocarbon reserves need not depend on a past record of profitability. There are numerous hydrocarbon reserves around the world and sufficient data allowing for future cash flow projections should be available to allow a DCF calculation.127