• Copier la référence
  • Tutoriel vidéo

Final Award

Introduction

1.
The Claimant in this arbitration is Devas Multimedia Private Limited (Devas), a company incorporated under the laws of India with its principal place of business at Preema Gardenia, 357/6 1st Cross, 1 Block, Jayanagar, Bangalore 560 011, India. The majority of Devas’ shares are owned by Deutsche Telekom Asia Pte Ltd (DT Asia), Telcom Devas Mauritius Ltd (Telcom Devas) and CC/Devas (Mauritius) Ltd (CC/Devas).1
2.
The Respondent is Antrix Corporation Limited (Antrix), a company incorporated in India with its principal place of business at Antariksh Bhavan, Near New BEL Road, Bangalore 560 231, India. Antrix is wholly owned by the Government of India (GOÍ).
3.
Devas is represented in this arbitration by:

a. Skadden, Arps, Slate, Meagher & Flom (UK) LLP of 40 Bank Street, London E14 5DS, United Kingdom (UK);

b. Skadden, Arps, Slate, Meagher & Flom LLP of Four Times Square, New York, NY 10036, United States of America (USA);

c. Amarchand & Mangaldas & Suresh A. Shroff & Co of 216 Okhla Industrial Estate Phase III, New Delhi 110 020, India;2 and

d. Senior Advocates in India Messrs Harish Salve and Ciccu Mukhopadhaya.

4.
Antrix is represented by Curtis, Mallet-Prevost, Colt & Mosle LLP of 101 Park Avenue, New York, NY 10178, USA.
5.
The tribunal is comprised of Mr V.V. Veeder QC (of Essex Court Chambers, 24 Lincoln’s Inn Fields, London WC2A 3EG, UK), Dr Adarsh Sein Anand (of "Gurukripa" C-49, Sector 14, 201301 Noida (U.P.), India) and Dr Michael Pryles (of Level 26, 530 Collins Street, Melbourne, Victoria 3000, Australia).
8.
In June 2010, however, Dr K. R. Radhakrishnan - the Chairman of Antrix as well as the Secretary of India's Department of Space (DOS) and Chairman of the Indian Space Research Organisation (ISRO) (an entity that sits under the DOS) and India’s Space Commission13-sought and obtained legal advice about annulling the agreement.14 Devas says he did so in response to political pressure that had been created by media criticism of the Devas Agreement;15 Antrix says he did so because India’s military needed to use the spectrum that had been leased to Devas.16 As will become apparent, Dr Radhakrishnan’s motivation is not necessary to determine. The ultimate result of his conduct, however, was a decision by India’s Cabinet Committee on Security (CCS) to annul the agreement.17 Devas was notified of the CCS’ decision on 25 February 2011,18
9.
Devas subsequently commenced this arbitration. Devas alleges that Antrix was not entitled to terminate the Devas Agreement and repudiated its obligations by purporting to do so. Devas says that it has accepted that repudiation and is entitled to damages equal to the value of its business (which it claims is USD 1.41 billion), plus interest and costs.19
10.
Initially Antrix did not participate in this arbitration. It denied that the tribunal had jurisdiction, commenced a separate arbitration concerning the Devas Agreement under the UNCITRAL Arbitration Rules and applied to the Supreme Court of India for an order that an arbitrator be appointed on behalf of Devas for that arbitration. The Supreme Court rejected its application.20
11.
Since then Antrix has participated in this arbitration, although it maintains that the tribunal does not have jurisdiction. It also denies that it breached the Devas Agreement. It says that it was required and, under the agreement, permitted to terminate the agreement in light of the CCS’ decision. It says further that even if it did breach its obligations, the agreement contains a limitation of liability clause that precludes Devas from receiving any award of damages.
12.
Before considering the parties’ claims, the tribunal will set out the relevant procedural background, relevant facts and the applicable law(s). It will then turn to the issues of jurisdiction, liability, damages and interest. Finally, it will address the matter of the costs of this arbitration.

Procedural Background

13.
On 1 July 2011 Devas filed a Request for Arbitration dated 29 June 2011 in respect of this matter with the International Court of Arbitration of the International Chamber of Commerce (ICC Court), and nominated Mr Veeder QC as an arbitrator.
14.
In its Request, Devas relied on Article 20 of the Devas Agreement. Article 20 states:

"Article 20. Arbitration

a. In the event of there being any dispute or difference between the Parties hereto as to any clause or provision of this Agreement or as to the interpretation thereof or as to any account or valuation or as to the rights, liabilities, acts, omissions of any Party hereto arising under or by virtue of these presents or otherwise in any way relating to this Agreement such dispute or difference shall be referred to the senior management of both Parties to resolve within three (3) weeks failing which it will be referred to an Arbital [sic] Tribunal comprising of three arbitrators, one to be appointed by each party (i.e. DEVAS and ANTRIX) and the arbitrators so appointed will appoint the third arbitrator.

b. The seat of Arbitration shall be at NEW DELHI in India.

c. The Arbitration proceedings shall be held in accordance with the rules and procedures of the ICC (International Chamber of Commerce) or UNCITRAL.

d. The Arbitration Tribunal shall reach and render a decision or award in writing (concurred in by a majority of the members of the Arbital [sic] Tribunal with respect to the appropriate award to be rendered or remedy to be granted pursuant to the dispute, (including the amount that any indemnifying Party is required to pay to the indemnified Party in respect of a claim filed by the indemnified Party).

e. To the extent practicable all decisions of the board of Arbitration shall be rendered no more than 30 (thirty) days following commencement of proceedings with respect thereto. The Arbital [sic] Tribunal shall realize its decision on award into writing and cause the same to be delivered to the Parties.

f. Any decision or award made by the board of Arbitration shall be final, binding and conclusive on the Parties and entitled to be enforced to the fullest extent permitted by Laws and entered in any court of competent jurisdiction.

g. Each Party to any Arbitration shall bear its own costs or expenses in relation thereto, including but not limited to such Party's attorneys' fees, if any, and the expenses and fees of the member of the Arbital [sic] Tribunal appointed by such party, provided, however, that the expenses and fees of the third member of the Arbital [sic] Tribunal and any other expenses of the Arbital [sic] Tribunal not capable of being attributed to any one member shall be borne in equal parts by the Parties."

15.
Antrix did not file an Answer to Devas’ Request for Arbitration or nominate an arbitrator for this arbitration, but the tribunal understands that it informed the Secretariat of the ICC Court (Secretariat), on numerous occasions, that it denied that any arbitral tribunal constituted under the 1998 ICC Rules of Arbitration (ICC Rules) would have jurisdiction to decide Devas’ claims; and that the ICC Court should not proceed with this arbitration.
16.
As noted above, Antrix also sought to commence a separate arbitration against Devas pursuant to the UNCITRAL Arbitration Rules, and applied to the Supreme Court of India for:

"a direction upon Devas to nominate its Arbitrator in accordance with the Agreement dated 28th January, 2005, and the UNCITRAL Rules, to adjudicate the disputes, which had arisen between the parties and to constitute the Arbitral Tribunal and to proceed with the Arbitration".21

17.
On 19 August 2011 the Secretariat informed the parties that at its session of 18 August 2011 the ICC Court had decided that this arbitration shall proceed pursuant to Article 6(2) of the ICC Rules.
18.
On 14 September 2011 the Secretariat informed the parties that the ICC Court will appoint an arbitrator on Antrix’s behalf pursuant to Article 8(4) of the ICC Rules and fix the time limit for the co-arbitrators to select the chairman of the arbitral tribunal. On 3 October 2011 the Secretariat sent a reminder to the parties and informed them that the ICC Court will proceed to appoint an arbitrator on Antrix’s behalf, but that any nomination received from Antrix before the ICC Court makes the appointment will be communicated to the ICC Court. No nomination was received from Antrix.
19.
On 13 October 2011 the Secretariat informed the parties that at its session of the same date the ICC Court had: confirmed Mr Veeder QC as co-arbitrator nominated by Devas pursuant to Article 9(1) of the ICC Rules; appointed Dr Anand as co-arbitrator on Antrix’s behalf pursuant to Article 9(6) of the ICC Rules; and granted Mr Veeder QC and Dr Anand 20 days to jointly nominate a Chairman.
20.
On 26 October 2011 the Secretariat informed the parties that Mr Veeder QC and Dr Anand had advised that they would be unable to jointly nominate a Chairman within those 20 days due to Antrix’s pending application in the Supreme Court of India. The Secretariat asked the parties to indicate whether they agreed to the co-arbitrators being given until the conclusion of that proceeding to nominate a Chairman, failing which the ICC Court would be invited to appoint the Chairman pursuant to Article 8(4) of the ICC Rules. The next day, Devas requested that the ICC Court appoint the Chairman. Antrix raised objections to the arbitral tribunal moving forward and to the constitution of the tribunal.
21.
On 10 November 2011 the ICC Court appointed Dr Pryles as the Chairman of the tribunal upon the Australian National Committee’s proposal, pursuant to Article 9(3) of the ICC Rules.
22.
On 14 November 2011, Dr Pryles wrote to the parties and made the following disclosure:

"I note that counsel from three firms are representing the Claimant, including Ciccu Mukhopadhaya of Amarchand & Mangaldas & Suresh A. Shroff & Co. I wish to point out, although I believe it is unnecessary to do so under the IBA Guidelines on Conflict of Interest in International Arbitration nor the ICC Rules of Arbitration, that Mrs Pallavi S Shroff of that firm is a member of the Board of Directors of the Singapore International Arbitration Centre (SIAC) of which I Chair. Members of the Board of Directors are not renumerated and SIAC is a not-for-profit company limited by guarantee. Mrs Shroff does not appear to be involved in this arbitration."

23.
On 24 November 2011 Antrix wrote to the Secretariat and stated (inter alia) that "there is definitely a conflict of interest involved" on the part of Dr Pryles. On 29 November 2011 the Secretariat informed Antrix that any challenge to an arbitrator must be made in accordance with Article 11 of the ICC Rules, and invited Antrix to state whether it wished to make a challenge concerning Dr Pryles. No challenge was made.
24.
Also on 29 November 2011, the tribunal sought submissions from the parties on what the language of this arbitration should be. Devas submitted that the language should be English. Antrix did not respond.
25.
On 16 December 2011 the Secretariat informed the parties that it had not heard from Antrix regarding any challenge to Dr Pryles and that unless otherwise advised, it understood that Antrix did not challenge Dr Pryles.
26.
On 30 December 2011 Antrix informed the Secretariat that it had filed an application before an Additional City Civil Judge in Bangalore for an "injunction restraining Devas from proceeding in any manner with the purported arbitration before the ICC". The tribunal understands that the application was made under section 9 of the Indian Arbitration and Conciliation Act 1996, seeking an order permanently restraining this arbitration from proceeding.
27.
Also on 30 December 2011, the Secretariat informed the arbitral tribunal and the parties that at its session of 8 December 2011, the ICC Court extended the time limit for the terms of reference until 29 February 2012, pursuant to Article 18(2) of the ICC Rules.
28.
On 10 January 2012 a preliminary conference was held to discuss draft terms of reference, the language of the arbitration, the appointment of a tribunal secretary and the procedural timetable. The conference was held by telephone and was attended by each member of the tribunal and representatives of Devas. Antrix was invited to attend but declined to do so.
29.
On 13 January 2012 the tribunal issued Procedural Order 1 (which specified that the language of the arbitration shall be English) and a provisional procedural timetable (which provided for an oral hearing on 12 and 13 April 2012). The tribunal had previously invited the parties to comment on both Procedural Order 1 and the procedural timetable. The tribunal also advised the parties that Devas had agreed, and Antrix had not objected, to the appointment of Mr Robert Kovacs as tribunal secretary.
30.
On 19 January 2012 Mr Kovacs was appointed as the tribunal’s secretary.
31.
On 9 February 2012 the ICC Court extended the time limit for the terms of reference until 31 March 2012.
32.
On 8 March 2012 the terms of reference were approved by the ICC Court pursuant to Article 18(3) of the ICC Rules.22
33.
On 9 March 2012 the Secretariat sent the terms of reference (as approved by the ICC Court) to Antrix and invited Antrix to sign the terms of reference. Antrix did not respond.
34.
On 9 April 2012 the Supreme Court of India ordered that:

"the arbitral proceedings before the learned Arbitrator, appointed under the ICC Rules, shall remain stayed".

35.
In light of this order, the hearing scheduled for 12 and 13 April 2012 did not proceed and the conduct of this arbitration was suspended. The Supreme Court’s order remained in place until 10 May 2013, when it dismissed Antrix’s application. Antrix filed a Review Petition but, on 29 August 2013, that too was dismissed.
36.
On 13 May 2013 Devas asked that the tribunal proceed with this arbitration, and on 24 June 2013 the tribunal directed that the arbitration would proceed.
37.
On 8 August 2013 Antrix advised that it would be participating in this arbitration and represented by Curtis, Mallet-Provost, Colt & Mosle LLP (Curtis). Curtis then advised the tribunal that Antrix wished to file a statement of defence together with supporting factual and expert evidence, without prejudice to its jurisdictional objections.
38.
On 9 August 2013 the tribunal proposed that Mr Andrew Barraclough replace Mr Robert Kovacs as the tribunal’s secretary. Both parties consented to the appointment of Mr Barraclough and, on 15 August 2013, the tribunal confirmed his appointment.
39.
On 3 September 2013 the tribunal held a case management conference. Matters that were addressed during the conference included the procedural timetable, preparation for the final hearing and potential dates and locations for that hearing.
40.
On 11 September 2013 Antrix applied for certain legal issues to be resolved as preliminary questions - namely, whether the tribunal has jurisdiction to decide Devas’ claims and, if it does, whether the available remedies for any breach of the agreement are limited to a refund of the UCRF. After receiving further submissions from both parties in respect of the application, on 2 October 2013 the tribunal notified the parties that it did not consider that the issues raised by Antrix should be decided as preliminary questions.
41.
On 11 October 2013, after consulting with the parties, the tribunal directed that the hearing would be held in the week beginning 15 December 2014 in New Delhi. It later transpired that, for serious medical reasons, one of the tribunal members, based in London, may have been unable to attend the hearing if it took place in New Delhi at that time. In light of this, and the long delay in the arbitration (as noted above the hearing was originally scheduled to take place in April 2012), the geographical venue of the hearing was moved to London (without howsoever affecting the place or seat of this arbitration).
42.
On 8 November 2013 the tribunal issued Procedural Order 2 after consulting with the parties. Both parties agreed to the inclusion of the following provision in Procedural Order 2:

"[t]he IBA Rules on the Taking of Evidence in International Arbitration (2010) ("IBA Rules") shall serve as a guide in the determination of evidentiary issues."

43.
The oral hearing of this arbitration was held in London from 15 to 20 December 2014.
44.
By the time of the hearing, the parties had submitted the following materials to the tribunal:

a. Pleadings / submissions

i. Devas’ Statement of Claim dated 20 February 2012 (Statement of Claim)

ii. Antrix’s Statement of Defence dated 15 November 2013 (Statement of Defence)

iii. Devas’ Reply dated 24 March 2014 (Reply)

iv. Antrix’s Rejoinder dated 1 August 2014 (Rejoinder)

v Devas’ Skeleton Argument dated 1 December 2014 (Devas’ Skeleton) vi. Antrix’s Skeleton Argument dated 1 December 2014 (Antrix’s Skeleton)

b. Witness statements - Devas

i. Statement of Gary Parsons dated 18 February 2012 (Parsons 1)

ii. Statement of Arun Gupta dated 19 February 2012 (Gupta 1)

iii. Statement of Lawrence T. Babbio Jr dated 19 February 2012 (Babbio 1)

iv. Statement of Dr Rajendra Singh dated 19 February 2012 (Singh 1)

v. Statement of Ramachandran Viswanathan dated 20 February 2012 (Viswanathan 1)

vi. Reply Statement of D. Venugopal dated 15 March 2014 (Venugopal)

vii. Reply statement of M. G. Chandrasekhar dated 15 March 2014 (Chandrasekhar)

viii. Reply statement of Dr Kim Larsen dated 19 March 2014 (Larsen)

ix. Reply statement of Gary Parsons dated 21 March 2014 (Parsons 2)

x. Reply statement of Lawrence T. Babbio Jr dated 23 March 2014 (Babbio 2)

xi. Reply statement of Ramachandran Viswanathan dated 24 March 2014 (Viswanathan 2)

xii. Reply statement of Rajendra Singh dated 24 March 2014 (Singh 2)

xiii. Reply statement of Arun Gupta dated 24 March 2014 (Gupta 2)

c. Witness statements - Antrix

i. Statement of Vijay Anand dated 15 November 2013 (Anand)

ii. Statement of K. Sethuraman dated 15 November 2013 (Sethuraman 1)

iii. Statement of Dr V. S. Hegde dated 30 July 2014 (Hegde)

iv. Supplemental statement of K. Sethuraman dated 31 July 2014 (Sethuraman 2)

d. Expert reports - Devas

i. Report of John Lewis dated 17 February 2012 (Lewis 1)

ii. Report of Brent Kaczmarek dated 20 February 2012 (Kaczmarek 1)

iii. Reply report of John Lewis dated 14 March 2014 (Lewis 2)

iv. Reply report of Brent Kaczmarek dated 24 March 2014 (Kaczmarek 2)

v. Report by Brent Kaczmarek on the areas of disagreement with Vladimir Brailovsky and Daniel Flores dated 30 September 2014 (Kazcmarek3)

vi. Supplemental report of Brent Kaczmarek dated 17 October 2014 (Kazcmarek 4)

e. Expert reports - Antrix

i. Report of Vladimir Brailovsky & Daniel Flores dated 15 November 2013 (Brailovsky/Flores 1)

ii. Second report of Vladimir Brailovsky & Daniel Fiores dated 1 August 2014 (Brailovsky/Flores 2)

iii. Report by Vladimir Brailovsky and Daniel Flores on the areas of disagreement with Mr Kaczmarek dated 30 September 2014 (Brailovsky/Flores3)

iv. Supplemental Report by Vladimir Brailovsky and Daniel Flores dated 11 December 2014 (Brailovsky/Flores 4)

f. Other

i. An agreed "dramatis personae"

ii. An agreed list of abbreviations

iii. Separate chronologies of relevant events

iv. A transcript of the hearing in another arbitration concerning the Devas Agreement, CC/Devas (Mauritius) Ltd et al v Republic of India, PCA No. 2013-09. The parties agreed that this transcript, which records testimony of a number of Devas’ and Antrix’s witnesses, would be admitted as evidence in this arbitration.

45.
Following the hearing, the parties submitted the following materials to the tribunal:

a. Devas’ post-hearing memorial dated 17 February 2015 (Devas’ PHM)

b. Antrix’s post-hearing memorial dated 17 February 2015 (Antrix’s PHM)

c. Devas’ post-hearing reply memorial dated 23 March 2015 (Devas’ PHRM)

d. Antrix’s post-hearing reply memorial dated 23 March 2015 (Antrix’s PHRM)

e. Devas’ submission on costs dated 10 April 2015

f. Antrix’s submission on costs dated 10 April 2015

46.
On 14 August 2015 the tribunal declared this proceeding closed pursuant to Article 27 of the ICC Rules.
47.
The initial time limit for rendering the final award was 9 September 2012 pursuant to Article 24(1) of the ICC Rules. Pursuant to Article 24(2) of the ICC Rules, the following extensions of time were granted by the ICC Court for the final award:

a. on 9 August 2012, until 31 January 2013;

b. on 10 January 2013, until 30 April 2013;

c. on 11 April 2013, until 31 July 2013;

d. on 11 July 2013, until 31 October 2013;

e. on 10 October 2013, until 31 October 2014;

f. on 16 October 2014, until 31 March 2015;

g. on 12 June 2015, until 30 June 2015; and

h. on 11 June 2015, until 30 September 2015.

Relevant Facts

48.
The following section contains facts that are either not disputed or agreed, as well as findings of fact by the tribunal.

Relevant GOI entities

49.
As will become apparent, a number of GOI entities are relevant to this arbitration. They are:

a. the Department of Telecommunications (DOT), which is responsible for the provision of telecommunication services;

b. the Wireless Planning and Coordination wing (WPC) of the DOT, which is responsible for (inter alia) issuing radio licenses and allocating and monitoring radio frequency spectrum;23

c. the DOS, which is responsible for space policy development and implementation of the Indian space programme. The DOS sits directly under the Prime Minister’s office and its Secretary reports directly to the Prime Minister. Antrix is described in the Devas Agreement as "a marketing arm" of the DOS;24

d. ISRO, which is responsible for developing space technology and its applications. ISRO sits under the DOS. Its primary responsibility is to build, launch, operate and lease satellites for national uses, including telecommunications, for both the public and private sectors. Antrix is described in the Devas Agreement as the "entity through which ISRO engages in commercial activities";25

e. the Space Commission, which includes the Minister of State, the National Security Advisor, the Cabinet Secretary, the Principal Secretary to the Prime Minister and the Secretary for GOI Economic Affairs in the Ministry of Finance, as well as senior directors of ISRO centres, with its secretary being the Additional Secretary DOS.26 The scope of the Space Commission’s responsibilities was not entirely clear from the evidence, but it appears to report directly to the Prime Minister27 and, as discussed below, it was involved in key decisions in relation to this arbitration, including the decision to annul (terminate) the Devas Agreement; and

f. the CCS, which is the ultimate authority within India on matters of internal and external security and defence.28 It is comprised of the Prime Minister, the Minister of Defence, the Minister of Home Affairs, the Minister of External Affairs and the Minister of Finance. The functions of the CCS include dealing with, inter alia, defence related issues, issues relating to law and order and internal security, policy matters concerning foreign affairs that have internal or external security implications (including cases relating to agreements with other countries on security related issues) and economic and political issues impinging on national security.29

50.
At all relevant times, the Secretary of the DOS, the Chairman of ISRO, Chairman of the Space Commission and the Chairman of Antrix were the same person, namely:

a. Dr Kasturirangan until August 2003;

b. Dr Nair from September 2003 to October 2009; and

c. Dr Radhakrishnan from November 2009.

International regulation of radio frequencies

51.
It is also necessary to provide a brief overview of the international regulation of radio frequencies. There are a limited number of available radio frequencies in the world, which are known by names such as C, extended C band, Ku, and S-band.30 As radio frequencies do not stop at national boundaries, governments have sought to regulate their allocation through the International Telecommunications Union (ITU), an agency of the United Nations.31
52.
The ITU is responsible for allocating available spectrum amongst its member States.32 Once it has allocated spectrum to a State, that State is then free to distribute the spectrum in accordance with its national laws.33
53.
By the early 1970s, the ITU had allocated the use of the S-band radio frequency in India to the GOI, and the GOI had allocated the right to use S-band in India to the DOS.34 The S-band frequency consists of several radio frequencies, including the 2.5 gigahertz (Ghz) band (i.e. frequencies from 2.5 Ghz to 2.69 Ghz).35
54.
Once an entity has been allocated a particular frequency,it typically seeks to launch a satellite into the earth’s orbit (or an "orbital slot") so that it can use that frequency to provide radio communication services.36
55.
Orbital slots are also regulated by the ITU.37 If a member State wishes to use a particular slot it must file a "co-ordination request" with the ITU.38 Slots are then allocated on a "first come, first served" basis, although member States must co-ordinate with other countries whose satellite networks might be affected by the orbital slots that they use.39
56.
To ensure that member States do not file co-ordination requests in respect of slots that they have no present intention of using, there is also a "use it or lose it" policy.40 Member States have seven years from the date of the initial coordination request to build and bring into operation the satellite in the designated orbital slot.41 Further, if a member State wishes to modify an existing coordination request, it has five years from the date of the modification filing to bring the modified or new satellite into use.42
57.
As discussed further below, the orbital slot that is relevant to this proceeding is the 83°E slot. The GOI submitted a coordination request in respect of that slot in 1994 (for a satellite named INSAT-2(83)), which it modified in December 200543

India’s SATCOM policy

58.
In early 2003, India’s Satellite Communication (SATCOM) policy provided for satellite capacity "to be leased to non-government (Indian and foreign) parties".44 It also stated that "[e]ncouraging the private sector investment in the space industry in India and attracting foreign investments in this area are other specific goals"45
59.
At the time, Dr Kasturirangan (the Secretary of DOS and the Chairman of ISRO, the Space Commission and Antrix) began speaking with Mr Viswanathan of Forge Advisors LLC (Forge Advisors), a consultancy firm with expertise in telecommunications.46 Mr Viswanathan was informed that the GOI had previously re-allocated 40 MHz of S-band spectrum from the DOS to the DOT, because the DOS had not used the spectrum efficiently and did not have plans to do so.47 Accordingly, the DOS needed to use its remaining satellite S-Band spectrum or face the possibility that the GOI would re-allocate it.48
60.
A briefing note from DOS to the Space Commission states that:

"ISRO initiated serious discussions in early 2003 for introduction of Satellite-based Digital Multimedia in the country, especially taking note of the fact that the allocation of the S-Band spectrum for ISRO/DOS... would expire by September 2010 unless [DOS/ISRO] place[d] S-Band Satellites in the orbit and demonstrate that necessary advance actions to build the Satellites have been taken".49

61.
The discussions between Dr Kastuurirangan and Mr Viswanathan led to Forge Advisors and Antrix signing, on 28 July 2003, a Memorandum of Understanding (MOU) with:

a. a "near-term objective" of Forge Advisors "supporting Antrix by undertaking a series of discrete tactical projects in the area of sales, marketing, business development, and other related arenas"; and

b. a "long-term objective" of building "a strategic partnership that leverages Antrix's satellite & space capabilities to enable new social & commercial applications".50

Forge Advisors’ proposal for a hybrid satellite-terrestrial communications system

62.
In March 2004 Forge Advisors proposed a joint venture between Forge Advisors and ISRO/Antrix that involved the provision of satellite derived video, audio, information and telematics services.51 In a letter to representatives of Antrix and ISRO dated 15 April 2004, Mr Viswanathan described the proposed joint venture as a "partnership to launch DEVAS, a new service that delivers video, multimedia and information services via satellite to mobile receivers... across India."52
63.
The proposal was for a hybrid satellite-terrestrial communications system that combined a satellite and a series of ground-based towers.53 Services would be provided to rural communities via the satellite signal alone and to consumers in urban areas by incorporating a network of towers. The towers would essentially re-use the frequencies used by the satellites. This would permit urban consumers whose line of sight to the satellite was blocked (e.g. by buildings) to still receive a signal.54
64.
Forge Advisors proposed that ISRO and Antrix would construct, launch and operate the required satellite network (as well as procure the required regulatory permits) and that Devas would develop services for the consumer and commercial market segments, operate the broadcast and ground network, market and sell to customers, and provide customer support.55

The Devas Agreement

65.
Ultimately, Forge Advisors was informed that ISRO and Antrix were not interested in a joint venture arrangement and preferred a straight lease agreement with a higher UCRF.56 Forge Advisors ultimately agreed to this. Accordingly, on 28 January 2005 Devas and Antrix executed the Devas Agreement.57
66.
Antrix’s obligations under the Devas Agreement included the following:

a. Antrix was required to build, launch and operate a primary satellite system (PSÍ)58 and, at the option of Devas, a secondary satellite system (PS2),59 and to lease transponder capacity in the S-band on those satellites to Devas;60

b. the leased capacity was for 12 years.61 At the time the agreement was executed, it provided that it would be "put up for renewal... for another twelve (12) years... at Lease Fees to be mutually agreed upon".62 The parties later agreed to a variation which required the fees under any renewed lease to be "reasonable";63

c. the leased capacity was "Non-Preemptible", meaning that it could not be utilised or repurposed for use by another party during the life of the satellite unless Devas was in default of its obligations or payments;64

d. PS1 was to be fully operational and ready within 36 months65 of the payment of the first instalment of the UCRF.66 It was to be launched into the 83°E orbital slot,67 and delivery was deemed to have taken place once in-orbit testing was completed by Antrix and accepted (in writing) by Devas;68 and

e. Antrix was responsible for obtaining "all necessary Governmental and Regulatory Approvals relating to orbital slot and frequency clearances, and funding for the satellite to facilitate DEVAS services".69 Antrix was also required "through ISRO/DOS" to obtain "clearances from National and international agencies (WPC, ITU, etc.) for use of the orbital slot and frequency resources" necessary to provide the leased capacity.70

67.
In return, Devas was required to pay to Anrix:

a. UCRF of USD 20 million per satellite in three equal instalments;71 and

b. a lease fee of USD 9 million (initially), and USD 11.25 million per annum when Devas became cash flow positive.72

68.
Accordingly, Antrix could expect to receive approximately USD 256 - 310 million in fees if both satellites were launched and the lease was renewed on similar terms. The GOI calculated that the "Internal Rate of Return (IRR) for the two satellites was 13.8%."73
69.
The parties agreed that they "intend to discharge their obligations in utmost good faith" and "will, at all times, act in good faith, and make all attempts to resolve all differences howsoever arising out of or in connection with this Agreement by discussion".74
70.
As discussed below, the agreement also specifies that its governing law is Indian law;75 it provides that any disputes that arise between the parties are to be resolved by arbitration;76 and it contains detailed provisions concerning "force majeure",77 termination78 and indemnities.79
71.
The agreement was to become "effective on the date that ANTRIX is in receipt of all required approvals and communicates to DEVAS in writing regarding the same".80 As discussed below, that occurred on 2 February 2006.

Cabinet approval and further ITU filings

72.
On 1 December 2005 the GOI's Press Information Bureau formally announced that the Union Cabinet had given its approval to undertake the design, development and launch of PS1. The press release described the benefits that the GOI anticipated receiving from the Devas Agreement as including "[a] state-of-the art National Satellite System with coverage exclusively devoted to entire population of India" and "[c]apacity to deliver over ten video channels and over ten audio channels in each beam (which will grow over time through better digital transmission, encoding and compression technologies)".81
73.
Soon after Cabinet approval was obtained, the GOI submitted a modified filing at the ITU in respect of the 83°E slot.82 Although the GOI had previously made a coordination request in respect of the 83°E slot (for the INSAT-2(83) satellite),83 the Devas Agreement specified that PS1 was to use five "spot beams" in specific S-band frequencies84 from that slot.85 The GOI had not previously coordinated the use of a satellite using a five spot beam configuration. The modified filing sought to do so, and was capable of being used for PS1,86

Commencement of the Devas Agreement and Devas’ procurement of funding

74.
As noted above, the Devas Agreement was to become "effective on the date that ANTRIX is in receipt of all required approvals and communicates to DEVAS in writing regarding the same".87 That occurred on 2 February 2006, when Antrix notified Devas that it had obtained the "necessary approval for building, launching and leasing the capacity of S-band satellite," and was "in a position to go ahead with the building and launch" of PS1.88
75.
Soon after, a number of venture capital firms agreed to invest in Devas’ business. On 16 March 2006 Telcom Devas and CC/Devas each agreed to invest USD 7.5 million in return for 15,730 Series A Preference Shares (which amounted to 19,001% of all Devas shares), as well as one equity share.89 The GOI’s Foreign Investment Promotion Board approved the investments and, in May 2006, Telcom Devas and CC/Devas each received 19% of the shares in Devas.
76.
According to Devas’ expert witness, Mr Brent Kazcmarek, the investment by Telcom Devas and CC/Devas gave Devas an implied value of about USD 40 million.90 It also provided Devas with the capital necessary to make the first payment of the UCRF for PS1. On 21 June 2006 Devas made that payment, which totalled approximately USD 7 million.91 This meant that, under the Devas Agreement, Antrix was required to deliver leased capacity from a fully operational and ready PS1 within 36 months.92
77.
On 11 June 2007 CC/Devas and Telcom Devas agreed to make a further investment in Devas, and entered into a Series B Share Subscription Agreement.93 Pursuant to that agreement they each invested a further USD 7,499,715.67 in exchange for 11,978 Series B Preference Shares.
78.
This additional capital permitted Devas to pay to Antrix the UCRF for PS2. On 18 June 2007 Devas paid that fee (again for approximately USD 7 million), thus exercising its right to secure Leased Capacity on the second satellite, and requiring Antrix to have PS2 launched and fully operational within 30 months.94
79.
Devas next began to look for a strategic partner that could assist in the roll-out of Devas’ services throughout India.95 It approached a subsidiary of Deutsche Telekom (DT). After examining Devas’ business plan (including its model of the cost of building, operating and maintaining an appropriate terrestrial network), travelling to India and meeting with representatives of Antrix and ISRO (including Dr Nair), DT decided to invest in Devas.96 On 19 March 2008 Devas and an investment vehicle named DT Asia executed a Class C Share Subscription Agreement,97 pursuant to which DT Asia received 28,349 Class C Shares in return for an investment of approximately USD 75 million.
80.
The parties’ expert witnesses agree that DT Asia’s investment in Devas is indicative of the fair market value of the business as of this point in time. Mr Kaczmarek (Devas’ expert witness) considers that it implies that the fair market value of Devas in March 2008 is at least USD 375 million on the basis that DT provided various "in kind" contributions to Devas.98 Mr Brailovsky (one of Antrix's expert witnesses) considers that it implies that the fair market value of Devas in March 2008 is no more than US$ 375 million,99 because the Class C shares that DT acquired "included rights not held by other shareholders, such as a right of first refusal, the right to name more directors than in proportion to the subscription, and some veto rights".100
81.
The tribunal does not agree with Mr Brailovsky. The evidence of Mr Larsen demonstrates that DT made a considerable contribution to Devas in addition to the price it paid for Devas’ shares. Among other things it provided 20 to 25 senior DT engineers and other technical specialists to plan Devas’ terrestrial network,101 as well as purchasing power for network, transport infrastructure, IT systems and IP equipment.102 Mr Brailovsky’s suggestion that DT Asia received "special rights" is an unsupported assertion, and is not borne out by the tribunal’s examination of the shareholder agreement.103 When cross-examined he admitted that DT "brought a lot into the project."104
82.
However, there is also no evidence that would permit the tribunal to place a value on the "in kind" contribution that DT provided. Accordingly, the tribunal is not in a position to find that DT Asia’s investment in Devas valued the company at any more than USD 375 million. The tribunal therefore finds that the investment valued Devas at USD 375 million.

Delays in the launch of PS1

83.
On 11 April 2009 members of the Devas team met with senior Antrix and ISRO officials and were informed that there would be a delay in the launch of PS1. They were told that, despite the June 2009 deadline for launching PS1,105the satellite would not be launched until "early 2010".106 According to Devas, this delay entitled it to damages under the Devas Agreement, but it elected not to seek damages because it expected (at that time) the delay to be for a relatively short period of time.107

ISP licence

84.
Devas was required to obtain a number of licences in order to provide the telecommunications services that it planned to provide. One of those licences was an internet service provider (ISP) licence, which it received on 2 May 2008.108 It later received approval from the DOT to provide Internet Protocol Television (IPTV) services.109 With the ISP and IPTV licences, Devas had permission to provide a portfolio of services that included digital television, video on demand and other types of entertainment to users in urban and rural areas.

Experimental trials

85.
On 20 August 2008 Devas submitted an application to the WPC for an experimental licence to test the wireless apparatus that underscored the Devas system.110 On 7 May 2009 the WPC issued the experimental licence, which permitted Devas to conduct an "Experimental/Trial of wireless equipment at Bangalore". With the licence, Devas was able to use the frequencies in the 2.5-2.69 GHz band to test run the entire Devas system, including terrestrial reuse of spectrum.111
86.
The trials were performed in Bangalore between June and September 2009. They involved trials and demonstrations of the capabilities of the Devas system, including mobile multimedia and broadband wireless services.112 As PS1 had not been launched, the satellite that was used for the trials was an "INSAT-3C" satellite that was owned (and operated during the trials) by the DOS/ISRO.113
87.
Devas considered that the trials were "extremely successful".114 Towards the end of the trials, it had a ceremony at its new office in Bangalore that was attended by (inter alia) Dr Nair and Dr Radhakrishnan.115 During the ceremony, Dr Radhakrishnan said that the Devas-Antrix partnership was "great" and that he was looking forward to the launch of PS1.116

Further financing

88.
After being notified that there would be delays in the launch of PS1, Devas elected to seek further capital from its investors. It asked investors for a "cash-cushion so that services could be ramped up quickly once the satellite was launched."117
89.
Each of Telcom Devas, CC/Devas and DT Asia agreed to provide further funding. Accordingly, on 14 September 2009 Devas sought approval for a new round of investment from the Foreign Investment Promotion Board and, on 29 September 2009, it received that approval. On the same day, Devas entered into a Share Subscription Agreement with each of Telcom Devas, CC/Devas and DT Asia pursuant to which Telcom Devas and CC/Devas each invested an additional USD 1,388,951.24 (for a further 525 Class C shares) and DT Asia invested USD 22,223,219.76 (for a further 8,400 Class C shares).118

Dr Radhakrishnan becomes Chairman of Antrix

90.
On 29 October 2009 Dr Radhakrishnan was appointed as the Chairman of Antrix, as well as the Secretary of the DOS and Chairman of ISRO and the Space Commission.119
91.
Soon after, the DOS received a complaint about "irregularities in connection with the [Devas] Contract".120 Dr Radhakrishnan commissioned Dr B. N. Suresh, Director of the Indian Institute of Space and Technology, to undertake "comprehensive review of all aspects" of the Devas Agreement.121
92.
At around this time, Devas started being informed of further delays to the launch of the satellites. On 11 or 12 November 2009, during "joint status review" meetings with Antrix, Devas was informed that the launch of the satellites had been delayed, and was now planned for 19 June 2010.122 However, PS1 was nearing the final stages of its construction; there were only "a few defined areas that needed focused attention" in order to be prepared for that launch date.123

Military needs for S-band

93.
On 15 December 2009, during a meeting with members of (inter alia) the Ministry of Defence "to discuss the Bandwidth requirements of services for satellite communication",124 ISRO was informed that India’s Armed Forces required the ability to use the S-band. The Armed Forces’ requirements were stated to be as follows:

"[t]o cater for requirements up to 2012 - 120 Carriers, 17.5 MHz. Out of which 50 Carriers are being used by the Armed Forces, (ii) Additional in 12th Plan - 40 MHz. (iii) Additional in 13th Plan - 50 MHz".125

94.
According to Antrix, this was the "crystallisation" of demands that the Armed Forces had been making on S-band since 2005.126
95.
Soon after, Devas was informed of further delays to the launch of PS1. On 30 December 2009, Devas was told that "Antrix/ISRO is putting all efforts to meet the launch schedule of July 2010",127 and on about 4 February 2010, Dr Radhakrishnan informed Devas that there was now a new deadline for launching the satellites of 1 September 2010.128
96.
Dr Suresh completed his review of the Devas Agreement in May 2010.129 His report did not find any wrongdoing in connection with the execution of the Devas Agreement. He found (inter alia) that:

a. the Devas Agreement was only executed after "technical feasibility, financial and market aspects, time schedule, risk mitigation" and "pricing" had been scrutinised by a "High Power Committee" comprised of specialist "ISRO Centres and also Additional Secretary and Joint Secretary of DOS";

b. Antrix entered into the agreement "in close coordination & participation of SCPO, ISRO HQ and other concerned agencies";

c. Antrix followed "guidelines for leasing the transponder services to private service providers as per the Satcom policy";

d. "[t]here is absolutely no doubt on the technical soundness of the digital multimedia services as proposed in this hybrid satellite and terrestrial system";

e. "[o]nly 10% of the capacity is available for use by ISRO" which would "bring in limitations on spectrum availability for essential strategic and social sectors applications in future"; and

f. "[t]he utilization of the S-band frequency spectrum allotted for satellite bases services to ISRO/DOS for satellite communications is extremely important. Therefore this aspect has to be critically examined considering all usages including GSAT-6 and GSAT-GA by a competent technical team on high priority. The strategic and other essential needs of the country should also be considered".130

Articles: The Hindu Business Line

97.
On 30 May 2010 an article concerning the Devas Agreement was published in The Hindu Business Line.131 Among other things, the article states that "[a]t a time when telecom operators are aggressively bidding in crores of rupees for acquiring spectrum, a little-known company in Bangalore, Devas Multimedia Pvt Ltd, has got preferential allocation of air waves controlled by the Indian Space Research Organisation by virtue of an agreement the two signed five years ago". It states that neither the amount of S-band spectrum allocated to Devas nor the price that Devas paid for that spectrum had been disclosed, but S-band was "a golden band that broadband wireless access operators covet worldwide" and that "Telecom industry players, who are scrounging for bandwidth, are raising eyebrows over the contract between Antrix and Devas".
98.
On 1 June 2010 a second article concerning the Devas Agreement was published in The Hindu Business Line. Its title was "[a]nother spectrum sold on the quiet".132 Among other things, it stated:

"[i]t is time the Government realised that a transparent mechanism is needed to supervise the sale of scarce assets... There is a simple principle in economics: if it is scarce, charge for it. And if there is one thing that is scarce today in relation to the demand for it, it is spectrum. But the cruel will say that it is perhaps too much to expect space scientists at the Indian Space Research Organisation (ISRO) to be aware of this sine qua non of economics and commerce. That is probably why that organisation has, in a rather mysterious way, allocated spectrum for an undisclosed sum to Devas Multimedia Private Limited, a company formed by some ex-ISRO employees."

99.
The article goes on to say that "[p]ast experience has shown that smart footwork by the sellers — who only have a fiduciary role — comes to public notice only after the deed is done. Then, as we have seen in the case of the 2G scandal, the Government is forced to hide behind technicalities and half-truths." This was a reference to an allegation (discussed below but not otherwise related to the parties' dispute in this arbitration) that the GOI had previously undervalued the 2G spectrum and sold it to favoured companies. The article also states: "there really isn't much to think about: the 2005 agreement should be annulled and the ISRO quota should be auctioned so that the Government can raise some more much-needed money".
100.
On 4 June 2010 the DOT wrote to Mr G. Balachandhran of ISRO enclosing the two articles and asking for a comment "immediately".133

Response from Dr Radhakrishnan to the articles in The Hindu Business Line

101.
On 14 June 2010 the DOT wrote to Dr Radhakrishnan enclosing the two articles, noting that Mr G. Balachandhran had not responded to its 4 June 2010 letter and asking Dr Radhakrishnan to "look into the matter personally and expedite [his] comments."134
102.
On the same day the DOS sought135 and received136 six copies of the Devas Agreement, and two days later (on 16 June 2010), Dr Radhakrishnan sent a note to the Ministry of Law and Justice seeking advice concerning the annulment (termination) of the Devas Agreement.137 The note stated:

"we seek your legal opinion on whether ANTRIX-Devas contract need be annulled invoking any of the provisions of the contract in order to (i) to preserve the precious S band spectrum for the strategic requirements of the nation and, (ii) to ensure a level playing field for the other service providers using terrestrial spectrum".138

103.
On the same day, Dr Radhakrishanan also met with Mr. T.K. Viswanathan of the Ministry of Law and Justice.139 According to Devas, Dr Radhakrishnan explained that what he was seeking was advice about "how to annul the contract" (cf. "whether" it "need be annulled", as his note stated).140 Devas also says that Dr Radhakrishnan "was simply looking for an excuse for Antrix to get out of the contract".141
104.
The tribunal accepts that the reason why Dr Radhakrishnan sought advice from the Ministry of Law and Justice was that he wanted advice about how to annul the Devas Agreement (i.e: he wanted to identify a legally permissible basis for terminating the agreement), and that he made this desire clear when he met with Mr Viswanathan on 16 June 2010. This is because:

a. as Devas submits, a note that was later provided to the Space Commission (see [109] below) states that the DOS had, prior to seeking advice from the Ministry of Law and Justice, "decided to request Ministry of Law and justice to give its opinion as to how to annul the contract";142

b. it is inherently implausible that Dr Radhakrishnan wanted advice about whether Antrix "needed" to annul the agreement. There is nothing in the agreement to suggest that its termination might ever be required; the Devas Agreement (like most, if not all agreements) provides only that it "may" be terminated in certain circumstances;

c. the advice that the Ministry of Law and Justice in fact gave was not whether Antrix "need annul" the agreement, but rather whether it was permitted to annul the agreement and how it could do so. The advice was provided to Dr Radhakrishnan on 18 June 2010. It stated:

"the Central Government (Department of Space) in exercise of its sovereign power and function, if so desire and feel appropriate, may take a policy decision to the effect that due to the needs of strategic requirements, the Central Govt/ISRO would not be able to provide orbit slot in S band for operating PS1 to the ANTRIX for commercial activities. In that event, ANTRIX in terms of Article 7(c) read with Article 11, of the agreement may terminate the agreement and inform M/s DEVAS accordingly. However on such termination ANTRIX shall be required to reimburse DEVAS all the Upfront Capacity Reservation Fees and corresponding service taxes received by ANTRIX till that date."143

105.
The tribunal does not, however, make any finding about whether or not Dr Radhakrishnan "was simply looking for an excuse for Antrix to get out of the contract", acting in bad faith in seeking advice about how to annul the agreement (as Devas alleges144) or responding to crystallised national security needs (as Antrix alleges145). As will become apparent below, it is not necessary for the tribunal to make specific findings about these matters in order to resolve the parties’ dispute.
106.
The tribunal also declines to draw any adverse inference from Antrix’s failure to call Dr Radhakrishnan.146 While it is certainly surprising that he was not called to give evidence (given his central role in events that are relevant to this arbitration), the parties have agreed that IBA Rules shall serve as a guide in the determination of evidentiary issues, and those rules provide for adverse inferences to be drawn in very limited circumstances. In relation to a failure to call a witness they state:

"[i]f a Party fails without satisfactory explanation to make available any other relevant evidence, including testimony, sought by one Party to which the Party to whom the request was addressed has not objected in due time or fails to make available any evidence, including testimony, ordered by the Arbitral Tribunal to be produced, the Arbitral Tribunal may infer that such evidence would be adverse to the interests of that Party".147

107.
Since Devas has not suggested that these circumstances apply, the tribunal does not consider that any adverse inference should be drawn from Antrix’s failure to call Dr Radhakrishnan (or any other witness). As noted above, however, the tribunal is certainly surprised that he was not called by Antrix as a factual witness to assist the tribunal. Dr Radhakrishnan was undoubtedly the central person in the events that gave rise to this arbitration. He was in an unparalleled position to give direct evidence concerning them.

Phase II Experimental trials

108.
In mid 2010 Devas conducted "Phase II trials" in China (Chengdu and Beijing) and Germany (Stuttgart). The purpose of the trials included ensuring that the DVB-SH technology148 and TD-LTE technology149 could co-exist in the 2.6gHz band.150 The trials were highly successful.151

Space Commission decides to annul the Devas Agreement

109.
On 30 June 2010 the DOS provided a note to the Space Commission concerning the termination of the Devas Agreement.152 The note stated that its purpose was to "apprise Space Commission on certain concerns that have arisen" in relation to the Devas Agreement, to "apprise on the imperative demand for S-band transponders for strategic and societal applications that have emerged" since the agreement was signed, and to "seek guidance on the prudent utilization of the S-band spectrum of 150 MHz allocated to ISRO" and "further course of actions to be followed by DOS".153
110.
The note provided the background to the Devas Agreement, including: an overview of India’s SATCOM policy; Forge Advisors’ proposed joint venture with Antrix; the entry into the Devas Agreement; Antrix’s approval of the Devas Agreement; the key terms of the agreement; India’s competing "strategic" and "societal" needs for S-band; Dr Suresh’s report on the agreement; and the DOS’ decision to "request Ministry of Law and justice to give its opinion as to how to annul the contract".154
111.
It then states, under the heading "Further Courses of Action and Implications":

"15.1 Annulling the Contract: Considering the need (i) to preserve S-band spectrum for national requirements in strategic sector and for societal applications, (ii) certain concerns on technical, managerial, financial and contractual aspects of ANTRIX-DEVAS contract, and (iii) issues involved in DEVAS obtaining the Spectrum License for the proposed services... it would be inevitable to annul the ANTRIX-DEVAS contract.

The ANTRIX-DEVAS contract has specific clauses for termination of the contract. Ministry of Law and Justice have given their views on feasibility of terminating the contract. The Department, in consultation with Law Ministry, may invoke appropriate clause, and terminate the contract.

In the event of termination of the contract, M/s ANTRIX will have to refund the Capacity Reservation Fee received from M/s DEVAS.

The Department will evolve a revised utilization plan for GSAT-6 and GSAT-6A satellites."

112.
The course of action proposed by the note (which was described as being the "inevitable" course) was therefore to annul the agreement. When the Space Commission met on 2 July 2010 it agreed to that course. It resolved that:

"[the] Department, in view of priority to be given to nation's strategic requirements including societal ones may take actions necessary and instruct Antrix to annul the Antrix-Devas contract".155

Advice from India’s Additional Solicitor General (or "ASG")

113.
The Space Commission also instructed the DOS to seek legal advice on the resolution that the Space Commission had passed at its meeting of 2 July 2010 concerning the annulment of the Devas Agreement, and the form of letters to be issued in order to give effect to that resolution.156
114.
Accordingly, on 8 July 2010, Dr Radhakrishnan wrote to the ASG enclosing (inter alia):

a. the Space Commission’s resolution (see [112] above);

b. a draft letter from the DOS to Antrix stating that Antrix may inform Devas that the Devas Agreement is terminated in accordance with "Article 7(c)(i) read with Article 11"; and

c. a draft letter from Antrix to Devas terminating the agreement in accordance with the "Article 7(c) read with Article 11".157

115.
The ASG issued his advice on 12 July 2010. He disagreed with the Ministry of Law and Justice’s advice that the agreement may be terminated pursuant to Article 7(c) read with Article 11, and advised to instead rely solely on Article 11. He stated that:

"[t]he modus of termination has been specified in the agreement in clause 7. But I am afraid that the conditions stipulated in this clause cannot be invoked at this stage for the purpose of terminating the contract The only other relevant provision for seeking recourse to terminate the contract under the given factual scenario viz., national needs and change in governmental policies, would be Article 11 of the contract, relating to 'Force Majeure'".

There can be no dispute whatsoever that the Government of India is the owner of satellite spectrum space and any policy taken by the Government of India with regard to allocation and use of S bandwith, including those which are subject matter of contractual obligations, would fall within the doctrine of force majeure, as envisaged in the very agreement between Antrix and Devas."158

116.
He also disagreed with the Space Commission’s resolution that the DOS be responsible for instructing Antrix to Annul the agreement. He stated:

"[i]t is always advisable that in the present case, instead of the Department of Space taking a decision to terminate, it would be more prudent that a decision is taken by the Government of India, as a matter of policy, in exercise of its executive power or in other words, a policy decision having the seal and approval of the Cabinet and duly gazetted as per the Business Rules of the Government of India. That would give a greater legal sanctity to the decision to terminate the contract in as much as the contractual provisions expressly stipulate that for the force majeure event, to disable one of the parties to perform its obligations under the contract, the act must be an act by the governmental authority acting in its sovereign capacity."159

Further delays to the launch of the satellites

117.
Soon after the ASG issued his advice, Devas was informed of further delays to the launch of PS1 and PS2:

a. during a "status review" on 5 August 2010 Devas was informed that "shipment and delivery date" for GSAT-6 was now 10 December 2010;160

b. on 20 August 2010 Devas requested an urgent meeting with Dr Radhakrishnan, noting that Antrix had stopped even referring to the potential launch date (cf. the "shipment and delivery’ date).161 Devas was told to seek a meeting with Mr Murthi (Executive Director of Antrix), rather than Dr Radhakrishnan.162 On 14 September 2010 Mr Murthi told Devas that PS1 would be finished in one to two months, but did not provide a launch date;163 and

c. on 27 October 2010 Devas met with Antrix’s new Executive Director, Mr Madhusudhan, who said that he would "apply his energies in getting ISRO to meet stated milestones and assist in exploring launch solutions".164 On 10 January 2011 Mr Madhusadhan said that PS1 was still three to four months away from completion.

118.
On 24 January 2011 Devas wrote to Dr Radhakrishnan and asked him to recommit to the launch of the PS1 satellite.165 Dr Radhakrishnan did not reply.166

Further media articles concerning the Devas Agreement

119.
In early February 2011 a series of further press articles concerning the Devas Agreement were published, after the former Minister for Telecommunications and two of his officers were arrested in respect of the 2G scandal (referred to in [99] above). It was alleged that they undervalued the 2G spectrum and sold it to favoured companies.
120.
One of the articles, published on 8 February 2011, states that "[a]nother spectrum scam has hit the UPA government which is already reeling from the fallout of allegations of corruption in the underpricing of 2G airwaves sold to telecom operators." It also states that:

"[s]ources said ISRO chief K Radhakrishnan had written to the PMO demanding cancellation of the agreement on the ground that it favoured Devas Multimedia. No urgency was, however, shown to revoke the deal even after the law ministry raised serious concerns about the proposal, terming it "illegal".167

121.
On 8 February 2011 Dr Radhakrishnan gave a press conference in New Dehli in which he explained what action had been taken in respect of the Devas Agreement. He stated that:

"we took up the matter to the Space Commission, which in July 2010 made a few decisions. One of the decision was there is high priority for the country's strategic requirements and the societal applications which have be to met using the S-band spectrum that is in the possession of ISRO and we also decided to take actions to annul the contract...

Subsequent to the decisions taken by the Space Commission, of which the Secretary Space is the Chairman and we have very senior members in the commission, we started necessary actions for terminating the contract which required extensive consultations with the concerned agencies in the government Department of Telecommunication, Department of Law and Justice, all included. The idea is to ensure that a ___ contract that has been entered into has to be now terminated without causing much of embarrassment and damage and financial loss to the government. We had to go through that process and we have been going through that process and soon we expect to complete that process."168

Devas’ response to Dr Radhakrishnan’s announcement

122.
Until this point, Devas appears to have been unaware of the proposed annulment (termination) of the Devas Agreement. It responded by sending a series of letters to Dr Radhakrishnan and Antrix:

a. on 11 February 2011 it wrote to Dr Radhakrishnan and stated (inter alia) that any decision to review the Devas Agreement without informing Devas was contrary to the parties’ obligation to act in "utmost good faith". Devas asked that any issues relating to the Devas Agreement that may further adversely impact the ability of Antrix to perform the Devas Agreement be disclosed.169 Dr Radhakrishnan did not respond;

b. also on 11 February 2011 Devas wrote to Antrix in respect of (inter alia) its delay in delivering space segment capacity for the period from 22 June 2009 to 21 June 2010. Devas demanded that Antrix pay (the Indian Rupees equivalent to) USD 5 million as a Late Delivery Penalty.170 Antrix did not respond; and

c. on 14 February 2011 Devas wrote to Antrix and asked Antrix to confirm that it intended to honour the terms of the agreement. It said that if it did not receive a response within one week it would assume that there were disputes or differences arising under the agreement and would be referring the matter to the senior management of Antrix and Devas for resolution in accordance with the agreement’s dispute resolution provisions.171 Antrix did not respond.

Involvement of the Prime Minister

123.
On 16 February 2011, the Prime Minister of India spoke to reporters regarding the annulment of the Devas Agreement. He said that:

"[t]here have been no backroom talks. I think I have not met anybody myself and the decision of the Space Commission to annul the deal was taken on 2nd July, 2010. Space Commission took a number of decision [sic] of which annulment of the contract was one of them. The Dept of Space was asked to take action on all the five decision points that emerged from the Space Commission meeting. The issue of how to annul the contract required consideration by legal experts and the Law Ministry was consulted. A decision had to be taken on whether to annul the contract using article 7(c) or Article 11 or both read together. Eventually it has been decided that the Government should take a sovereign policy decision regarding the utilization of Space Band capacity which uses S Band spectrum having regard to the country's strategic requirements."172

Note to the CCS

124.
On the same day (16 February 2011) Dr Radhakrishnan submitted a note to the CCS. The note stated that its purpose was to seek the CCS’ approval to annul the Devas Agreement "in view of priority to be given to nation's strategic requirements including societal ones".173 It also referred to the need to "level the playing field" for other providers of telecommunications services.174 It went on to request approval to annul the agreement, as follows:

"45.1) Taking note of the fact that government policies with regard to allocation of spectrum have undergone a change in the last few years and there has been a increased demand for allocation of spectrum for national needs, including for the needs of defence-, para-military forces, railways and other public utility services as well as for societal needs, and having regard to the needs of the country's strategic requirements, the Government will not be able to provide orbit slot in S band to Antrix for commercial activities, including for those which are the subject matter of existing contractual obligations for S Band.

45.2) In the light of this policy of not providing orbit slot in S Band to Antrix for commercial activities, the "Agreement for the lease of space segment capacity on ISRO/Antrix S-Band spacecraft by Devas Multimedia Pvt. Ltd." entered into between Antrix Corporation and Devas Multimedia Pvt. Ltd. on 28th January, 2005 shall be annulled forthwith."

125.
On 17 February 2011 the CCS met and approved the annulment of the Devas Agreement. The decision was announced later that day.175

Notification of the annulment of the Devas Agreement

126.
On 25 February 2011 Antrix wrote to Devas informing it that the agreement was terminated.176 The letter stated:

"[t]he Central Government has communicated that it has taken a policy decision not to provide orbital slot in S-Band to our Company for commercial activities including those which are the subject matter of the existing agreements.

In accordance with Article 7(c) of the Agreement, it is declared that Antrix is unable to obtain the necessary frequency and orbital slot coordination as stipulated in the Agreement.

Without prejudice to the inability expressed under Article 7(c), notice of force majeure as defined in Article 11, is expressed. The policy decision of the Central Government acting in its sovereign capacity is the event of force majeure which has occurred on 23rd February 2011. The force majeure commenced on 23rd February 2011. The scope and duration of the said decision cannot be anticipated. It is likely to be indefinite. It is not possible for Antrix to take any effective step to resume the obligations under the Agreement. The event of force majeure is beyond the reasonable control of Antrix and is clearly covered by Article 11(b) of the Agreement and, in particular, 11 (b)(v) "... act of governmental authority in its sovereign capacity... ". Any possibility of resumption of obligations by Antrix under the Agreement stands excluded. The subject Agreement, No. ANTX/203/DEVAS/2005 dated 28th January 2005, therefore, is terminated with immediate effect."

127.
It is not entirely clear from the evidence adduced before this tribunal when or why a decision was made to rely on Article 7(c) to terminate the Devas Agreement (given that this involved a departure from the ASG’s advice, referred to in [115] above).
128.
On 28 February 2011 Devas wrote to Antrix, denying that the Devas Agreement was terminated and stating that, pursuant to Article 20(a) of the Devas Agreement, it was "referring all disputes arising from or under the Agreement... to senior management of both parties."177
129.
On 15 April 2011 Antrix wrote to Devas that referred to its letter of 25 February 2011 and enclosed a cheque for the amount of INR 58,37,34,000 (approximately USD 13 million) as a "reimbursement" of the UCRF.178
130.
On 18 April 2011 Devas wrote to Antrix, returned Antrix’s cheque and stated (inter alia) that Antrix had failed to state a proper basis for terminating the Devas Agreement pursuant to Article 7(c) of the agreement, and that it was not entitled to rely on the force majeure clause in the agreement because the events said to give rise to the force majeure were self-induced.179

Devas’ commencement of this arbitration and claim for damages

131.
As noted above, Devas commenced this arbitration on 1 July 2011. Initially, Devas alleged that Antrix had repudiated its obligations under the agreement, but that it had not accepted the repudiation, and sought specific performance of the agreement. However, Devas later changed its position. On 13 June 2013 Devas wrote to Antrix and stated:

"[w]e refer to your letter of 25 February 2011 in which you purported to terminate the above-referenced Agreement.

There clearly was no basis for you to terminate the Agreement and, accordingly, the purported termination of the Agreement by your 25 February 2011 letter was wrongful and in repudiatory breach of the Agreement. Devas was entitled to accept Antrix’s repudiatory breach of contract and to bring the Agreement to an end, whilst claiming damages.

Since then Antrix also has obstructed the expeditious determination of the arbitration proceedings commenced by Devas.

Antrix continues to be in repudiatory breach of the Agreement even today and has clearly evinced its intention not to perform the Agreement. Devas has elected to, and does hereby, accept Antrix’s repudiatory breach of the Agreement, bringing the Agreement to an end as a result of Antrix’s wrongful actions.

Devas will be amending its claim in the ICC arbitration to reflect the withdrawal of its claim for specific performance whilst maintaining its claim for damages as a result of Antrix’s breaches of contract.

Devas reserves all of its rights including under Indian law and international law."

132.
As noted above, Devas now claims damages equal to the value of its business (which it claims is USD 1.41 billion), plus interest and costs.

Applicable law

133.
The Devas Agreement states that "[t]his Agreement and the rights and responsibilities of the Parties hereunder, shall be subject to and construed in accordance with the Laws of India".180 Both parties agree that, in light of this provision, the tribunal is required to apply the laws of India when determining the parties’ rights and obligations under the agreement.181
134.
Devas has also submitted that English and other common law decisions have important persuasive value which influence the courts in India.182 The tribunal agrees. In Bhagwandas Goverdhandas Kedia v Girdharlal Parshottamadas,183 the Supreme Court of India stated:

"[i]n the administration of the law of contracts, the Courts in India have generally been guided by the rules of the English common law applicable to contracts where no statutory provision to the contrary is in force".184

135.
Similarly, in Forasol v Oil And Natural Gas Commission,185 the Supreme Court stated that English authorities are "of high persuasive value to which [Indian courts] may legitimately turn for assistance".186
136.
The tribunal has therefore treated English and other common law authorities as persuasive, unless they are contrary to any Indian statutes. In addition, where there has been any conflict or inconsistency between Indian and other common law authorities, the tribunal has followed Indian authorities.

Principal Issues in Dispute

137.
During the course of the hearing the parties agreed that the following principal issues are to be determined by the tribunal:

a. Does the tribunal have jurisdiction to hear and determine this dispute?

b. Did Antrix have any right to terminate the Devas Agreement pursuant to Article 7(c) thereof?

c. Was there any "Force Majeure Event" as defined in Article 11 of the Devas Agreement? If so, to what consequence?

d. Is Antrix entitled to rely on Section 56 of the Indian Contract Act, 1872 and if so, can it claim impossibility of the Devas Agreement based-on the CCS decision?

e. Did Antrix’s conduct amount to a repudiation/renunciation of the Devas Agreement or was the Devas Agreement validly terminated by Antrix’s letter of 25 February 2011?

f. If Antrix’s conduct amounted to a repudiation/renunciation of the Devas Agreement, was that a material breach of the Devas Agreement within the meaning of Article 7(b), and did Devas terminate the agreement within the meaning of Article 7(b) when it accepted the repudiation?

g. In the event the tribunal finds jurisdiction and concludes that Antrix is liable, would it be appropriate to use a discounted cash flow (DCF) analysis to determine damages and, if so, whet compensation/damages should be awarded?

h. What is the rate of pre-award and post-award interest that should be applied to an award of compensation/damages?

i. Which party should bear the legal and arbitration costs of this matter, and in what amount?

138.
The approach that the tribunal has taken is to decide only those issues that are necessary to decide in order to resolve Devas’ claims. In other words, if the tribunal decides that it does not have jurisdiction, it will not consider issues relating to liability and quantum, and if it decides that it has jurisdiction but that Antrix is not liable to pay any damages, it will not consider issues relating to the quantum of damages. To do otherwise would, in the tribunal’s view, provide no practical benefit and would add unnecessarily to the already significant costs of this arbitration.

A. Does the tribunal have jurisdiction to hear and determine this dispute?

139.
The first issue that is in dispute is whether the tribunal has jurisdiction to decide Devas’ claims.
140.
Antrix’s basis for challenging the tribunal’s jurisdiction is that the arbitration clause "does not provide for ICC arbitration, but rather specifies two possible sets of arbitration rules", being the ICC and UNCITRAL rules. According to Antrix the clause is therefore pathological and "cannot be enforced without agreement of the parties as to which of the two sets of rules applies".187
141.
In response, Devas says:

a. the Supreme Court of India has held that Devas was entitled to commence this arbitration, which "forecloses" Antrix from now challenging the tribunal’s jurisdiction;

b. in any event, the arbitration agreement is not pathological; and

c. further, Antrix ought to be estopped from arguing that the clause is pathological, because when it purported to start an arbitration under the UNCITRAL Arbitration Rules it accepted that the arbitration clause in the Devas Agreement was "fully workable" and "not at all pathological".188

142.
The tribunal will consider each of these issues in turn.

Has the Supreme Court of India "foreclosed" Antrix from challenging the tribunal’s jurisdiction?

143.
As noted above, after Devas commenced this arbitration Antrix commenced an arbitration under the UNICTRAL Arbitration Rules. It then applied to the Supreme Court for an order under section 11 of the Indian Arbitration and Conciliation Act 1996 (1996 Act) that the Chief Justice direct Devas to nominate it", arbitrator in accordance with the UNCITRAL Rules.189 It submitted that such an order should be made because (inter alia):

"the Arbitration Agreement contemplates the constitution of an Arbitral Tribunal without any reference to the ICC Rules or the ICC Court, [so] the recourse taken by Devas to approach the ICC Court was without any basis and was contrary to the express agreement between the parties".190

144.
The Supreme Court rejected Antrix’s application. It held that:

"[t]he matter is not as complex as it seems and in our view, once the Arbitration Agreement had been invoked by Devas and a nominee Arbitrator had also been appointed by it, the Arbitration Agreement could not have been invoked for a second time by the Petitioner, which was fully aware of the appointment made by the Respondent".191

145.
The Court also stated that:

"[i]n view of the language of Article 20 of the Arbitration Agreement which provided that the arbitration proceedings would be held in accordance with the rules and procedures of the International Chamber of Commerce or UNCITRAL, Devas was entitled to invoke the Rules of arbitration of the ICC for the conduct of the arbitration proceedings".192

146.
According to Devas, this is a clear finding that it was entitled to commence this ICC arbitration, and "conclusively adjudicates this issue of jurisdiction".193
147.
Antrix, on the other hand, notes that Supreme Court also stated that Devas invoked ICC arbitration "[r]ightly or wrongly",194 and that:

"[o]nce the provisions of the ICC Rules of Arbitration had been invoked by Devas, the proceedings initiated thereunder could not be interfered with in a proceeding under Section 11 of the 1296 Act. The invocation of the ICC Rules would, of course, be subject to challenge in appropriate proceedings but not by way of an application under Section 11(6) of the 1996 Act. Where the parties had agreed that the procedure for the arbitration would be governed by the ICC Rules, the same would necessarily include the appointment of an Arbitral Tribunal in terms of the Arbitration Agreement and the said Rules".195

148.
Antrix submits that the reference to the "invocation of the ICC Rules" being "subject to challenge in appropriate proceedings" means that it is entitled to challenge the tribunal’s jurisdiction in this arbitration.196
149.
Devas, on the other hand, says that the Supreme Court’s reference to Devas’ invocation of the ICC Rules being open to challenge was not a reference to a jurisdictional challenge, but rather to a challenge under section 13 of the 1996 Act.197 Section 13 concerns the procedure for challenges to arbitrators.
150.
The tribunal has carefully considered the parties’ submissions but has formed the view that it is not necessary to decide which of them is correct. This is because, for the reasons set out below, even if the Supreme Court intended that Antrix would be able to challenge the tribunal’s jurisdiction in this arbitration on the basis that Article 20 is pathological, the tribunal considers that that challenge must fail.

Is Article 20 pathological?

151.
Antrix submits that the Article 20 of the Devas Agreement is pathological because it refers to both ICC and UNCITRAL arbitration, and therefore requires the parties to agree on which of those two sets of rules should apply.198 Antrix also says that:

"the only precedents in the world on the question of the effectiveness of an arbitration clause naming two different institutions or sets of arbitration rules without agreement of the parties on which would apply have made clear that the clause would be inoperative to confer jurisdiction without such agreement."199

152.
The precedents that Antrix relies on are decisions of the Supreme Court of Lebanon200 and the courts of the People’s Republic of China,201 in which it was found that arbitration clauses that referred to two sets of arbitral rules were ineffective or inoperative.
153.
Contrary to Antrix’s submission, however, these are not the only cases in which the effectiveness of an arbitration clause naming two sets of arbitral rules has been considered. First, as Devas notes, the arbitral tribunal in Millicom International Operations B. V. and Sentel GSM SA v The Republic of Senegal202 did so when it considered an arbitration clause that stated:

"[i]f the dispute continues, the Parties can submit to binding arbitration before international bodies such as the arbitration court of OHADA, the Centre for the Settlement of International Disputes (ICSID) or the International Chamber of Commerce in Paris."203

154.
The case involved claims against the Republic of Senegal pursuant to an investment treaty. The tribunal rejected a submission that the arbitration clause was not binding because it required a further agreement between it and the claimant concerning the choice of arbitration rules. The tribunal found that "[n]othing... prevents an arbitration clause from affording several options [of arbitration rules], from amongst which the party initiating the proceeding has the right to choose."204
155.
Indeed, investment treaties commonly refer to more than one set of arbitration rules. Where they do so, it is well accepted that investors may commence arbitral proceedings against the relevant State pursuant to whichever of those rules it prefers.
156.
Second, in Panamanian Owner X v. Korean Charterer Y,205 an ICC arbitral tribunal considered an arbitration clause that stated that:

"[a]ny dispute arising under this charter party to be referred to 'The Korean Commercial Arbitration Association, Seoul, Korea' and 'The Japan Shipping Exchange, Inc. Japan' and the award of which to be final and binding upon both parties."

157.
The tribunal in that case found the clause to be effective. It said: "if arbitration procedure is initiated by either party in one of the places, then the other party must file its plea and/or counterclaim in that place."206
158.
Further, according to Indian law, arbitration clauses must be construed in a pragmatic, common sense way by reference to the perspective of a reasonable business person. As the Supreme Court of India stated in Enercon (India) Ltd v Enercon GmbH:207

"[i]n our opinion, the Courts have to adopt a pragmatic approach and not a pedantic or technical approach while interpreting or construing an arbitration agreement or arbitration clause. Therefore, when faced with a seemingly unworkable arbitration clause, it would be the duty of the Court to make the same workable within the permissible limits of the law, without stretching it beyond the boundaries of recognition. In other words, a common sense approach has to be adopted to give effect to the intention of the parties to arbitrate. In such a case, the court ought to adopt the attitude of a reasonable business person, having business common sense as well as being equipped with the knowledge that may be peculiar to the business venture. The arbitration clause cannot be construed with a purely legalistic mindset, as if one is construing a provision in a statute."208

159.
Adopting that common sense approach, the tribunal considers that Article 20 is not pathological. It clearly provides for the arbitration of disputes relating to the Devas Agreement, and for the arbitral proceedings to be held in accordance with the ICC or UNCITRAL Rules. The fact that it refers to two sets of arbitral rules does not necessarily mean that the parties had to agree on which set of rules would apply. It simply means that whichever party started the arbitration was entitled to choose between ICC or UNCITRAL arbitration.
160.
Accordingly, the tribunal finds that it does have jurisdiction to decide Devas’ claims.

Estoppel

161.
In light of this conclusion, it is unnecessary to address Devas' claim that Antrix is estopped from denying that Article 20 is operative.

B. Was Antrix entitled to terminate the Devas Agreement pursuant to Article 7(c)?

162.
Under the Devas Agreement, Antrix was responsible for obtaining "Governmental and Regulatory Approvals relating to orbital slot and frequency clearances"209 as well as "clearances from National and International agencies (WPU, ITU, etc) for use of the orbital slot and frequency resources".210
163.
If it failed to obtain "necessary frequency and orbital slot coordination" it was entitled to terminate the agreement pursuant to Article 7(c). Article 7(c) states:

"Termination for convenience by ANTRIX

ANTRIX may terminate this Agreement in the event ANTRIX is unable to obtain the necessary frequency and orbital slot coordination required for operating PS1 on or before the completion of the Pre Shipment Review of the PS1. In the event of such termination, ANTRIX shall immediately reimburse DEVAS all the Upfront Capacity Reservation Fees and corresponding service taxes received by ANTRIX till that date. Upon such termination, neither Party shall have any further obligation to the other Party under this Agreement nor be liable to pay any sum as compensation or damages (by whatever name called)."

164.
As noted above, on 25 February 2011 Antrix sent a letter to Devas purporting to terminate the Devas Agreement in accordance with Article 7(c). Its letter stated (in relevant part):

"[i]n accordance with Article 7(c) of the Agreement, it is declared that Antrix is unable to obtain the necessary frequency and orbital slot coordination as stipulated in the Agreement... The subject Agreement, No. ANTX/203/DEVAS/2005 dated 28th January 2005, therefore, is terminated with immediate effect."

165.
Antrix then sent a cheque to Devas for INR 58,37,34,000 (approximately USD 13 million) as reimbursement of the UCRF.211
166.
Devas says that Antrix was not entitled to terminate the agreement under Article 7(c). It says that Antrix was able to - and did - obtain the necessary frequency and orbital slot coordination required for operating PS1, so Article 7(c) cannot apply. It returned Antrix’s cheque.212
167.
To determine whether Antrix was permitted to terminate the agreement pursuant to Article 7(c) the following issues need to be decided:

a. What weight, if any, is to be placed on the ASG’s opinion that Antrix was unable to terminate the Devas Agreement in accordance with Article 7?

b. Does Article 7(c) concern frequency and orbital slot clearance from both international and national agencies?

c. If yes:

i. Was Antrix unable to obtain the necessary clearance from international agencies?

ii. Was Antrix unable to obtain the necessary clearance from domestic agencies?

168.
The tribunal will consider each of these issues in turn.

What weight, if any, is to be placed on the ASG’s opinion that Antrix was unable to terminate the Devas Agreement in accordance with Article 7?

169.
The ASG’s opinion of 12 July 2010 states (in relevant part):

"[t]he modus of termination has been specified in the agreement in clause 7. But I am afraid that the conditions stipulated in this clause cannot be invoked at this stage for the purpose of terminating the contract".

170.
Devas has referred to this opinion numerous times in support of its submission that Antrix was not entitled to terminate the agreement pursuant to Article 7.213 It says that this opinion is significant because the reason why the ASG was "afraid" that Antrix could not rely on Article 7 was that "the frequency and orbital slot coordination ‘required for operating PST already had been obtained".214 It says that, in light of this opinion, the tribunal should also conclude the required frequency and orbital slot coordination had been obtained.
171.
It is not entirely clear why the ASG thought that Antrix could not rely on Article 7 - he did not give a reason for his view. But even if he did consider that the orbital slot coordination required for operating PS1 had already been obtained, there has been no suggestion that he is an expert in respect of that factual issue, so his view would be an opinion of a lay witness. It therefore has no probative value (particularly since it does not set out the facts on which it is based).215 Accordingly, in the tribunal’s view, it is not appropriate to place any weight on his opinion.

Does Article 7(c) concern clearances from both international and national agencies?

172.
Antrix says that it was entitled to terminate the Devas Agreement pursuant to Article 7(c) if it was unable to obtain frequency and orbital slot clearance from relevant international or national agencies.216
173.
Devas disagrees. It says that Article 7(c) is concerned with clearance from international agencies only. It says that if the parties intended Article 7(c) to embrace clearance from national agencies, Article 7(c) would have referred to "Regulatory Approval" (which incorporates GOI entities217), like Article 7(a). Instead it refers to "frequency and orbital slot coordination",218 which makes no (express) reference to GOI entities.
174.
The tribunal does not accept that submission. By the same logic, one could also say that if the parties intended Article 7(c) to apply to clearance from international agencies only, it would have expressly stated that it applies to international agencies only.219
175.
In the tribunal’s view, the fact that Article 7(c) does not refer to either "Regulatory Approval", domestic agencies or international agencies suggests that the parties intended that it apply to all relevant agencies. In other words, since the parties did not introduce any words limiting the type of frequency and orbital slot clearance that was required, it is likely that they did not intend for there to be any such limit.220
176.
The tribunal therefore accepts Antrix’s submission that Article 7(c) applies if it was unable to obtain frequency and orbital slot clearance from relevant international or national agencies.

Was Antrix unable to obtain frequency or orbital clearance from any relevant international agency?

177.
The international agency responsible for providing clearance for use of S-band and the 83° East orbital slot was the ITU. Antrix says that it was unable to obtain the required clearance from the ITU.221 It says that "Devas’ own 2010 presentations reflect the fact that the coordination on the international level had not yet been completed".222

Was Antrix unable to obtain frequency or orbital clearance from any relevant national agency?

183.
Antrix also submits that it was unable to obtain necessary clearances from relevant national agencies. It has not identified any specific clearance that it was unable to obtain, but in its post-hearing memorial it stated that:

"the Contract is clear that Antrix had to obtain the "necessary Governmental and Regulatory Approvals relating to orbital slot and frequency clearances," including from the WPC. There is no dispute that such Governmental and Regulatory Approvals were not obtained and, after the decision of the Cabinet Committee on Security, could never be obtained".230

184.
Nor did Antrix refer to any specific clearance that it was unable to obtain in its post-hearing reply memorial. It stated only that "on the national level, the only document addressing the use of the orbital slot by Antrix for the Devas Services is the decision of the CCS, which in no uncertain terms denied such use".231
185.
The tribunal therefore understands that, in so far as frequency and orbital slot clearance from national agencies is concerned, Antrix is relying on the CCS’ decision. In particular, the tribunal understands that Antrix is submitting that the CCS’ decision to annul the Devas Agreement made it impossible for Antrix to provide services pursuant to the Devas Agreement from the 83° East orbital slot.
186.
Devas, on the other hand, says that "any internal approvals [that were] needed... were satisfied", and that this happened "before filings were made at the ITU".232 Devas says that"[t]he nodal agency for all submissions by the GOI to the ITU... was the WPC, which coordinated inputs from DOS, DOT, and all other relevant agencies",233 and that once the WPC had completed coordination of the five spot beams at the 83° East orbital slot at the ITU, no further approvals were required.234
187.
Given that Antrix has not identified any specific clearances from national agencies that it was required and unable to obtain, it is necessary to determine whether Antrix is entitled to rely on the CCS’ decision in order to terminate the agreement pursuant to Article 7(c).
188.
In the tribunal’s view, it is not. As noted above, Article 7(c) states that:

"ANTRIX may terminate this Agreement in the event ANTRIX is unable to obtain the necessary frequency and orbital slot coordination required for operating PS1 on or before the completion of the Pre Shipment Review of the PS1" (emphasis added).

189.
The reference to Antrix being "unable to obtain" the "necessary" frequency and orbital slot coordination implies that there is a regulatory clearance that it was necessary for Antrix to obtain. In other words, it implies that for Article 7(c) to apply, there must be a national or international agency that was responsible for granting clearance or approval to use S-band at the 83° East orbital slot, and that Antrix was required to obtain that clearance or approval, and was unable to do so.
190.
Since Antrix was not required to apply for frequency and orbital slot clearance from the CCS, it is therefore not permitted to rely on the CCS’ decision alone in order to terminate the agreement pursuant to Article 7(c).
191.
The tribunal also notes that, even if the CCS’ decision had the effect of annulling any necessary clearance or approval that Antrix had obtained, that would not be sufficient to enliven Article 7(c). Article 7(c) refers to Antrix being unable to "obtain the necessary frequency and orbital slot coordination", unlike Article 7(a) which refers to Devas being unable to "get and retain" Regulatory Approvals. As Devas has submitted,235 this wording suggests that Article 7(c) was intended to apply only in the case of inability to obtain a relevant clearance, not inability to retain a clearance.
192.
Accordingly, the tribunal considers that the pre-conditions for the application of Article 7(c) have not been satisfied, and that Article 7(c) did not permit Antrix to terminate the Devas Agreement.

C. Was there any "Force Majeure Event" as defined in Article 11 of the Devas Agreement? If so, to what consequence?

193.
Antrix’s letter of 25 February 2G11 also purported to terminate the Devas Agreement on the basis that "Force Majeure Event" had occurred. It stated (in relevant part):

"[t]he policy decision of the Central Government acting in its sovereign capacity is the event of force majeure which has occurred on 23rd February 2011. The force majeure commenced on 23rd February 2011. The scope and duration of the said decision cannot be anticipated. It is likely to be indefinite. It is not possible for Antrix to take any effective step to resume the obligations under the Agreement. The event of force majeure is beyond the reasonable control of Antrix and is clearly covered by Article 11 (b) of the Agreement and, in particular, 11 (b)(v) '... act of governmental authority in its sovereign capacity...'".

194.
Article 11 of the Devas Agreement states as follows.

"Article 11. Force Majeure

a. Neither of the Parties hereto shall be liable for any failure or delay in performance of its obligations hereunder if such failure or delay is due to Force Majeure as defined in this Article, provided that notice thereof is given to the other Party within seven (7) calendar days after such event has occurred.

b. For the purposes of this Agreement, "Force Majeure Event" shall include any event, condition or circumstance that is beyond the reasonable control of the party affected (the "Affected Party") and that, despite all efforts of the Affected Party to prevent it or mitigate its effects (including the implementation of a business continuation plan), such event, condition or circumstance prevents the performance by such Affected Party of its obligations hereunder. The following events may be considered Force Majeure Events under the Agreement: (i) explosion and fire; (ii) flood, earthquake, storm, or other natural calamity or act of God; (iii) strike or other labor dispute; (iv) war, insurrection, civil commotion or riot; (v) acts of or failure to act by any governmental authority acting in its sovereign capacity; (vi) changes in law and regulation, (vii) National emergencies, (ix) Launch Failure.

c. If an Affected Party Is rendered unable, wholly or in part, by a Force Majeure Event, to carry out some or all of its obligations under the Agreement, then, during the continuance of such Inability, the obligation of such Affected Party to perform the obligations so affected shall be suspended.

d. The Affected Party shall give written notice of the Force Majeure Event to the other party (the "Unaffected Party") as soon as practicable after such event occurs, and not later than 7 days after such event, which notice shall include information with respect to the nature, cause and date of commencement of the occurrence(s), and the anticipated scope and duration of the delay. Upon the conclusion of a Force Majeure Event, the Affected Party shall, with all reasonable dispatch, take all necessary and effective steps to resume the obligation(s) previously suspended.

e. Notwithstanding the foregoing, an Affected Party shall not be excused under this Article for (1) any non-performance of its obligations under the Agreement having a greater scope or longer period than is justified by the Force Majeure Event, or (2) the performance of obligations that arose prior to the Force Majeure Event. Nothing contained herein shall be construed as requiring an Affected Party to settle any strike, lockout or other labor dispute in which it may be involved.

f. Notwithstanding anything contained herein, in the event of Launch Failure of PS1 or PS2, the articles related to re-launch guarantee in Article 3 (d), and termination under special circumstances in Article 7 shall apply and take precedence over the terms contained herein.

g. In the event of failure or delay in the performance of this Agreement arising out of an event of Force Majeure which lasts longer than 90 (ninety) days, both parties shall discuss the further course of action on a mutually agreeable basis. However, such action could include termination at the option of Unaffected Party if total delays exceed 12 liability shall arise on termination under this clause as far as the affected party is concerned."

195.
Devas says that Antrix was not entitled to rely on Article 11 for the following reasons:

a. the decision of the CCS to annul the agreement was not an "act of or failure to act by any governmental authority acting in its sovereign capacity" within the meaning of Article 11(b);236

b. the CCS’ decision was "brought about by, or is otherwise attributable to" Antrix’s "own or its parent's actions" (and therefore cannot, in law, be a force majeure event);237 and

c. Antrix "instigated" the alleged "Force Majeure Event", so it was not "beyond the reasonable control" of Antrix within the meaning of Article 11(b);238

d. Antrix did not make "all efforts" to "prevent it or mitigate its effects" as required by Article 11(b);239

e. Article 11 permits the "Unaffected Party" (Devas) to terminate the agreement in light of "Force Majeure Events", not the "Affected Party" (Antrix).240

196.
Before considering these submissions, it is necessary to return to the question of which party bears the burden of proof in respect of whether Antrix was entitled to terminate the agreement pursuant to Article 11. Each party says that the other bears the burden of proof.241 As noted by the authors of Redfern and Hunter on International Arbitration, however:242

"[t]he practice of nearly all international arbitral tribunals is to require each party to prove the facts upon which it relies in support of its case... The only exceptions relate to propositions that are so obvious, or notorious, that proof is not required".

197.
The tribunal has adopted this approach in respect of all issues that are in dispute in this arbitration. That is to say, it has required each party to prove the facts and establish the principles on which that party relies.

Was there an act of or failure to act by any governmental authority acting in its sovereign capacity?

198.
As noted above, Article 11(b) of the Devas Agreement states (inter alia) that"[t]he following events may be considered Force Majeure Events under the Agreement:... (v) acts of or failure to act by any governmental authority acting in its sovereign capacity". Devas says that the decision of the CCS to annul the Devas Agreement does not fall within this definition, for the following reasons:

a. it was not "a final policy ‘decision’ by a sovereign regulator" to use S-band for military purposes, but rather left "open for the government itself (whether ISRO or another entity) to use the S-band for commercial activity".243 The tribunal does not accept this submission. There is nothing to suggest that Article 11(b) was intended to apply only to "final policy decisions". It refers to "acts of or failure to act by any governmental authority acting in its sovereign capacity". The CCS’ decision was clearly an "act" of a "government authority" that was acting in its "sovereign capacity", so it falls within that definition. In any event, it was a final policy decision (being that the Devas Agreement should be annulled);

b. Article 11(b) "cannot be construed to allow a governmental entity to make unavailable the very thing that Antrix was unconditionally required under Article 3(c) to provide" (i.e. Governmental and Regulatory Approvals relating to orbital slot and frequency clearances).244 To the contrary, Devas contends that it is "well settled under Indian law that a contract should not be interpreted so as to render any term thereof redundant or futile".245 The tribunal does not accept this submission either. Construing Article 11(b) to permit Antrix to terminate the agreement based on its failure to provide orbital slots and frequency does not render Article 3(c) redundant or futile; it simply means that the obligation in Article 3(c) is subject to Article 11;

c. a "sovereign event must act upon the parties ab extra" (i.e. "from outside"), whereas "[h]ere, Antrix is leasing a property belonging to the Government acting not as an independent party but as the marketing arm".246 The tribunal also does not accept this submission. Devas has not referred to any provision of the Devas Agreement, or any authority, to suggest that the term "sovereign event" must operate ab extra. In any event, the CCS’ decision was an ab extra event. As discussed below (see [205] - [206]), Antrix has a legal personality that is separate and distinct to the GOI, so the CCS’ decision operated on it "from outside"; and

d. CCS’ motivation for terminating the agreement was not military needs, but "political compulsions".247 Again, however, the relevant criteria are that there was an "act" of a "government authority" that was "acting in its sovereign capacity". CCS’ motivation for deciding to annul the Devas Agreement is therefore not relevant.248 Accordingly, the tribunal does not accept this submission either.

199.
The tribunal therefore finds that the CCS’ decision to annul the agreement was an act of a governmental authority acting in its sovereign capacity for the purpose of Article 11 (b).

Can force majeure events be brought about by a company’s own or its parent's actions?

200.
Devas also submits that Antrix cannot rely on Article 11 because, at law, a force majeure event cannot be brought about by a company’s own or its parent’s actions.
201.
The tribunal accepts that Antrix cannot rely on Article 11 if the CCS’ decision was brought about by Antrix’s actions. Article 11(b) clearly states that "Force Majeure Events" do not include events that were beyond the reasonable control of the party affected. Whether the CCS’ decision was beyond Antrix’s control is discussed below (see [215] to [235]).
202.
In support of its submission that a party cannot rely upon a force majeure event that has been brought about by its parent's actions, Devas relies on the English Court of Appeal’s decision in Mamidoil-Jetoil Greek Petroleum Co. v. Okta Crude Oil Refinery AD No (2)249(Okta) and the Court of Appeal’s250 and House of Lords’251 dicta in C. Czarnikow Ltd. v. Céntrala Handlu Zagranicznego Rolimpex (Rolimpex).
203.
Okta concerned a contract between a Greek company (Jetoil) and the owner of an oil refinery in Macedonia (Okta) pursuant to which Jetoil had (a) an exclusive right to "manipulate" (i.e. handle) non-heated crude oil for Okta at a terminal in Thessaloniki, Greece, that Okta bought for its own account; and (b) a right of first refusal to supply crude oil to Okta. The contract contained a provision (clause 4) to the effect that:

"[n]either party shall be responsible for damage caused by delay or failure to perform in whole or in part the stipulations of the present Agreement, when such delay of (sic) failure is attributable to earthquakes, acts of God, strikes, riots, rebellion, hostilities, fire, flood, acts or compliance with requests of any governmental or EC authority war conditions or other causes beyond the control of the party affected, whether or not similar to those enumerated. The party invoking force majeur (sic), shall give prompt notice to the other party by fax, telex followed by registered letter stating the kind of Force Majeure. The certificate issued by the respective Chamber of Commerce and Industry shall be considered as sufficient proof of such circumstances and the duration".

204.
The Government of the Former Yugoslav Republic of Macedonia issued letters to Okta containing requests that Okta cease honouring its contract with Jetoil. Okta claimed that those letters constituted a force majeure event within the meaning of clause 4 of the agreement.
205.
The Court of Appeal rejected this claim on the basis that Okta had instigated or initiated the requests that it received, so they were not "beyond its control". The Court stated:

"[f]or Okta to be able to rely on the clause they have to show that the failure to perform is attributable to a request which was beyond Okta’s control... The essential issue is whether, if it is the case that Okta instigated or initiated the requests contained in the November and May letters, they can rely on the letters as constituting 'requests... beyond their control'. Once the question is posed in that form, it is clear that they cannot, for the simple reason that they need not have set the process in motion at all. They could, instead, have decided to comply with their contractual obligations."252

206.
This case is therefore not, as Devas submits, authority for the proposition that a company cannot rely upon a force majeure event that has been brought about by its parent's actions. Rather, it is authority for the proposition that a force majeure event is not beyond a party’s reasonable control if it instigates or initiates that event. Whether Antrix instigated or initiated the CCS’ decision is a separate issue, which is discussed below (see [215] to [226]).
207.
Rolimpex concerned contracts between a Polish state-owned foreign trade organisation, Rolimpex (having its own legal personality), and an English company, Czarnikow, pursuant to which Rolimpex was to supply Czarnikow 17,000 metric tonnes of sugar. The contracts included a "force majeure" clause stating that if delivery was prevented "by Government intervention... or any [other] cause of force majeure... beyond the Seller's control', the contracts would become void. In 1974 there was a poor sugar harvest and the Polish Government, concerned about a potential lack of sugar for domestic consumption, placed a ban on the export of sugar. The ban (which Rolimpex opposed) applied to the contracts and, as a result, Rolimpex failed to deliver the quantity of sugar to Czarnikow that it had agreed to supply.
208.
Czarnikow then commenced an arbitration seeking damages from Rolimpex for breach of contract. Rolimpex relied on the force majeure clause, stating that the government’s ban on sugar exports was beyond its control. The tribunal agreed, but stated a case for the decision of the court. The trial judge, Court of Appeal and House of Lords upheld its decision, finding that Rolimpex was entitled to rely on the force majeure clause.
209.
Devas relies on the judgment of by Lord Denning MR in the Court of Appeal - in particular, a statement by his Lordship that "when the government itself is a party... [i]t cannot rely on a self-induced 'intervention' any more than it could rely on a self-induced frustration." Devas says that Lord Denning thus accepted the view that "a government can bind itself to perform a contract with an implication that it will not do anything with or in connection with that particular contract so as to hinder or prevent the performance of its obligations thereunder". Devas notes that his Lordship also stated that "if Rolimpex [was] a department of the Government of Poland," it could not have relied upon "the clause about 'government intervention.'"253
210.
These comments by Lord Denning do not, however, support the proposition that a company is unable to rely on a force majeure clause if the relevant force majeure event is created by its parent. Lord Denning was considering whether a party can rely on force majeure events created by that same party. He was accepting that if Rolimpex was a department of the Polish Government, then the government would be party to the agreement, and Rolimpex would be unable to rely on force majeure events created by the government.
211.
Devas also relies on a passage of Lord Wilberforce’s judgment in the House of Lords, in which his Lordship stated that there may be cases where the evidence shows that it was:

"so clear that a foreign government is taking action purely in order to extricate a state enterprise from contractual liability, that it may be possible to deny to such action the character of government intervention, within the meaning of a particular contract."254

212.
That passage must be read in context. Lord Wilberforce was not suggesting that a state-owned company is unable to rely on a force majeure clause simply because the government took steps to extricate the company from contractual liability. Nor was he suggesting more broadly that a company is unable to rely on a force majeure event created by its parent.
213.
Rather, he was referring to Lord Denning MR’s conclusion that "if Rolimpex was a department of the Government of Poland, it cannot rely on the clause about ‘government intervention’". Lord Wilberforce expressed doubt about whether that doctrine, "which is very much one of English constitutional law, can viably be transplanted into the constitutional climate of foreign states, particularly such states as Poland", being a country which has "an entirely different constitutional structure" to the United Kingdom.255 He then went on to say that despite that doubt, there may certain cases in which it may nevertheless be appropriate to deny that a government act is a force majeure event. He was therefore saying that even if an organisation is to be treated as part of the government, it is only in certain circumstances that it "may be possible" to conclude that the organisation cannot rely on acts of the government as force majeure events.
214.
Accordingly, neither Okta nor Rolimpex support Devas’ submission that, at law, force majeure events cannot be brought- about by the actions of a company’s parent. The tribunal therefore does not accept that submission.

Was the CCS’ decision beyond Antrix’s reasonable control?

215.
Devas also submits that Antrix is unable to rely on Article 11 of the Devas Agreement because the CCS’ decision was not beyond Antrix’s reasonable control. It says that the decision was not beyond Antrix’s reasonable control because it was "instigated" by Antrix’s Chairman, Dr Radhakrishnan.256 Devas says that:

"[i]t was Dr. Radhakrishnan who in June 2010 obtained Law Ministry advice "as to how to annul the Contract"; it was he who proposed and secured the Space Commission's decision authorizing him to pursue this strategy; it was he who obtained confirmation from the Additional Solicitor-General as to the means of annulling the contract by contriving to deprive Antrix of the leased spectrum for commercial purposes; and it was he who, several months later, secured a CCS decision in precisely the form devised by the ASG - the supposed "Force Majeure Event".257

216.
Antrix, on the other hand, submits that "every document in the record relating to this issue shows that Dr. Radhakrishnan took no action as Chairman of Antrix and always acted in his official governmental capacity"258 - that is, in his capacity as Secretary of the DOS and/or Chairman of ISRO or the Space Commission. It says further that Devas has not identified any proper legal basis for attributing Dr Radhakrishnan’s conduct to Antrix.259
217.
Underlying Antrix’s submission is the long-standing principle that companies have legal personalities that are separate and distinct from their shareholders.260 This principle applies to government owned as well as private entities. As the Supreme Court -of India stated in Electronics Corporation of India Ltd and Ors v Secretary, Revenue Department, Government of Andhra Pradesh and Ors:261

"[a] clear distinction must be drawn between a company and its shareholder, even though that shareholder may be only one and that the Central or a State Government. In the eye of the law, a company registered under the Companies Act is a distinct legal entity other than the legal entity or entities that hold its shares".262

218.
In light of this principle, in order to prove that the conduct of Dr Radhakrishnan caused the alleged "Force Majeure Event", and that his conduct should be treated as conduct of Antrix, it is necessary to consider:

a. whether or not Dr Radhakrishnan was acting in his capacity as Chairman of Antrix when he engaged in the conduct that Devas relies on; or

b. if he was acting in his capacity as an officer of DOS, ISRO or the Space Commission, his conduct should be attributed to Antrix. For that to be the case, however, the tribunal must be satisfied that:

i. the DOS, ISRO and/or the Space Commission were acting as the agent of Antrix at relevant times; or

ii. there is some other legal basis for treating the conduct of DOS, ISRO and/or the Space Commission as the conduct of Antrix, such as "piercing the corporate veil".

219.
Devas has not alleged that Dr Radhakrishnan was acting in his capacity as Chairman of Antrix at any relevant time.
220.
Nor has Devas alleged that the GOI was acting as Devas’ agent.263 Initially it alleged that Antrix was acting as the GOI’s agent, but that allegation has been abandoned.264 Even if it had been pressed (and accepted), however, it would not have permitted the GOI’s conduct to be attributed to Antrix: agency permits the agent’s conduct to be attributed to the principal, not the other way around.
221.
Devas has, however, submitted that Antrix and the GOI should be treated as one and the same entity. In its post-hearing memorial it stated that:

"[t]o the extent it seeks to claim Dr. Radhakrishnan's actions, in seeking to undermine the Devas Agreement and bring about the CCS decision, were done in a capacity other than as Antrix’s Chairman (e.g., as Secretary of DOS or Chairman of ISRO), this notion should be rejected... The relationship between Antrix and GOI are dispositive of this issue. Antrix is the marketing arm of the Government (DOS)."265

222.
Similarly, in its post-hearing memorial Devas stated that:

"Devas does not assert that Antrix signed the contract as a pass-through "booking" agent, as Antrix now seeks to characterize Devas's case. Rather, Devas has alleged, and Antrix has admitted, that in signing the contract, Antrix expressly did so as the "marketing arm of [DOS]" and "the entity through which ISRO engages in commercial activities.""266

223.
Devas does not put this submission on the basis that the tribunal should "pierce the corporate veil", and it has not relied on any authorities that concern piercing the corporate veil. Rather, its submission is that since the contract states that Antrix is the DOS’ marketing arm and the entity through which ISRO engages in commercial activities, the tribunal is entitled to disregard Antrix’s separate legal personality. As Devas explained to the tribunal during the hearing:

"[i]f you read the recitals [of the contract], sir... [t]he second recital then says: "Whereas Antrix is a marketing arm of the Department of Space and is the entity through which ISRO engages in commercial activities". As far as this contract is concerned - and you do not need extraneous evidence, much less judgments of the Supreme Court which state the obvious, ie that a corporate entity is distinct from its shareholders for certain purposes - this is what the contract says. "Antrix is". It is sufficient for me, and we don’t need to go beyond this".267

224.
The tribunal does not accept that submission. To find that a company’s distinct legal personality may be disregarded simply because it is a government’s "marketing arm" and/or performs commercial activities for a government’s benefit (but is not the government’s agent) would, in the tribunal’s view, be a significant departure from the long-standing approach of courts of India and England to a company’s separate legal personality. It is telling that Devas has not referred the tribunal to any authority in support of this submission. The tribunal is not aware of any such authority.
225.
On the contrary, the tribunal agrees with Antrix that:

"[w]hether dealing with state companies or private companies, including the myriad subsidiaries and special purpose companies organised by the world’s major corporations, the formation of "marketing arms" does not abrogate or in any way compromise the separate legal personality of such entities."268

226.
Accordingly, the tribunal does not accept that Antrix itself "instigated" the alleged "Force Majeure Event".
227.
However, that is not determinative of whether the event was beyond Antrix’s reasonable control. For an event to be beyond Antrix’s reasonable control Antrix must, in addition to not instigating the event, have been unable to prevent the event from taking place. It is therefore also necessary to ask: was Antrix able to prevent the CCS from deciding to annul the Devas Agreement?
228.
Antrix submits that it "had nothing to do, and could not legally have had anything to do, with the decision of the CCS, the highest body in India entrusted with national security matters".269 The tribunal accepts that submission. In addition to being the ultimate authority within India on matters of internal and external security and defence,270 none of the CCS’ members were officers of Antrix271 and Devas has not led evidence to the effect that Antrix was able to seek judicial review of, or otherwise able to challenge, the CCS’ decisions.272 Nor has Devas submitted that Antrix was permitted at law to refuse to comply with the CCS’ direction to annul the agreement.
229.
But that establishes only that the CCS’ decision was beyond Antrix’s reasonable control once it has been made. It does not answer the question of whether Antrix could have prevented the CCS from receiving a proposal to annul the Devas Agreement.
230.
In the tribunal’s view, it could have done so. This is because, if Dr Radhakrishnan had, from the time that he was appointed Chairman of Antrix, and acting in his capacity as Chairman of Antrix, done everything in his power to ensure that the agreement remained on foot, in the tribunal’s view he would not have taken any of the steps that led to the CCS being asked to approve the annulment of the agreement. As a result, those steps would not have occurred.
231.
In particular, if Dr Radhakrishnan had been personally lobbying and making representations to the DOS, ISRO and the Space Commission to ensure that the Devas Agreement remained on foot, he would not, at the same time, have:

a. obtained advice from the Ministry of Law and Justice about how to annul the agreement;273

b. permitted his department to inform the Space Commission that it was "inevitable" that the Devas Agreement be annulled;274

c. sat as Chair of the Space Commission when it resolved that the DOS may instruct Antrix to annul the agreement;275

d. sought advice from the ASG concerning the annulment of the Devas Agreement;276 and/or

e. sought approval from the CCS to annul the Devas Agreement.277

232.
He would not have taken those steps because they would have required him to adopt diametrically opposed positions in respect of the Devas Agreement: on the one hand, that the agreement should remain on foot, and on the other, that it should be annulled. This would have created a clear and irreconcilable conflict of interest.
233.
The difficulty that he would have faced becomes apparent when one considers the meeting of the Space Commission on 2 July 2010. Before that meeting Dr Radhakrishnan’s department advised the Space Commission that it was "inevitable" that the agreement be annulled. If at the same time Dr Radhakrishnan was lobbying the Space Commission to ensure that the agreement remained on foot, the Space Commission would have been required to decide whether to annul the agreement in light of two diametrically opposed views, which would have both come (directly or indirectly) from the same person, who was also the Commission’s Chairman. In the tribunal’s view, Dr Radhakrishnan would not have allowed either himself or the Space Commission to be put in such a position.
234.
Accordingly, the tribunal considers that, if Dr Radhakrishnan had done everything in his power (as Chairman of Antrix) to prevent the annulment of the Devas Agreement, he would not have taken the steps referred to in [231] above. They are the steps that led directly to the CCS’ decision to annul the agreement. If they had not occurred, the CCS would not have been invited to annul the agreement. Nor would the CCS have acted on what was Dr Radhakrishnan’s clear recommendation to annul the agreement. As a result, in all probability the agreement would not have been annulled.
235.
Further, since Dr Rhadakrishnan (acting in his capacity as Chairman of Antrix) could have prevented the CCS from being asked to annul the agreement, Antrix could have effectively prevented the CCS from making that decision, which means that the CCS’ decision was not beyond Antrix’s reasonable control. Given that Article 11(b) limits "Force Majeure Events" to events that are beyond Antrix’s reasonable control, the CCS’ decision cannot be a "Force Majeure Event" for the purpose of Article 11 (b).
236.
The tribunal therefore finds that Antrix was not permitted to terminate the Devas Agreement pursuant to Article 11.

Devas’ other submission concerning Article 11

237.
In light of this conclusion, it is not strictly necessary to consider Devas’ other grounds for alleging that Article 11 does not apply. The tribunal notes, however, that if it had been necessary to consider Devas’ other submissions, the tribunal would also have accepted the submission that Antrix did- not make all efforts to prevent the effects of the alleged "Force Majeure Event", and therefore that Article 11(b) does not apply.278 This is because:

a. the definition of "Force Majeure Event" in Article 11(b) is limited to events that Antrix has made "all efforts... to prevent". Therefore, in order for Article 11 (b) to apply in respect of the CCS’ decision to annul the Devas Agreement, Antrix must have made "all efforts" to prevent that decision from being made; and

b. Antrix made no efforts to prevent that decision from being made. There is no evidence of Dr Rhadakrishnan - or any other officer of Antrix - making any effort to prevent the CCS from annulling the Devas Agreement. Nor is there any evidence of Dr Rhadakrishnan -or any other officer of Antrix - making any effort to prevent the conduct that led to CCS making that decision (such as the Law of Ministry and Justice providing advice about how to annul the Devas Agreement, the Space Commission being advised that annulment of the agreement was "inevitable" and the ASG’s advice being sought concerning the annulment of the agreement).

238.
It is clear that in these circumstances Article 11 was not intended to apply.

D. Is Antrix entitled to rely on Section 56 of the Indian Contract Act, 1872 and if so, can it claim impossibility of the Devas Agreement based on the CCS decision?

239.
Antrix submits that, even if it was not entitled to terminate the agreement pursuant to Articles 7(c) or 11 of the Devas Agreement, the decision of the CCS rendered the agreement impossible to perform and therefore void under section 56 of the Indian Contracts Act.279
240.
Section 56 states:

"[a] contract to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the Promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful".

241.
Devas does not deny that the CCS’ decision made performance of the agreement impossible. However, it denies that section 56 of the Indian Contracts Act applies. According to Devas, "once the parties have expressly addressed the possibility of a supervening event in their contract through a force majeure clause, then Section 56 cannot apply".280 In support of that proposition Devas relies on decision of the Supreme Court of India in Mary v State of Kerala (State of Kerala)281 In that case, the Supreme Court stated that:

"in a case in which the consequences of non-performance of contract is provided in the statutory contract itself, the parties shall be bound by that and cannot take shelter behind Section 56 of the Contract Act".282

242.
According to Antrix, however, State of Kerala is only authority for the proposition that "the parties to an agreement may allocate the risk of force majeure to one of the parties".283 Antrix says that the case therefore:

"has no applicability here, where the force majeure clause, far from purporting to allocate the risk of force majeure to Antrix, expressly acknowledges that governmental acts taken in a sovereign capacity do constitute force majeure".284

243.
To consider which party’s view of State of Kerala is correct it is necessary to consider the facts and the Court’s findings in that case. The appellant (Mary) was a bidder in an auction for the right to sell Arak (an alcoholic drink) from a shop in Kalady (a town in the State of Kerala). The auction was conducted pursuant to the Kerala Abkari Shops (Disposal in Auction) Rules, 1974. Rule 5(15) stated:

"[o]n the failure of the auction purchaser to make such deposit referred to in sub-rule (10) or take out such licence or execute such agreement temporary or permanent or furnish such personal surety or additional cash security as aforesaid, the deposit already made by him towards earnest money and security shall be forfeited to Government".

244.
Mary’s bid was successful and she paid an amount equal to 30% of her bid as a deposit. Subsequently, residents of a nearby Christian pilgrim centre objected to her opening an "abkari shop" (i.e. a liquor shop) and the State’s law agencies said that they were "unable to assure smooth conduct of the business". Mary believed that this made it impossible for her to operate the business, and..sought a refund of her deposit. The State refused. It said that the sale had already been confirmed, and asked her to enter into the "permanent agreement" referred to in Rule 5(15). Mary refused and court proceedings were commenced.
245.
During those proceedings, Mary sought to rely on section 56 of the Indian Contract Act. The Supreme Court held that she was not entitled to do so. The relevant passage of the Court’s judgment is as follows:

"[i]t is not the case of the State that appellant has purposely, or for any oblique motive, or as a device to avoid any loss, refused to execute the agreement. It appears to us that the State was helpless because of the public upsurge against the sale of arrack at Kaladi, the birth place of Adi Shankaracharya as, in their opinion, the same will render the soil unholy. Consequently, the State also found it impossible to re-sell or redispose of the arrack shops. In view of second paragraph of Section 56 of the Contract Act, a contract to do an act which after the contract is made, by reason of some event which the promissory could not prevent becomes impossible, is rendered void. Hence, the forfeiture of the security amount, may be illegal. But what would be the position in a case in which the consequence for non-performance of contract is provided in the statutory contract itself? The case in hand is one of such cases. The doctrine of frustration excludes ordinarily further performance where the contract is silent as to the position of the parties. In the event of performance becoming literally impossible. However, in our opinion, a statutory contract in which a party takes absolute responsibility cannot escape liability whatever may be the reason. In such a situation, events will not discharge the party from the consequence of non-performance of a contractual obligation. Further, in a case in which the consequences of non-performance of a contract is provided in the statutory contract itself, the parties shall be bound by that and cannot take shelter behind Section 56 of the Contract Act."285

246.
In the tribunal’s view, this passage makes clear that what the Supreme Court found was that Mary was not entitled to rely on section 56 because her agreement with the State specified the consequences of non-performance of her contractual obligations.
247.
That is precisely what the parties have done in the Devas Agreement. The parties have set out the consequences of non-performance of their obligations. For example, Article 13 provides that if one party breaches its obligations the other is to indemnify it against any loss or damage it suffers, unless that other party terminates the agreement; Article 7 sets out the consequences where the agreement is terminated; and Article 11 sets out the parties’ obligations in the case of "Force Majeure Events". Indeed, examination of the Devas Agreement reveals that the parties have set out the consequences of non-performance of their contractual obligations in considerable detail.
248.
Accordingly, the tribunal accepts Devas’ submission that section 56 of the Indian Contract Act does not apply, so it does not render the Devas Agreement void.
249.
The tribunal notes that it has considered Boothalinga Agencies v VTC Poriaswanmi Nadarm (Boothalinga), an earlier decision of the Supreme Court.286 As Antrix has noted,287 in Boothalinga the Court stated that section 56 "lays down a rule of positive law and does not leave the matter to be determined according to the intention of the parties".288 In the tribunal’s view, however, this statement does not assist Antrix. When the Supreme Court made that statement, it was not considering whether section 56 applies in cases where parties specify the consequences of non-performance of their contractual obligations. Rather, it was explaining that the English doctrine of frustration is a contractual remedy, whereas section 56 is a statutory remedy.289 Accordingly, after making that statement, the Court went on to discuss relevant English authorities concerning the theoretical foundation of the doctrine of frustration, before concluding that:

"[i]n English law therefore the question of frustration of contract has been treated by courts as a question of construction depending upon the true intention of the parties. In contrast, the statutory provisions contained in Section 56 of the Indian Contract Act lay down a positive rule of law and English authorities cannot therefore be of direct assistance, though they have persuasive value in showing how English courts have approached and decided cases under similar circumstances."290

250.
Boothalinga therefore does not address the question of whether section 56 applies in cases where parties specify the consequences of non-performance of their contractual obligations.

E. Did Antrix’s conduct amount to a repudiation/renunciation of the Devas Agreement or was the Devas Agreement validly terminated by Antrix’s letter of 25 February 2011?

251.
As noted above on 25 February 2011 Antrix wrote to Devas purporting to terminate the agreement. The tribunal has found that it was not entitled to do so. Since it was not entitled to do so, its letter plainly amounted to a wrongful repudiation of the agreement.291

F. Was Antrix’s repudiation of the Devas Agreement a material breach of the Devas Agreement within the meaning of Article 7(b), and did Devas terminate the Agreement within the meaning of Article 7(b) when it accepted the repudiation?

252.
Antrix submits that even if it did wrongfully repudiate the Devas Agreement, according to Article 7(b) Devas’ only remedy is a refund of the UCRF.292
253.
Article 7(b) states as follows:

"DEVAS may terminate this Agreement at any time if ANTRIX is in material breach of any provisions of this Agreement and ANTRIX has failed to cure the breach within three months after receiving notice from DEVAS setting out the nature of breach and reasons for considering the same as material breach. In such event, ANTRIX shall immediately reimburse DEVAS all the Upfront Capacity Reservation Fees and corresponding taxes if applicable, received by ANTRIX till that date. Upon such termination, neither Party shall have any further obligation to the other Party under this Agreement nor be liable to pay any sum as compensation or damages (by whatever name called)."

254.
Devas denies that its entitlement to damages is limited by Article 7(b). It says that Article 7(b) does not apply because:

a. it only applies where Devas "terminates" the agreement, and Devas did not terminate the agreement but rather accepted Antrix’s repudiation;

b. it does not apply to repudiatory breaches; and

c. it does not apply unless Devas (a) put Antrix on written notice that Devas believed Antrix was in material breach and (b) gave Antrix the opportunity to cure that breach within three months, and Devas did not take either of those steps.293

Did Devas terminate the Devas Agreement?

255.
Antrix says that Devas terminated the agreement when it sent its letter of 13 June 2013.294 As noted above, that letter stated that Devas "accept[ed] Antrix’s repudiatory breach of the Agreement, bringing the Agreement to an end".295
256.
Devas says that "[a]ccepting a repudiation is not the same thing as terminating a contract pursuant to a contractual right"296 and that its 13 June 2013 letter therefore did not terminate the agreement.
257.
Certainly, repudiation and termination are not the same thing. Repudiation involves refusing to perform, or disclosing an intention to not perform, contractual obligations. A contract is not automatically brought to an end when it is repudiated. It is only if the innocent party accepts the repudiation that the contract is brought to an end. By contrast, when a contract is terminated it is automatically brought to an end.
258.
However, the tribuna