1991 FI Law | Law on Foreign Investments in the RSFSR, 1991 |
1994 Joint EC Statement | Joint statement on Article 45 of the European Energy Charter Treaty, made by the Council, Commission, and Member States of the European Community, 14 December 1994 |
1999 FI Law | Law on Foreign Investments in the Russian Federation, 1999 |
Achmea | Achmea v. Slovak Republic, PCA Case No. 2008-13, Award on Jurisdiction, Arbitrability and Suspension (26 October 2010) |
Alpha | Alpha Projektholding GmbH v. Ukraine ICSID Case No. ARB/07/16, Award (8 November 2010) |
Alps Finance | Alps Finance and Trade AG v. Slovak Republic (UNCITRAL Award) (5 March 2011) |
Amto | Limited Liability Company Amto v. Ukraine, SCC Case No. 080/2005, Final Award (26 March 2008) |
August 2004 Loan | The August 2004 loan, made to Yukos Oil by Yukos Capital, in the principal amount of USD 355 million |
Brittany | Brittany Assets Ltd. |
Brittany Loan Agreement | Agreement establishing a loan between Brittany (lender) and Yukos Capital (borrower) dated 20 November 2003 |
Caratube | Caratube International Oil Company LLP v. Republic of Kazakhstan, ICSID Case No. ARB/08/12, Award (5 June 2012) |
Claimant / Yukos Capital | Yukos Capital S.à r.l., the Claimant |
Constitution | Constitution of the Russian Federation, 1993 |
Constitutional Court | The Constitutional Court of the Russian Federation |
Counter-Memorial | Claimant's Counter-Memorial on Jurisdiction dated 3 November 2014 |
December 2003 Loan | The December 2003 loan, made to Yukos Oil by Yukos Capital, in the principal amount of RUB 79.3 billion |
Domestic Law Inconsistency Clause | Article 45(1) of the Energy Charter Treaty: "to the extent that such provisional application is not inconsistent with its constitution, laws or regulations" |
ECT / Treaty | Energy Charter Treaty, 1994 |
Electrabel | Electrabel S.A. v. The Republic of Hungary, ICSID Case No. ARB/07/19, Decision on Jurisdiction, Applicable Law and Liability (30 November 2012) |
Emmis | Emmis International Holding BV v. Hungary ICSID Case No. ARB/12/2, Award (16 April 2014) |
FLIT | Federal Law on International Treaties of the Russian Federation, 1995 |
GATT | 1994 General Agreement on Tariffs and Trade |
Gazprom | O.J.S.C. Gazprom |
Gazprom ECP | Gazprom ECP S.A. |
Hedgerow | Hedgerow Ltd |
Hedgerow Loan Agreement | Agreement establishing a loan between Hedgerow (lender) and Yukos Capital (borrower) dated 18 August 2004 |
Hulley Enterprises | Hulley Enterprises Limited v. Russian Federation, PCA No. AA226, Interim Award on Jurisdiction and Admissibility (30 November 2009) |
Kardassopoulos | Ioannis Kardassopoulos v. The Republic of Georgia, ICSID Case No. ARB/05/18, Decision on Jurisdiction (6 July 2007) |
KT Asia | KT Asia Investment Group B.V. v. Kazakhstan, ICSID Case No. ARB/09/8, Award (17 October 2013) |
Loans | The December 2003 Loan and the August 2004 Loan | |
Memorial | Respondent's Memorial on Jurisdiction dated 28 July 2014 | |
Notice of Arbitration | Notice of Arbitration dated 15 February 2013 | |
Oil Platforms | Oil Platforms (Islamic Republic of Iran v. United States of America) (Preliminary Objection) [1996] ICJ Rep 803 | |
Parties | The Claimant and the Respondent | |
PCA | Permanent Court of Arbitration | |
Phoenix Action | Phoenix Action Ltd v Czech Republic ICSID Case No ARB/06/5, Award (15 April 2009) | |
Plama | Plama Consortium Limited v. Republic of Bulgaria, ICSID Case No. ARB/03/24, Decision on Jurisdiction (8 February 2005) | |
PO No. 1 | Procedural Order No. 1 dated 24 April 2014 | |
PO No. 2 | Procedural Order No. 2 dated 20 January 2015 | |
Rejoinder | Claimant's Rejoinder on Jurisdiction dated 15 June 2015 | |
Reply | Respondent's Reply on Jurisdiction dated 2 March 2015 | |
Resolution No. 8-P | Resolution No. 8-P of the Constitutional Court of the Russian Federation dated 27 March 2012 | |
Respondent / Russia / Russian Federation | Government of the Russian Federation, the Respondent | |
Romak | Romak S.A. (Switzerland) v. Uzbekistan, PCA Case No. AA280, UNCITRAL, Award (26 November 2009) | |
Rospan | Rospan Overseas Ltd | |
Russia / Russian Federation / Respondent | Government of the Russian Federation, the Respondent | |
Sibneft | Sibneft, a joint stock company incorporated in the Russian Federation in 1995 |
Standard Chartered Bank | Standard Chartered Bank v. Tanzania, ICSID Case No. ARB/10/12, Award (2 November 2012), para. 200 |
Stati | Stati v. The Republic of Kazakhstan, SCC Case No. 116/2010, Award (19 December 2013) |
Stichting | Stichting Administratiekantoor Yukos International, a foundation incorporated in the Netherlands in 2005 |
Terms of Appointment | Terms of Appointment between the Parties appointing the Tribunal dated 17 February 2014 |
The Hague District Court Judgment | Judgment dated 20 April 2016 of a District Court sitting at The Hague in action nos C/09/477160 / HA ZA 15-1, C/09/477162 / HA ZA 15-2 and C/09/481619 / HA ZA 15112 re: Hulley Enterprises Ltd/Yukos Universal Ltd (Isle of Man)/Veteran Petroleum Ltd (Cyprus) v. Russian Federation |
TMF (or TMF Luxembourg) | TMF Corporate Services S.A. and TMF Management Luxembourg S.A., the Claimant's corporate and management service providers in Luxembourg |
Toto Costruzioni | Toto Costruzioni Generali S.p.A. v. Lebanon, Decision on Jurisdiction (11 September 2009) |
Treaty / ECT | Energy Charter Treaty, 1994 |
UNCITRAL Rules | Arbitration Rules of the United Nations Commission on International Trade Law, 1976 |
USSR FLIT | Law of the USSR dated 6 July 1978 "On the Procedure for Conclusion, Performance, and Denunciation of International Treaties of the USSR" |
USSR Fundamentals | Fundamentals of Legislation on Foreign Investments in the USSR, 1991 |
VCLT | Vienna Convention on the Law of Treaties, 1969 |
Yukos Capital / Claimant | Yukos Capital S.à r.l., the Claimant |
Yukos Capital Loan Agreement | Agreement establishing a loan between Yukos Capital (lender) and Yukos Oil (borrower) dated 2 December 2003 |
Yukos Oil | Yukos Oil Company OJSC, a joint stock company incorporated in the Russian Federation in 1993 |
Yukos Finance | Yukos Finance B.V., a private limited liability company incorporated in the Netherlands |
Yukos International | Yukos International UK B.V., a private limited liability company incorporated in the Netherlands |
Arbitration Rules of the United Nations Commission on International Trade Law, 1976, GA Res. 31/98. The Notice of Arbitration purported to invoke the revised 2010 UNCITRAL Arbitration Rules, but it was accepted by the Parties and recorded in the Terms of Appointment of the Tribunal that the 1976 rules were applicable: Terms of Appointment (17 February 2014) ("Terms of Appointment"), para. 4(a).
On 8 October 2013, the Claimant requested that the Secretary-General of the Permanent Court of Arbitration (the "PCA") act as the appointing authority with regard to the appointment of a presiding arbitrator, pursuant to Articles 6 and 7 of the UNCITRAL Rules. In its submission, the Claimant stated that the Parties were "in agreement as to the employment of the list-procedure referred to in Article 6(3) of the 1976 Rules ..., but wish for the list to be provided by the Secretary-General to include at least five names."5
Claimant's Application for the Secretary-General to Act as Appointing Authority (8 October 2013), para. 17.
Claimant
Mr Cyrus Benson
Ms Ceyda Knoebel
Gibson, Dunn & Crutcher LLP
Mr Daniel Feldman
Party Representative
Respondent
Mr David Sabel
Ms Claudia Annacker
Mr Cameron Murphy
Cleary Gottlieb Steen & Hamilton LLP
Registry
Mr Hanno Wehland PCA
Court Reporter
Ms Claire Hill
(i) "[t]he Russian Federation never ratified the ECT and applied the ECT until October 18, 2009 on a provisional basis pursuant to Article 45(1) ECT only 'to the extent that such provisional application is not inconsistent with its constitution, laws or regulations'";6
(ii) "[t]he intra-company loans allegedly made by Claimant to Yukos Oil Company are not 'investments' within the meaning of Article 1(6) ECT";7 and
(iii) "[s]ince Claimant is a shell company with no substantial business activities in Luxembourg and is ultimately controlled by nationals of a third State, Respondent is entitled to deny Claimant the advantages of Part III of the ECT pursuant to Article 17 ECT."8
(a) On 28 July 2014, the Respondent filed a Memorial on Jurisdiction, together with an Expert Report of Professor Anton V. Asoskov ("Asoskov 1").
(b) On 3 November 2014, the Claimant filed a Counter-Memorial on Jurisdiction ("Counter-Memorial"), together with a Witness Statement of Bruce K. Misamore ("Misamore 1") and Expert Reports of Professor Paul B. Stephan ("Stephan 1"), Stuart B. Gleichenhaus ("Gleichenhaus 1"), and Professor Justice J. H. M. Willems ("Willems 1").
(c) On 2 March 2015, the Respondent filed a Reply on Jurisdiction, together with a Second Expert Report of Professor Asoskov ("Asoskov 2") and Expert Reports of Professor Thomas Z. Lys ("Lys"), Lionel Noguera ("Noguera"), and Professor Dr. Riemert Pieter Jan Lucris Tjittes ("Tjittes").
(d) On 15 June 2015, the Claimant filed a Rejoinder on Jurisdiction, together with a Second Witness Statement of Mr Misamore ("Misamore 2"), further Expert Reports of Professor Stephan ("Stephan 2"), Mr Gleichenhaus ("Gleichenhaus 2"), and Professor Willems ("Willems 2"), and Expert Reports of Professor Stephen E. Shay ("Shay") and Andrew Grantham ("Grantham").
Claimant
Mr Cyrus Benson
Ms Penny Madden
Ms Ceyda Knoebel
Mr Piers Plumptre
Ms Sophy Cuss
Mr Sergey Okoev
Gibson, Dunn & Crutcher LLP
Mr David Godfrey
Ms Natalia Kantovich
Ms Sophy Bae
Party Representatives
Mr Bruce K. Misamore
Fact Witness
Professor Paul B. Stephan
Mr Stuart B. Gleichenhaus
Professor Stephen E. Shay
Mr Andrew Grantham FCA
Professor Justice J.H.M. (Huub) Willems LLM
Expert Witnesses
Respondent
Dr Claudia Annacker
Mr David G. Sabel
Mr Lawrence B. Friedman
Mr Matthew D. Slater
Mr Larry C. Work-Dembowski
Dr Enikő Horvath
Ms Laurie Achtouk-Spivak
Mr Lorenzo Melchionda
Ms Ksenia Khanseidova
Ms Aija Lejniece
Ms Sarah Schröder
Mr Sean McGrew
Cleary Gottlieb Steen & Hamilton LLP
Mr Andrey Kondakov
Party Representative
Mr Jesse Stevenson
Trial Graphic Consultant
Professor Anton V. Asoskov
Professor Thomas Z. Lys
Professor Dr. Riemert P.J.L. Tjittes
Expert Witnesses
Tribunal Assistant
Mr Jack Wass
Registry
Dr Hanno Wehland
Mr Robert James
PCA
Court Reporter
Mr Trevor McGowan
Interpreters
Ms. Irina van Erkel
Mr Sergei Mikheyev
On 17 May 2016, the Tribunal wrote to the Parties in the following terms:
The Tribunal has before it, as legal authorities introduced into the arbitration file in these proceedings, the Interim Awards on Jurisdiction and Admissibility in Hulley Enterprises Ltd/Yukos Universal Ltd (Isle of Man)/Veteran Petroleum Ltd (Cyprus) v. Russian Federation (PCA Case Nos AA 226, 227 & 228, 30 November 2009), exhibited in this arbitration as CL-9, CL-26 & CL-27. Both Parties have pleaded as to the relevance of those Decisions for the issues of jurisdiction presently before this Tribunal.
It has come to the Tribunal's attention from the public record that on 20 April 2016 a District Court sitting at The Hague in action nos C/09/477160 / HA ZA 15-1, C/09/477162 / HA ZA 15-2 and C/09/481619 / HA ZA 15-112 rendered judgment in proceedings challenging these Awards (together "The Hague District Court Judgment").
The Tribunal invites the Parties' observations as to (i) the admission of The Hague District Court Judgment into the record in the present proceedings; (ii) whether, if admitted, the Parties would wish to be heard on its relevance (if any) to the proceedings in the present case and (iii) if so, in what form they would wish to be heard. The Parties are requested to file their preliminary observations on these questions by 5pm (CET) on Monday, 30 May 2016.11
(a) By email of the same date, the Claimant replied, suggesting that "the fact that neither party has sought to introduce [The Hague District Court Judgment] into the record of this proceeding speaks for its relevance." In the event that the judgment were to be introduced into the record on the application of the Respondent, the Claimant submitted that its relevance could be addressed in submissions not exceeding three pages.
(b) By letter dated 23 May 2016, the Respondent made certain observations on The Hague District Court Judgment and requested that it be admitted into the record and taken into account by the Tribunal in its award. The Respondent expressed the opinion that it was not necessary for the Parties to be further heard on the relevance of the judgment.
(c) By letter of 24 May 2016, the Claimant advised that it did not object to the Respondent's request for The Hague District Court Judgment to be placed on the record, but offered certain observations on its relevance.
The relevant provisions of the ECT are as follows:
Article 1—Definitions
(6) Investment" means every kind of asset, owned or controlled directly or indirectly by an Investor and includes:
(a) tangible and intangible, and moveable and immovable, property, and any property rights such as leases, mortgages, liens, and pledges;
(b) a company or business enterprise, or shares, stock, or other forms of equity participation in a company or business enterprise, and bonds and other debt of a company or business enterprise;
(c) claims to money and claims to performance pursuant to contract having an economic value and associated with an Investment;
(d) Intellectual Property;
(e) Returns;
(f) any right conferred by law or contract or by virtue of any licences and permits granted pursuant to law to undertake any Economic Activity in the Energy Sector.
A change in the form in which assets are invested does not affect their character as investments and the term "Investment" includes all investments, whether existing at or made after the later of the date of entry into force of this Treaty for the Contracting Party of the Investor making the investment and that for the Contracting Party in the Area of which the investment is made (hereinafter referred to as the "Effective Date") provided that the Treaty shall only apply to matters affecting such investments after the Effective Date.
"Investment" refers to any investment associated with an Economic Activity in the Energy Sector and to investments or classes of investments designated by a Contracting Party in its Area as "Charter efficiency projects" and so notified to the Secretariat.
(7) "Investor" means:
(a) with respect to a Contracting Party:
(i) a natural person having the citizenship or nationality of or who is permanently residing in that Contracting Party in accordance with its applicable law;
(ii) a company or other organization organized in accordance with the law applicable in that Contracting Party;
(b) with respect to a "third state," a natural person, company or other organization which fulfils, mutatis mutandis, the conditions specified in subparagraph (a) for a Contracting Party.
...
Article 17—Non-Application of Part III in Certain Circumstances
Each Contracting Party reserves the right to deny the advantages of this Part to:
(1) a legal entity if citizens or nationals of a third state own or control such entity and if that entity has no substantial business activities in the Area of the Contracting Party in which it is organized;
...
Article 26—Settlement of Disputes Between an Investor and a Contracting Party
(1) Disputes between a Contracting Party and an Investor of another Contracting Party relating to an Investment of the latter in the Area of the former, which concern an alleged breach of an obligation of the former under Part III shall, if possible be settled amicably.
(2) If such disputes cannot be settled according to the provisions of paragraph (1) within a period of three months from the date on which either party to the dispute requested amicable settlement, the Investor party to the dispute may choose to submit it for resolution:
(a) to the courts or administrative tribunals of the Contracting Party to the dispute;
(b) in accordance with any applicable, previously agreed dispute settlement procedure; or
(c) in accordance with the following paragraphs of this Article.
(3) (a) Subject only to subparagraphs (b) and (c), each Contracting Party hereby gives its unconditional consent to the submission of a dispute to international arbitration or conciliation in accordance with the provisions of this Article.
(b) (i) The Contracting Parties listed in Annex ID do not give such unconditional consent where the Investor has previously submitted the dispute under subparagraph (2)(a) or (b).
...
(4) In the event that an Investor chooses to submit the dispute for resolution under subparagraph (2)(c), the Investor shall further provide its consent in writing for the dispute to be submitted to:
...
(b) a sole arbitrator or ad hoc arbitration tribunal established under the Arbitration Rules of the United Nations Commission on International Trade Law (hereinafter referred to as "UNCITRAL")
(6) A tribunal established under paragraph (4) shall decide the issues in dispute in accordance with this Treaty and applicable rules and principles of international law.
...
Article 45—Provisional Application
(1) Each signatory agrees to apply this Treaty provisionally pending its entry into force for such signatory in accordance with Article 44, to the extent that such provisional application is not inconsistent with its constitution, laws or regulations.
(2) (a) Notwithstanding paragraph (1) any signatory may, when signing, deliver to the Depository a declaration that it is not able to accept provisional application. The obligation contained in paragraph (1) shall not apply to a signatory making such a declaration. Any such signatory may at any time withdraw that declaration by written notification to the Depository.
(b) Neither a signatory which makes a declaration in accordance with subparagraph (a) nor Investors of that signatory may claim the benefits of provisional application under paragraph (1).
(c) Notwithstanding subparagraph (a), any signatory making a declaration referred to in subparagraph (a) shall apply Part VII provisionally pending the entry into force of the Treaty for such signatory in accordance with Article 44, to the extent that such provisional application is not inconsistent with its laws or regulations.
(3) (a) Any signatory may terminate its provisional application of this Treaty by written notification to the Depository of its intention not to become a Contracting Party to the Treaty. Termination of provisional application for any signatory shall take effect upon the expiration of 60 days from the date on which such signatory's written notification is received by the Depository.
(b) In the event that a signatory terminates provisional application under subparagraph (a), the obligation of the signatory under paragraph (1) to apply Parts III and V with respect to any Investments made in its Area during such provisional application by Investors of other signatories shall nevertheless remain in effect with respect to those Investments for twenty years following the effective date of termination, except as otherwise provided in subparagraph (c).
(c) Subparagraph (b) shall not apply to any signatory listed in Annex PA. A signatory shall be removed from the list in Annex PA effective upon delivery to the Depository of its request therefor.
(4) Pending the entry into force of this Treaty the signatories shall meet periodically in the provisional Charter Conference, the first meeting of which shall be convened by the provisional Secretariat referred to in paragraph (5) not later than 180 days after the opening date for signature of the Treaty as specified in Article 38.
(5) The functions of the Secretariat shall be carried out on an interim basis by a provisional Secretariat until the entry into force of this Treaty pursuant to Article 44 and the establishment of a Secretariat.
(6) The signatories shall, in accordance with and subject to the provisions of paragraph (1) or subparagraph (2)(c) as appropriate, contribute to the costs of the provisional Secretariat as if the signatories were Contracting Parties under Article 37(3). Any modifications made to Annex B by the signatories shall terminate upon the entry into force of this Treaty.
(7) A state or Regional Economic Integration Organization which, prior to this Treaty's entry into force, accedes to the Treaty in accordance with Article 41 shall, pending the Treaty's entry into force, have the rights and assume the obligations of a signatory under this Article.
The Respondent contends that the Tribunal lacks jurisdiction to hear Yukos Capital's claims. The Respondent bases its argument on three grounds:
(i) Arbitration of the present dispute is inconsistent with the Russian Federation's "constitution" and "laws" for purposes of Article 45(1) of the ECT, and, accordingly, the obligation to provisionally apply the ECT did not extend to Article 26; the arbitration agreement on which the Claimant seeks to rely is "null and void";22
(ii) Yukos Capital has not made an Investment protected under Article 1(6) of the ECT, because the purported Loans were in substance dividends designed to repatriate to Russia the profits of Yukos Oil's Russian trading subsidiaries, in which Yukos Capital played no meaningful role and should be "disregarded";23 and
(iii) The Respondent is entitled to deny the Claimant the benefits of Article 17 of the ECT because the Claimant is a shell company with "no substantial business activities" in Luxembourg and is controlled by nationals of a third state, namely the United States nationals who are members of the Stichting's board.24
(i) In relation to Article 45(1), the Claimant makes three independent submissions: first, a signatory may avoid provisional application only where the principle of provisional application itself is inconsistent with domestic law – Article 45(1) does not contemplate a "piecemeal" comparison of specific provisions of the Treaty with domestic law;25 second, provisional application is not inconsistent with Russian law because the executive had authority to commit the Respondent to provisional application of Article 26 (and that renders it consistent with Russian law); third, even examined on a piecemeal basis, Article 26 – the arbitration of investment disputes – is not inconsistent with Russian law.26
(ii) The Loans qualify as "Investments" under Article 1(6) of the ECT;27 the Claimant rejects the argument that they fail a test derived from "general international law" as to what qualifies as "investment."28
(iii) The Respondent's attempt to invoke Article 17(1) cannot give rise to a jurisdictional challenge, since the Respondent would only be entitled to deny the benefits of Part III of the ECT (whereas Article 26 is found in Part V);29 the Claimant submits that the Respondent's purported invocation of Article 17 after the arbitration had been commenced could not operate retrospectively to deny the Claimant accrued rights;30 and that the Respondent cannot make out the two substantive requirements of the Article.
(i) Decline to exercise jurisdiction over the Claimant's claims;
(ii) Order the Claimant to pay to the Respondent the full costs of this arbitration, including, without limitation, arbitrators' fees and expenses, administrative costs, counsel fees and expenses and any other costs associated with this arbitration;31
(iii) Order the Claimant to pay to the Respondent interest on the amounts awarded under (ii) above until the date of full payment; and
(iv) Grant any further relief to the Respondent as it may deem appropriate.32
Pursuant to Article 21(1) of the UNCITRAL Rules, "[t]he arbitral tribunal shall have the power to rule on objections that it has no jurisdiction, including any objections with respect to the existence or validity of the arbitration clause or of the separate arbitration agreement." This provision reflects the concept, fundamental to international arbitration, of compétence–compétence, namely that an international tribunal has jurisdiction to rule upon its own jurisdiction.
Hulley Enterprises Limited v. Russian Federation, PCA No. AA226, Interim Award on Jurisdiction and Admissibility (30 November 2009) ("Hulley Enterprises") (Exhibit CL-9). See para. 92 below.
See para. 94 below and Counter-Memorial, para. 75.
Reply, para. 86, citing Counter-Memorial, para. 56. See para. 92 below.
Reply, para. 88, citing Counter-Memorial, para. 59. See Hulley Enterprises, para. 318 (Exhibit CL-9). See para. 92 below.
See para. 77 below. Counter-Memorial, paras. 43-45, citing Ioannis Kardassopoulos v. The Republic of Georgia, ICSID Case No. ARB/05/18, Decision on Jurisdiction (6 July 2007) ("Kardassopoulos"), paras. 71, 73-74 (Exhibit CL-11); Hulley Enterprises, paras. 269, 309, 319 (Exhibit CL-9).
The Respondent also refers to the "'to the extent' clause in paragraph 1(b) of the Protocol of Provisional Application" of the General Agreement on Tariffs and Trade ("GATT"), pointing out that there is a "consistent body of GATT case law" confirming that "GATT Contracting States were entitled to and did invoke specific inconsistencies of their domestic laws with particular GATT obligations."99 The Respondent also argues that there was "never any suggestion that consent by the executive to provisional application may suffice to eliminate inconsistencies" between domestic law and GATT obligations.100
See para. 96 below and Counter-Memorial, para. 90.
[e]ven in the case of a state not making such a declaration [pursuant to Article 45(2)(a) of the ECT], it could prove extremely difficult to ascertain the extent to which the provisions of the ECT are inconsistent with the particular signatory's constitution, laws or regulations.112
Interpreting Article 45(1) in this manner, the Claimant focuses on the word "such," which it alleges was "ignored by Respondent."120 The plain meaning of "such" in this context is, according to the Claimant, "of the kind specified."121 The Claimant further argues that "the kind of provisional application specified is that '[e]ach signatory agrees to apply [the ECT] provisionally pending its entry into force for such signatory'."122 Therefore, as the Claimant contends, "the limiting 'to the extent' language ... operates only where applying 'this Treaty' (i.e., the principle of provisional application itself) is inconsistent with the signatory's constitution, laws or regulations."123 The Claimant notes that such an interpretation is consistent with the findings of the tribunals in Hulley Enterprises124 and Kardassopoulos.125
Counter-Memorial, paras. 41-42.
Counter-Memorial, para. 42.
Counter-Memorial, para. 42.
Counter-Memorial, para. 42 (emphasis in original); T1/145/4-5.
Counter-Memorial, paras. 43, 50-51, citing Hulley Enterprises, paras. 308, 314-315 (Exhibit CL-9); Rejoinder, paras. 29-30.
Counter-Memorial, paras. 44-45, citing Kardassopoulos, para. 210 (Exhibit CL-11); Rejoinder, paras. 30, 33.
The Claimant further contends that "'provisional application' has the same meaning under both Articles 45(1) and 45(2)(a) (i.e. application of the Treaty as a whole)."126 According to the Claimant, the Respondent concedes that the Claimant "is correct that the phrase 'such provisional application' refers to the provisional application previously mentioned in Article 45(1) ECT, namely the provisional application of 'this Treaty'."127 After making such a concession, however, the Claimant asserts that the Respondent offers a rebuttal128 that is no more than a tautology and a "confused commentary devoid of any apparent logic."129 The Claimant adds that the Respondent's authorities in this regard do not support the Respondent's position.130
The Claimant also disputes the Respondent's contention that the Claimant's interpretation renders Article 45(1) "superfluous."138 The Claimant notes that, for signatories that do not make an opt-out declaration, Article 45(1) "provides a safety net that ... permits [signatories] to ... avoid provisional application if, and only if, it is inconsistent with their laws to so apply the Treaty," as opposed to opt out declarations made pursuant to Article 45(2)(a), which "may be made for any reason."139 So if any state had a concern with provisional application, they were free to opt out pursuant to that clause.140 They could also opt out of the 20 year tail.141
The Claimant rejects the Respondent's interpretation of other provisions in Article 45 as well, finding the Respondent's contentions142 regarding Article 45(3)(b) "impossible to comprehend."143 The Claimant criticizes the Respondent's interpretation as ignoring the fact that Article 45(3)(b) holds that, under Article 45(1), there exists an "obligation ... to apply Parts III and V," the effect of which is to "strip[] Article 45(3)(b) of all meaning for any signatory claiming that Parts III and V are inconsistent with its domestic law."144 What this conveys, according to the Claimant, is that "under any interpretation of Article 45(1), signatory states are applying provisionally Parts III and V."145
See Reply, para. 68.
Rejoinder, para. 46.
Rejoinder, para. 47.
T1/148/5-8.
See para. 63 above and Reply, paras. 72, 75.
The Claimant also cites Article 45(2)(b) of the ECT and its "reciprocity of obligations," providing that "investors of a signatory may not claim [ECT] benefits unless the signatory consents to apply [the ECT] provisionally (i.e., in its entirety)."157 On such obligations, the Claimant references Hulley Enterprises for the proposition that "[a]llowing a State to modulate ... the obligation of provisional application ... would undermine the principle that provisional application of a treaty creates binding obligations,"158 thus "creat[ing] unacceptable uncertainty in international affairs."159 It would also mean that one state could be "provisionally applying virtually nothing and receive all of the benefits from states that are applying the whole thing."160
Counter-Memorial, para. 49.
Counter-Memorial, para. 50, citing Hulley Enterprises, para. 314 (Exhibit CL-9).
Counter-Memorial, para. 51, citing Hulley Enterprises, para. 315 (Exhibit CL-9).
T1/146/25 – T1/147/3.
See para. 63 above and Reply, paras. 75-76.
See para. 51 above and Reply, paras. 40-41.
The Claimant also rejects the Respondent's citation of Professor Reisman's critique of the same position that the Claimant has adopted in this arbitration,168 noting that the Respondent omits a portion of Professor Reisman's analysis that shows that Professor Reisman, Hulley Enterprises, and Kardassopoulos are all in accord with the proposition that a signatory state wishing to avoid provisional application "must duly notify in advance that its constitution, laws or regulations disable it from provisional application" and that, for investors having already invested in a State, "Part III and Part V of the ECT remain in force for 20 years with regard to any investments made in that state during the provisional application unless a declaration rejecting the 'tail' is made at the time of signature."169
The Claimant also cites Article 27 of the VCLT to show that the Respondent is wrong to "invoke the provisions of its internal law as justification for its failure to perform a treaty."173 As authority for this proposition, the Claimant cites the legal opinions of Professor Crawford and Professor Reisman in Hulley Enterprises,174 as well as the Constitutional Court.175 The Claimant concedes that, under Article 46(1) of the VCLT, a "narrow exception" applies "[i]f a fundamental provision of internal law 'regarding competence to conclude treaties' ... manifestly precludes the giving of consent to so conclude ... the treaty."176 Nevertheless, the Claimant rejects the notion that the Respondent has suggested or could suggest that this exception applies to the Respondent here.177 According to the Claimant, the interpretation advanced by the Respondent would give Article 45 of the ECT "the function of a reservation," and Article 46 of the ECT "precludes any reservations to individual Treaty provisions."178
Counter-Memorial, para. 56.
Counter-Memorial, paras. 59-60, citing Hulley Enterprises, paras. 316-318 (Exhibit CL-9).
Counter-Memorial, para. 57, citing Resolution No. 8-P, para. 6 (Exhibit R-35).
Counter-Memorial, paras. 61-62, citing VCLT, Art. 46(1).
Counter-Memorial, paras. 63-65.
Rejoinder, para. 62.
The Claimant further rejects the Respondent's interpretation arguments, noting that "[m]ost of the Respondent's arguments in support of its ... approach may be described as supplementary means of interpretation arguments."179 The Claimant contends that Article 45(1) of the ECT is not "ambiguous or obscure" and that interpreting the ECT using a plain language approach does not lead to a "manifestly absurd or unreasonable" result. Thus, according to the Claimant, the Respondent's arguments are "unnecessary and should not be considered pursuant to Article 32 of the [VCLT]."180
The Claimant further contends that, regarding state practice, the Respondent only analyzes the practice of one State – Finland – and that, moreover, the documents it relies on fail to "provide evidence of 'any agreement' between the parties or an instrument accepted by the other parties on signature or any 'subsequent agreement' or 'practice' establishing the agreement of the parties for purposes of Article 31 of the [VCLT]."191 Additionally, the Claimant finds the other documents cited by the Respondent to be irrelevant and, "in any event, consistent with the Claimant's interpretation."192
The Claimant argues that state practice in fact provides support for its interpretation, noting that, during the negotiating process, an "emphasis on legal certainty prevailed over opposition from various delegations"193 and referring to the Energy Charter Conference Secretariat's request to the delegations that they notify the Secretariat of their intention not to provisionally apply the ECT.194 The Claimant notes that nine states – Iceland, Malta, Bulgaria, Cyprus, Switzerland, Turkmenistan, Norway, Japan, and Poland – made declarations pursuant to Article 45(2)(a), and that Hungary made a declaration citing Article 45 without specifying a particular paragraph.195 The Claimant cites the Hulley Enterprises decision, which highlighted that no state relied on Article 45(1) for "selective or partial application of the ECT based on the non-application of only those individual provisions that are claimed to be inconsistent with a signatory's domestic law."196 According to the Claimant, the Respondent has not provided evidence that any signatory that did not give notice or make a declaration adopted the Respondent's "piecemeal approach" to Article 45(1).197
Rejoinder, para. 63.
Rejoinder, para. 64.
Rejoinder, para. 71.
Rejoinder, para. 72, citing Hulley Enterprises, para. 321 (Exhibit CL-9). See also T1/151/19 – T1/153/6.
Rejoinder, para. 84.
The Claimant also refers to the Decision of the Energy Charter Conference of 7 December 2000 recording the termination of certain transitional arrangements contained in Annex T by Armenia and Russia, noting that the decision does not suggest an understanding that, after the transitional arrangements were terminated, Russia would only apply in part the substantive obligations referred to in Article 32(1), since such a point would have been recorded.198 The Claimant sees further support for its interpretation of Article 45(1) in "the practice of the ECT Secretariat concerning transitional provisions in Article 32 in relation to, inter alia, Article 10(7) on non-discrimination."199
Rejoinder, para. 74, citing Decision of the Energy Charter Conference, CCDEC 2000, 14 NOT Brussels (7 December 2000) (Exhibit R-104).
Rejoinder, para. 74, citing European Commission, Communication from the Commission to the Council and the European Parliament on the signing and provisional application by the European Communities of the European Charter Treaty, COM(94) 405 final (21 September 1994) (Exhibit R-19).
The Claimant also rejects the Respondent's notion that the 1994 Joint EC Statement is relevant.201 Again turning to Hulley Enterprises, the Claimant argues that "[t]he [1994 Joint EC Statement] does not say, and cannot be read as meaning, that certain elements of the ECT will not be provisionally applied by the European Community because they are inconsistent with the Community's internal legal order."202 Rather, the Tribunal in Hulley Enterprises found that "the [1994 Joint EC Statement] concludes that the European Community can safely sign the ECT, and accept the obligation of provisional application, without taking on any obligation to do anything that is beyond its competence."203 Accordingly, the 1994 Joint EC Statement is "not so much an example of partial provisional application of the ECT due to inconsistency with the EC's legal order, as ... an example of the EC's partial jurisdiction for the provisional application of the whole ECT."204
Counter-Memorial, para. 94.
Counter-Memorial, para. 94, citing Hulley Enterprises, para. 327 (Exhibit CL-9).
Counter-Memorial, para. 94, citing Hulley Enterprises, para. 327 (Exhibit CL-9).
Counter-Memorial, para. 94, citing Hulley Enterprises, para. 327 (Exhibit CL-9).
See para. 72 above and Reply, para. 116.
See para. 144 below and Counter-Memorial, para. 116.
A number of the explanatory notes accompanying these treaties were put in evidence. The Respondent also referred to the texts of two of the treaties themselves, those between the USSR and the Netherlands (Exhibit RL-174) and between the Russian Federation and Denmark (Exhibit CL-78), both of which refer to the treaties entering into force on the completion of internal procedures: T2/194/2 – T2/195/17.
See para. 148 below and Counter-Memorial, paras. 111, 129.
Likewise, the Claimant contends that tribunals in investment treaty arbitrations also have required "express prohibition under domestic law" in their determination of whether an inconsistency exists between treaty provisions and domestic law.331 The Claimant refers to the decisions in Kardassopoulos,332 Achmea v. Slovak Republic333 ("Achmea"), Electrabel v. Hungary334 ("Electrabel"), and Khan Resources v. Mongolia335 as authority for this proposition. In other words, only where domestic law "forbids compliance" will the necessary inconsistency exist – a vacuum is not sufficient.336 With these decisions in mind, the Claimant argues that the "Respondent fails to put forward any case to establish that Russian law existing at the time of ECT signature forbade arbitration of investment disputes or required Respondent to modify existing legislation – i.e., that a conflict existed."337 The Claimant cites authority from the GATT context in support, arguing that it was not the case that the Russian Federation had "no choice but to violate the treaty."338 So, where domestic law offers only one form of recourse, but the treaty provides an alternative, then provisional application will enable the claimant to take advantage of the treaty procedure.339
Rejoinder, para. 97.
Rejoinder para. 97, citing Kardassopoulos, paras. 237, 245 (Exhibit CL-11).
T1/124/15-21, citing Eureko B.V. v. Poland, Partial Award (19 August 2005) (Exhibit RL-74); T5/159/8-12.
Rejoinder, para. 102.
T1/125/7-20, citing GATT ANALYTICAL INDEX: GUIDE TO GATT LAW AND PRACTICE ("GATT GUIDE") (Exhibit RL-139); T5/148/5 – T5/149/15.
T5/133/2-19.
See para. 72 above and Reply, para. 115.
In any event, the Claimant explains that, contrary to the Respondent's position, Article 23(2) recognizes that the termination of the provisional application of treaties operates by notification to other Contracting States, a fact that was also appreciated by the Respondent when it "communicat[ed] its termination of provisional application by a notification to the ECT depository on 20 August 2009."402 The Claimant provides authority for this proposition via references to Professor Stephan's first report,403 a note the Respondent submitted to the Secretariat of the ECT,404 and the Respondent's compliance with the ECT after the passage of the six-month period.405
Counter-Memorial, paras. 132-136, citing William E. Butler, "National Treaty Law and Practice: Russia," in NATIONAL TREATY LAW AND PRACTICE (Duncan B. Hollis, Merritt R. Blakesee, and L. Benjamin Ederington, eds., 2005), pp. 537, 545 (Exhibit CL-30).
Counter-Memorial, paras. 139-141, citing Stephan 1, paras. 74-75, 77.
Counter-Memorial, para. 137, citing Note on the Legal Aspects of Provisional Application of International Treaties in the Territory of the Russian Federation (8 July 1997); Energy Charter Secretariat, List of Participants in the Charter Conference (8 July 1997) (Exhibit C-148).
Counter-Memorial, paras. 143-144, citing Hulley Enterprises, para. 390 (Exhibit CL-9).
See para. 113 above and Reply, para. 164.
See para. 138 above and Reply, para. 187.
Did Russia's provisional application of the ECT "to the extent that such provisional application is not inconsistent with its constitution, laws or regulations" under the terms of Article 45(1) include its consent to international arbitration under Article 26(3)(a)?
Kardassopoulos, paras. 71, 73-74 (Exhibit CL-11); Hulley Enterprises (Exhibit CL-9); cf. Action nos C/09/477160 / HA ZA 15-1, C/09/477162 / HA ZA 15-2 and C/09/481619 / HA ZA 15-112 re: Hulley Enterprises Ltd/Yukos Universal Ltd (Isle of Man)/Veteran Petroleum Ltd (Cyprus) v. Russian Federation (20 April 2016) ("The Hague District Court Judgment").
(a) Section (b) analyses the proper interpretation of the regime of provisional application under Article 45 of the ECT in accordance with the general rule of interpretation set forth in Article 31(1) of the VCLT.
(b) Section (c) considers that regime against the background of the institution of provisional application in general international law (pursuant to Article 31(3)(c) of the VCLT).
(c) Section (d) examines relevant practice of the ECT States at the conclusion of the Treaty (Article 31(2)) and the preparatory materials for the Treaty (Article 32) as to the construction of Article 45.
(d) Section (e) considers the evidence as to Russian practice under the ECT.
(e) Section (f) addresses the extent to which Article 26 is "not inconsistent" with Russian law.
Although this Article has been set out earlier in this Decision, it is necessary to repeat the terms of its paragraphs (1)–(3) for clarity of the analysis that is to follow:430
Article 45—Provisional Application
(1) Each signatory agrees to apply this Treaty provisionally pending its entry into force for such signatory in accordance with Article 44, to the extent that such provisional application is not inconsistent with its constitution, laws or regulations.
(2) (a) Notwithstanding paragraph (1) any signatory may, when signing, deliver to the Depository a declaration that it is not able to accept provisional application. The obligation contained in paragraph (1) shall not apply to a signatory making such a declaration. Any such signatory may at any time withdraw that declaration by written notification to the Depository.
(b) Neither a signatory which makes a declaration in accordance with subparagraph (a) nor Investors of that signatory may claim the benefits of provisional application under paragraph (1).
(c) Notwithstanding subparagraph (a), any signatory making a declaration referred to in subparagraph (a) shall apply Part VII provisionally pending the entry into force of the Treaty for such signatory in accordance with Article 44, to the extent that such provisional application is not inconsistent with its laws or regulations.
(3) (a) Any signatory may terminate its provisional application of this Treaty by written notification to the Depository of its intention not to become a Contracting Party to the Treaty. Termination of provisional application for any signatory shall take effect upon the expiration of 60 days from the date on which such signatory's written notification is received by the Depository.
(b) In the event that a signatory terminates provisional application under subparagraph (a), the obligation of the signatory under paragraph (1) to apply Parts III and V with respect to any Investments made in its Area during such provisional application by Investors of other signatories shall nevertheless remain in effect with respect to those Investments for twenty years following the effective date of termination, except as otherwise provided in subparagraph (c).
(c) Subparagraph (b) shall not apply to any signatory listed in Annex PA. A signatory shall be removed from the list in Annex PA effective upon delivery to the Depository of its request therefor.